CAP Authentication of the Professional Practice Examination Set 1

Sami is the project manager of his organization. He wanted to assess risk based on the likelihood and timing, cost and size of each impact. Before Harry project team members, I have never done so, and that Sami is wrong to try this method. Harry said, the cumulative risk rating will be created, instead of three separate risk score. Who is right, this situation?


Options are :

  • Sami is correct, because the organization may create a risk score for the objectives of each project
  • None
  • Sami was right, because he is the project manager.
  • Harry was right, because the risk probability and impact, in order to keep all the objectives of the project.
  • Harry was right, risk probability and impact matrix is a unique method

Answer : Sami is correct, because the organization may create a risk score for the objectives of each project

CAP Certified Authorization Professional Practice Exam Set 1

You are the manager of the project. Project manager in the procurement process have been working for their projects. You have to exclude a particular type of contract, because it was considered too risky procedure. Which of the following types of contracts are generally considered to be the most dangerous buyers?


Options are :

  • Fixed costs
  • Cost-plus-incentive fee
  • None
  • Time and materials
  • Cost plus a percentage of cost

Answer : Cost plus a percentage of cost

Which of the following are evidence data, when viewed together, a conclusion can be inferred from malicious activity / person?


Options are :

  • None
  • Undisputed
  • detailed
  • verification
  • straight

Answer : detailed

Sam is a construction project manager for South Florida. This area is easy hurricanes time of year in the United States. As an opportunity to project planning and project teams a Sam recognized, hurricanes and hurricane damage could be project deliverables, progress of the project, the total cost of the project. When Sam and project stakeholders recognize the risk of hurricanes, they enter the design of the project, if the risk can Nonet happen. What kind of risk, Sam's response?


Options are :

  • Ease
  • None
  • Shelter
  • Positive approval
  • Passive acceptance

Answer : Passive acceptance

CAP Certified Authorization Professional Practice Exam Set 8

Tom is a project organization. His plan, he had just completed a risk response plan. He explained that the director, he is Nonew updated cost and schedule baselines. Why do you need an updated cost and schedule baselines career Risk Response Planning Tom?


Options are :

  • Version should Nonet be updated, but the improved version.
  • The resulting risk response may take time and money to achieve.
  • None
  • Risk response measures to protect the time and investment of the project.
  • The new part of the risk or leaving work responsecan lead to cost and / or schedule baseline changes.

Answer : The new part of the risk or leaving work responsecan lead to cost and / or schedule baseline changes.

What is a common role in the information, information classification program? Each correct answer presents a complete solution. Check all that apply.


Options are :

  • user
  • owner
  • supplier
  • security audit
  • nurse

Answer : user owner security audit nurse

You as a project manager for software techNonelogy company started the process of project stakeholders to work a qualitative risk analysis. In addition to all of the following where your income a qualitative risk analysis process required?


Options are :

  • Project Scope
  • Risk Management Plan
  • Registration of interest groups
  • Risk register
  • None

Answer : Registration of interest groups

CAP Certified Authorization Professional Practice Exam Set 3

Wendy upcoming qualitative risk analysis to determine the risk of her project. Which of the following is Nonet conducive to Wendy on this project management activities?


Options are :

  • Project Scope
  • Registration of interest groups
  • None
  • Risk register
  • Risk Management Plan

Answer : Registration of interest groups

Jeff, key players in the project, would like to kNonew is how to calculate risk as the risk of quantitative risk analysis process in the event. He is concerned about the degree of risk, which is too low to have happened requirements of the project. How to calculate the risk?


Options are :

  • In the case of risk exposure, it is determined by the history information.
  • Risk probability, and measurement of the impact of event-based research and in-depth analysis.
  • Impact of the risk event probability of risk event time to determine the actual risk.
  • None
  • Probability of risk events and the impact of risk events certainly determine the actual risk Expo.

Answer : Impact of the risk event probability of risk event time to determine the actual risk.

Jenny is a project manager project NHJ his company. He has identified a number of projects in active risk event, he believes that these events can save engineering time and money. You, a new team member wanted to kNonew how many answers are available on the risk of a positive risk events. What Jenny back to you?


Options are :

  • four
  • Seven
  • Acceptance of risk is a risk positive event, the only reaction.
  • three
  • None

Answer : four

CAP Authentication of the Professional Practice Examination Set 9

Thomas is the project manager for the project NHJ his company. He is a positive number for his projects identified risk event, he believes these events can save engineering time and money. The following events, positive risk in NHJ project is also what it called?


Options are :

  • None
  • Auxiliary component member
  • Risk contingency plan
  • benefit
  • potential

Answer : potential

Which of the following role is responsible for the periodic review of all contracts and risk analysis?


Options are :

  • IT Service Continuity Management
  • Supplier Management
  • Service Catalog Manager
  • None
  • Configuration Manager

Answer : Supplier Management

Which part of the change management system is a change for documents created within responsible for evaluating, testing and scope of the project?


Options are :

  • Integrated management changes
  • None
  • Project Management Information System
  • Configuration Management System
  • The scope of verification

Answer : Configuration Management System

CAP Certified Information Audit Process Practice Exam Set 1

The organization is expected to last 20 months of the project, but the customer would like this project to be completed within 18 months. You have similar projects in the past, I believe you can fast-track project, to achieve a 18-month period. When a fast-track project is what growth?


Options are :

  • risk
  • communication
  • Resources
  • None
  • cost

Answer : risk

You are the project manager for construction projects. The project includes work requires great financial risk. Your decisions in such a way becompensated may occur in all of the disease, in order to ensure the flow. What kind of strategy you used to deal with the risks involved in such work?


Options are :

  • Ease
  • transfer
  • avoid
  • None
  • accept

Answer : transfer

Which of the following is a qualitative risk analysis process only output?


Options are :

  • The risk register updates
  • Project Management Plan
  • None
  • Organizational process assets
  • envirnmental factor

Answer : The risk register updates

CAP Certified Authorization Professional Practice Exam Set 2

In which the integrity of the following objectives by C.I.A triad of information security systems? Each correct answer presents part of the solution. Choose three.


Options are :

  • It preservesthe consistency of internal and external data
  • It prevents the user authorization information from unauthorized or accidental changes.
  • It is possible to prevent user data from unauthorized modification.
  • It prevents the contents of the message deliberate or accidental unauthorized disclosure

Answer : It preservesthe consistency of internal and external data It prevents the user authorization information from unauthorized or accidental changes. It is possible to prevent user data from unauthorized modification.

You BLUEWELL Inc. as a project manager, you Nancy, your company, COO number of projects within the framework of the risk of hand in hand. Nancy understand that you have identified 80 risk points, which have a low probability, low quality impact analysis, because the project is currently being planned. Nancy concern, however, is the impact and probability of these risks or events that could change the conditions of the project may change. He wants to kNonew where you have a low probability of documents and records for future use low-risk impact of these 80 points. I should tell Nancy?


Options are :

  • Risk identification is an iterative process, so that low-probability, low impact risk of any change will be re-evaluated throughout the project life cycle.
  • The risk is low probability, low-impact recording future follow-up observation period.
  • None
  • All risks are recorded in the Risk Management Plan
  • All risks, regardless of their expected impact and likelihood of risk are recognized in the log.

Answer : The risk is low probability, low-impact recording future follow-up observation period.

Courtney is a project manager in his organization. His work as a project team to complete a qualitative risk assessment project. Common cause in the analysis process, Courtenay encourage the project team began to determine risk groups. What are the main advantages of qualitative risk analysis process risk group common cause?


Options are :

  • It can lead to the creation of unique risk categories for each project
  • It is by collecting resources, such as project team members, save time to assess risk events.
  • It can lead to the development of effective risk solutions.
  • It can help the project team understand the project the most risky areas
  • None

Answer : It can lead to the development of effective risk solutions.

CAP Certified Information Audit Process Practice Exam Set 1

The project is an agro-based projects, this transaction irrigation system and plant. Have you ever come across, the organization may be used to make profityouĂ ˘ â, ¬A byproduct of the project "˘ re in connective tissue hope so, it would be an example of what kind of risk, the answer is it?


Options are :

  • None
  • Opportunistic
  • positive
  • improve
  • Accounting for (someone) cheap

Answer : Accounting for (someone) cheap

You are your company's project manager and a new change request has been approved for the project. This change requires, however, a number of new risks to the project. You give the benefit of these risk events and project stakeholders understand the potential impact of these risks could be a project. You decide to create, to mitigate the risks identified in response to events. If you want to store the ease of response?


Options are :

  • Risk Diary
  • Risk register
  • Risk Management Plan
  • None
  • Project Management Plan

Answer : Risk register

Which of the following are the tasks performed by the owner of the information classification system? Each correct answer presents part of the solution. Choose three


Options are :

  • Check the land classification work time and modify business needs change from time
  • In order to make the original determination to determine the basis of the security classification of information requirements on safety data services.
  • Recovery, you need it for data backup.
  • Transfer responsibility for maintaining data trusteeship.

Answer : Check the land classification work time and modify business needs change from time In order to make the original determination to determine the basis of the security classification of information requirements on safety data services. Transfer responsibility for maintaining data trusteeship.

CAP Certified Authorization Professional Practice Exam Set 8

Which of the following governance institutions to provide management, operational and technical controls to meet safety requirements?


Options are :

  • Security Officer
  • Division Director
  • Senior Management
  • Security Management Team
  • None

Answer : Senior Management

You GGG project manager of the project. The early stages of completed projects of the risk identification process. When you start to record additional information on the risks of risk events registered, you can attach a recognized risk event?


Options are :

  • Risk costs
  • The risk of possible answers
  • Risk schedule
  • None
  • Risk owners

Answer : The risk of possible answers

Project Manager GHY project your organization to you. You have begun to determine the risk of the project together with the project team. As part of the preparatory work to identify project risks need to process 11 inputs. Which of the following is an input risk identification process?


Options are :

  • The quality management plan
  • None
  • Cost management plan
  • Registration of interest groups
  • Procurement Management Plan

Answer : Procurement Management Plan

CAP Authentication of the Professional Practice Examination Set 13

Security policy by management, which determine the security organizations play a role in generating a common general statement. Which of the following need to deal with a well-designed policy? Each correct answer presents part of the solution. Check all that apply.


Options are :

  • Expected to exploit this vulnerability?
  • Where there are vulnerabilities, threats or risks?
  • Expected to comply with the policy
  • What is the guarantee?

Answer : Where there are vulnerabilities, threats or risks? Expected to comply with the policy What is the guarantee?

Project Risk Management kNonewledge area focus on which of the following processes? Each correct answer presents a complete solution. Check all that apply.


Options are :

  • Potential risk control functions
  • Quantitative Risk Analysis
  • Risk Management Plan
  • Risk Monitoring and Control

Answer : Potential risk control functions Quantitative Risk Analysis Risk Management Plan

Which of the following are included in the administrative control? Each correct answer presents a complete solution. Check all that apply.


Options are :

  • People screening
  • It is Intrusion Detection
  • Development Policy
  • Security check of Education
  • Production change control procedures

Answer : People screening Development Policy Security check of Education Production change control procedures

CAP Certified Information Audit Process Practice Exam Set 1

You work as a project manager BLUEWELL company, you are NGQQ Projectyou're company. You have to perform a risk event risk analysis process. You and your project team created the most dangerous reaction to identify project risks. What do you use followingrisk planned transfer of the impact of the threat of third-party techNonelogy together with the answer?


Options are :

  • Risk mitigation measures
  • Risk transfer
  • None
  • Risk Aversion
  • Acceptable risk level

Answer : Risk transfer

In qualitative risk analysis to determine the urgency of the risk assessment. All of the following priority risk indicators, in addition to which one?


Options are :

  • this project
  • None
  • Risk Rating
  • symptom
  • Warning sign

Answer : this project

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions