Blue Prism Certified Developer - Mock Test Set 1

Study the following image showing part of the flow within an Object Studio action:

What problem do you see with the process flow?


Options are :

  • The Retry Limit data item is set to 10 when it should always be set to 3.
  • There is a missing Recover Stage on one of the routes through the flow.
  • There is a missing Resume Stage on one of the routes through the flow.
  • There is a missing link from the "Missing Elements?" choice stage.

Answer :There is a missing Resume Stage on one of the routes through the flow.

Blue Prism Developer Certification AD01- Exam Dumps Set 5

Examine the following process flow:

The Loop Orders loop is configured to loop through the Orders collection.

How many times will the ‘Process Order' page be executed?


Options are :

  • 1
  • 15
  • The loop will be infinite
  • It's impossible to tell. There is no loop counter.

Answer :15

Study the following page in a process:

Calculation stages will write A, B or C to the Output value data item.

What will be the outcome after the page has run?


Options are :

  • Data Item Output Value contains "A"
  • Data Item Output Value contains "B"
  • Data Item Output Value contains "C"
  • An Internal Exception will be thrown

Answer :An Internal Exception will be thrown

Study the following configuration:

Which of the following statements is correct?


Options are :

  • When the configuration is run in Control Room, it will become stuck in an infinite loop
  • When the configuration is run in Control Room, it will become stuck in an infinite loop until the ‘Switch' Session Variable is changed to True in System Manager
  • When the configuration is run in Control Room, it will become stuck in an infinite loop until the ‘Switch' Session Variable is changed to True in the Control Room
  • When the configuration is run in Control Room, it will fail with an internal error on the first execution of the ‘Switch?' stage with the error: Decision did not result in a yes/no answer

Answer :When the configuration is run in Control Room, it will become stuck in an infinite loop until the ‘Switch' Session Variable is changed to True in the Control Room

Blue Prism Developer Certification AD01- Exam Dumps Set 4

Consider the following flow in an object:

Which of the following statements are true?


Options are :

  • There just needs to be a wait stage after the start stage to correct this action.
  • There should be a wait stage after every stage in this flow (i.e. after the navigate, read, write stages)
  • If during testing in object studio this flow works no additional wait stages should be added as they will slow the interface down.
  • There should be an intelligent wait stage after the start stage and after any stage that cause the application we are interfacing with to change

Answer :There should be an intelligent wait stage after the start stage and after any stage that cause the application we are interfacing with to change

There should be an intelligent wait stage after the start stage and after any stage that cause the application we are interfacing with to change


Options are :

  • It is common for duplicate elements to be found based upon the attributes that are ticked by default using the Blue Prism product. Time needs to be spent experimenting with the attribute ticks until a unique, reliable, and consistent selection of attributes are found.
  • It will not be possible to interface with the element in a unique way. You will need to use Surface Automation techniques for this element.
  • A code stage interface will need to be created and used for this application, this will give you more flexibility to interact with the application elements.
  • You will need to make the attributes you have selected dynamic. This will allow your flow to loop around, incrementing the attribute value until the correct element is found and used.

Answer :It is common for duplicate elements to be found based upon the attributes that are ticked by default using the Blue Prism product. Time needs to be spent experimenting with the attribute ticks until a unique, reliable, and consistent selection of attributes are found.

Which of the following statements about Business Objects is true?


Options are :

  • It is Blue Prism best practice to include business rules within Business Objects
  • A Business Object is configured in the Studio area of Blue Prism
  • A Business Object can be exposed to Control Room
  • Logging of individual stages is not configurable in Business Objects

Answer :A Business Object is configured in the Studio area of Blue Prism

Blue Prism Certified Developer - Mock Test Set 3

A Blue Prism solution works fine when developing and testing it in Process and Object studio but when it is ran in Control Room exceptions occur because of screen elements not being found.

What is the most likely cause?


Options are :

  • The most likely cause for the errors is that your application has changed.
  • The most likely cause for the errors seen in Control Room is that best practice use of wait stages has not been followed.
  • The most likely cause for the errors is that the Object Studio action has not been published and therefore cannot be used by the Process in control room.
  • The most likely cause for the exceptions is that best practice exception handling has not been incorporated into the Process.

Answer :The most likely cause for the errors seen in Control Room is that best practice use of wait stages has not been followed.

The Order System application has been successfully launched and Blue Prism has navigated the application to the following screen:

There is a requirement to ensure this screen is in focus before any further interfacing is done with the screen. Which is the correct configuration to ensure the New Order screen is in focus?

A)

B)

C)

D)


Options are :

  • Order System - Activate Application
  • Order System - Attach
  • New Order Window - Click Window
  • New Order Window - Activate Application

Answer :New Order Window - Activate Application

When automating a Windows application what type of stage is configured to perform a Global Send Key Events?


Options are :

  • Notes Stage
  • Navigate Stage
  • Read Stage
  • Write Stage

Answer :Navigate Stage

Blue Prism Developer Certification AD01- Exam Dumps Set 1

When configuring an object's run model which of the following is true?


Options are :

  • Setting the run model to foreground will give the object priority over the target system ahead of any other Business Object.
  • Leaving the run mode blank will allow any number of processes and objects to run at the same time on the same resource.
  • Setting the run mode to exclusive will ensure only one process runs on that resource at a time.
  • Setting the run mode to background will enable the object to run at the same time as foreground and background objects on the same resource.

Answer :Setting the run mode to background will enable the object to run at the same time as foreground and background objects on the same resource.

Examine the process flow:

The Process is intended to attempt to perform the processing in the recover block, Block 3, a maximum of three times before throwing an exception.

Data Item "Attempts" is a number data item with an initial value of 0

Data Item "Max Attempts" is a number data item with an initial value of 3

The ‘Increment Attempts' calculation stage outputs a result to the "Attempts" data item

To enable this to work correctly, what is the correct expressions for the ‘Increment Attempts' calculation stage?


Options are :

  • +1
  • [Max] + 1
  • [Attempts] + 1
  • Attempts + 1

Answer :[Attempts] + 1

If you can change a session variable when will the new value be available to the process?


Options are :

  • Next time a new case is taken from a Work Queue
  • Next time resource PC starts
  • Next time the process starts
  • Immediately

Answer :Immediately

BluePrism Developer Certification (AD01) - Practice Tests Set 3

When a process is running in Control Room which of the following functions within the process can be accessed from Control Room to request the process to stop?


Options are :

  • Stop ()
  • IsStopRequested?
  • IsStopRequested ()
  • IsStopRequested {}
  • StopNow ()

Answer :IsStopRequested ()

An action called ‘Get Account details' fails with the following exception detail:

Which of the following could cause this exception?


Options are :

  • An internal error always indicates a problem with the Blue Prism product. The Blue Prism support team should be contacted for assistance.
  • The Read Details action is not connected to another stage so cannot execute.
  • The Business Object has not been coupled to the application by either launching it or attaching to it.
  • The Read Details action in the Get Account Details Business Object no longer exists but the Process is attempting to use it.

Answer :The Business Object has not been coupled to the application by either launching it or attaching to it.

Which of the following flows can you not create in Blue Prism? (select 2 responses)


Options are :

  • Option A
  • Option B
  • Option C
  • Option D

Answer :Option A Option B

Blue Prism Developer Certification AD01- Exam Dumps Set 4

Look at this flow diagram from the Main Page of a process in Process Studio:

Thinking about the standard Blue Prism Process Templates, what is wrong with how this Main Page is handling exceptions?


Options are :

  • There is nothing wrong with the Main Page flow shown in the image, it is a copy of Blue Prism's standard Process Template.
  • It would be better to remove the Exception Block and recover, resume logic, and instead handle any exceptions in the sub-pages. Flag data items could instead be passed up as output parameters from the sub-pages informing the Main Page flow if an exception has occurred.
  • Between the Recover and Resume stages there should be logic to reset the application ready for the next case to be worked. For example, this could call the Close Down and Start Up pages.
  • The Exception Block in the image should be extended to cover all stages in the flow rather than just 4 sub-pages.
  • The exception handling in the image does not contain any concurrent exception logic. This means there is nothing stopping every item in the Work Queue being marked with the exact same System Exception.

Answer :There is nothing wrong with the Main Page flow shown in the image, it is a copy of Blue Prism's standard Process Template.

Consider the following process flow from a sub-page of a process:

What is wrong with the flow shown in the image?


Options are :

  • Sub-pages should not have retry logic, exception handling should be in the object level rather than in the process.
  • The resume stage must also be within the exception block
  • The retry loop logic does not include any navigation after the resume stage to ensure the application is ready to try the ‘Search Screen ?EPerform Search' action again.
  • The retry loop logic shown in the image is incorrect because it uses multiple action stages. There should be a retry loop around every action.

Answer :The retry loop logic does not include any navigation after the resume stage to ensure the application is ready to try the ‘Search Screen ?EPerform Search' action again.

Consider the following flow within an Object Studio action:

The developer of this flow found that writing some credentials to the target application sometimes failed with an exception even though the element exists on the screen. He found that simply catching the exception, waiting for 2 seconds and then retrying fixed the problem.

What problems do you see within the flow? (select 2 responses)


Options are :

  • A block has not been placed around the Write stage and the Recover stage, meaning the credentials action could be unnecessarily retried if another stage further into this action throws an exception.
  • There is a potential for an infinite loop if the ‘Credentials' stage keeps throwing an exception for some unforeseen reason.
  • The credentials stage is a read stage not a write stage.
  • There is not a Resume stage following the timeout of the Wait stage

Answer :A block has not been placed around the Write stage and the Recover stage, meaning the credentials action could be unnecessarily retried if another stage further into this action throws an exception. There is a potential for an infinite loop if the ‘Credentials' stage keeps throwing an exception for some unforeseen reason.

BluePrism Developer Certification (AD01) - Practice Tests Set 3

Consider the following diagram from an object studio action:

What is the problem with this flow?


Options are :

  • There is a risk of the flow causing an infinite loop.
  • There should be a wait stage at the end of the flow, before the end stage to ensure the flow logic has worked correctly.
  • There is nothing wrong with the object flow shown in this image.
  • The Exception Block should be removed from the page so that all exceptions on that page can be recovered.

Answer :There is a risk of the flow causing an infinite loop.

A process has been created but it is not listed in Control Room. The following reasons have been suggested.

1. The process uses objects with different run modes

2. The process has not been published

3. Process validation shows more than 99 errors

4. The user does not have privileges to run processes in Control Room

Which of the above could cause the process not to be visible in Control Room?


Options are :

  • 1 and 2
  • 1 and 2
  • 1 and 4
  • 2 only

Answer :2 only

When designing a Blue Prism solution a Blue Prism architect must respect the requirement that no customer data is visible within the Blue Prism database.

Consider these possible design alternatives;

1. No customer data in the work queue

2. Encrypt the data in the work queue

3. Switch off all stage parameter logging

Which combination of the above will guarantee that no customer data is visible in the Blue Prism log file?


Options are :

  • 1 only
  • 1 and 3
  • 2 and 3
  • NONE

Answer :2 and 3

Blue Prism Certified Developer - Mock Test Set 2

When building a solution to use Tags within a Work Queue, which of the following statements is correct true?


Options are :

  • Adding a tag requires an item to be locked
  • Adding a tag requires an item to be locked if there are multiple resources working the same queue
  • Adding a tag does not require an item to be locked

Answer :Adding a tag does not require an item to be locked

According to Blue Prism best practice which of the following information would be appropriate to store in a Work Queue tag? (select 3 responses)


Options are :

  • Something that identifies the type of work that was performed. Example tags might be: Funds Transferred, SIM Card Requested, Account Closed, Account Suspended, Account Noted
  • Something that identifies exact datetime of a step in the process. Example of tags might include: Account Closed 20/03/2017 12:12:16, Work Completed 20/03/2017 12:12:16, Request Loaded 20/03/2017 12:12:16
  • Something that identifies the source of work. Example of tags might include: Email, Web Form, Excel, Adhoc, Database
  • Something that identifies the client record to make work queue items easier to search. Example tags might be a phone number, customer reference number or ID, customer full name. For example: +4407994446767, 00023231A, Mr John A Smith.
  • Something that identifies the type of process scenario. Example of tags might include: Invalid Product, Unrecognized customer, Gone away Marker, Invalid Status
  • Details of an exception that has occurred. For example: The Login Screen was not found.

Answer :Something that identifies the type of work that was performed. Example tags might be: Funds Transferred, SIM Card Requested, Account Closed, Account Suspended, Account Noted Something that identifies the source of work. Example of tags might include: Email, Web Form, Excel, Adhoc, Database Something that identifies the type of process scenario. Example of tags might include: Invalid Product, Unrecognized customer, Gone away Marker, Invalid Status

A Process Definition Document(PDD) should achieve which of the following?


Options are :

  • Inform the Blue Prism developer how to structure their process within Process Studio
  • Outline the risks of robotic automation on the host systems
  • To describe how a process will be automated using Blue Prism
  • Provide a highly detailed description of every step required to perform the manual process

Answer :Provide a highly detailed description of every step required to perform the manual process

Blue Prism Certified Developer - Mock Test Set 3

What is correct sequence for delivery documents to be created?


Options are :

  • SDD, IPA, ODI
  • PDI, ODI, SDD
  • PDD, OID, ODI
  • PDD, IPA, OID

Answer :PDD, OID, ODI

Which part of Blue Prism interacts with the target system (the application a user would use)?


Options are :

  • Control Room
  • Process Studio
  • Application Modeller
  • Object Studio

Answer :Application Modeller

In which area of Blue Prism would you monitor the contents of a Work Queue?


Options are :

  • Object Studio
  • Process Studio
  • Control Room
  • System Manager

Answer :Control Room

Blue Prism Developer Certification AD01- Exam Dumps Set 2

A process is required to get data from a file. The Developer puts the file in the C:\Temp folder and uses a data item to hold the file path. In the Live environment however, the file is located in a network folder and Blue Prism is locked down so that processes cannot be edited.

How could the data item ‘exposure' be set so that the process could read the file location on start up in either environment?


Options are :

  • None
  • Statistic
  • Session
  • Environment

Answer :Environment

Which of these phrases best describes what Blue Prism is used for?


Options are :

  • Blue Prism is used for modelling business processes
  • Blue Prism is used to create virtual robots that can replicate user actions and decisions
  • Blue Prism is used to transfer data from one system to another
  • Blue Prism is used to link core business application together

Answer :Blue Prism is used to create virtual robots that can replicate user actions and decisions

How many Resume Stages can a Process have?


Options are :

  • 0, only Object Studio can have Resume Stages
  • 1 Only
  • The same number as the number of Recover Stages in the Process
  • Maximum 2 only
  • Any Number

Answer :Any Number

Blue Prism Developer Certification AD01- Exam Dumps Set 6

A screen contains two buttons, Cases and Logout. When the buttons are spied, the attributes are identical except for the Window Text attribute.

The values for the Window Text attribute are "Cases" for the Cases button and 'Logout' for the Logout button.

The Button to Select element has been spied and has the following attributes set:

A navigate stage has been configured to press the cases button:

What additional configuration is required to ensure the cases button is selected by the navigation stage?


Options are :

  • The Params button must be selected and the parameter configured to override the Window Text attribute to 'cases'.
  • None. The value 'cases' is already selected in Application Modeller.
  • A new element is required with the Window Text value set to 'cases' and the Match Type set to equal.
  • It is not possible to select the button with a navigate stage.

Answer :The Params button must be selected and the parameter configured to override the Window Text attribute to 'cases'.

Which of the following best describes a System Exception?


Options are :

  • A case that was being processed when the process failed.
  • A case made an exception by the process because it is outside of the current process scope.
  • A case that need to be manually reviewed by the Business.
  • A case that cannot be completed due to unexpected system responses/issues.

Answer :A case that cannot be completed due to unexpected system responses/issues.

To run a Blue Prism process on Virtual Robot you would access;


Options are :

  • Control Room
  • Process Studio
  • System Manager
  • Object Studio

Answer :Control Room

Blue Prism Developer Certification AD01- Exam Dumps Set 6

Which of the following statements is true when employing multiple objects in the object layer?


Options are :

  • Reduces the number of developers who can work concurrently on the Object Layer
  • Makes a Process run faster
  • Creates a smaller Application Modeller
  • Increases the risk to the Process Layer when changes is made in the Object Layer

Answer :Creates a smaller Application Modeller

Which of the following can you perform in System -> Workflow area of Blue Prism? (select all that apply)


Options are :

  • Refresh a Work Queue
  • Create a Work Queue
  • Encrypt a Work Queue
  • View the contents of a Work Queue

Answer :Create a Work Queue Encrypt a Work Queue

How can an environment variable value be updated? (select all that apply)


Options are :

  • By using the Internal - Environment Variables business object
  • By changing the Blue Prism Server configuration
  • By updating the value in Control Room
  • By updating the value in Credential Manager
  • By updating the value in System Manager

Answer :By updating the value in System Manager

BluePrism Developer Certification (AD01) - Practice Tests Set 1

When considering an element's attributes in Application Modeller which of the following statements are true? (select all that apply)


Options are :

  • The attributes are provided to Blue Prism by the Target System
  • The initial selection of attributes made by Blue Prism will always be the optimum attribute set for the element
  • The list of attributes may vary from application type to application type
  • Selected attributes are shown as ticks in the Match column of Application Modeller

Answer :The attributes are provided to Blue Prism by the Target System The list of attributes may vary from application type to application type Selected attributes are shown as ticks in the Match column of Application Modeller

Which of the following Stages can be found in both Process Studio and Object Studio?


Options are :

  • Option A)
  • Option B)
  • Option C)
  • Option D)

Answer :Option C)

Study the following image showing pan: of the flow within a process:

What problems do you see with the process flow? (Select 2 responses)


Options are :

  • There is a missing Recover stage on one of the routes through the flow.
  • There is a missing Resume stage on one of the routes through the flow.
  • If an exception is thrown in the Cancel Reservation page and is allowed to bubble up to be caught by the Recover stage, the Create Reservation action won't be retried.
  • The Retry Count is not being incremented for each retry.

Answer :If an exception is thrown in the Cancel Reservation page and is allowed to bubble up to be caught by the Recover stage, the Create Reservation action won't be retried. The Retry Count is not being incremented for each retry.

Blue Prism Certified Developer - Mock Test Set 1

A screen contains four buttons, Find, Save, Close and New. When the buttons are spied, the attributes are identical except for the Window Text attribute. The values for the Windows Text attribute are Find' for the Find button. 'Save' for the Save button, Close' for the Close button and New' for the New Button.

The Dynamic Button element has been spied and has the following attributes set:

What additional configuration is required to ensure the Close button is selected by the Navigate stage?


Options are :

  • Set the Mouse Button value to 'Close'
  • The Params button must be selected and the parameter configured to override the Window Text attribute value to 'Close'
  • It is not possible to select the Close button using the Dynamic Button element because the value is set to 'Find in the Application Modeller
  • A new element is required with the Window Text value set to "Close and the Match Type set to equal

Answer :The Params button must be selected and the parameter configured to override the Window Text attribute value to 'Close'

Consider the following process flow from a sub-page of a process:

What is the problem with this sub-page flow?


Options are :

  • There is nothing wrong with the sub-page flow shown in this image
  • The sub-page process flow is missing any retry exception handling that should exist where a process calls object actions that interface with an application.
  • For better visibility of the process logic the flow steps shown in the image should be on the main page rather than in a sub-page of the process
  • The exception stage within the flow should be removed and replaced with an End stage that returns the found data item as an output parameter

Answer :There is nothing wrong with the sub-page flow shown in this image

Which of the following tools can be used to spy the mainframe applications?


Options are :

  • Grid Tool
  • Spy++
  • Active Accessibility API
  • Java Access Bridge

Answer :Grid Tool

What is the default port of Blue Prism ResourcePc?


Options are :

  • 8000
  • 8081
  • 8100
  • 8181

Answer :8181

Which of the following Methods is not used to read the PDF text documents which was created using Microsoft Word or Adobe Acrobat?


Options are :

  • Using the Adobe Acrobat API
  • Using Windows Clipboard
  • Saving PDF as XML or Word
  • OCR Engine

Answer :OCR Engine