SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 6

Final assembly takes place in three work centers, one after the other. Routing, which consists of three related functions (10, 20, 30), plan a given BOM component can be mounted during the use of 30 rather than before it. The component should, therefore, just ask at the start of operation of 30. What order do you keep track of master data maintenance in SAP to make this part of the available activities during final assembly line?


Options are :

  • 1. Create a BOM 2. Create workstations 3. Create a routing 4. Run component or task Bom routing (Correct)
  • 1. Create a BOM 2. Create workstations 3. Create a routing 4. Execute the center of the work of the component
  • 1. Create workstations 2. Create a routing BOM 3. Create 4. Execute the center of the work of the component
  • None
  • 1. Create a routing 2. Create workstations 3. Create a BOM component 4. Run the task Bom or routing

Answer : 1. Create a BOM 2. Create workstations 3. Create a routing 4. Run component or task Bom routing

SAP C_TSCM66_66 Certified Associate Logistics Execution Exam Set 2

Which settings you can offer the user to manage the SAP system costs (cost accounting and settlement) in terms of orders? (Choose two.)


Options are :

  • Product price collectibles (Correct)
  • A series of cost accounting
  • In order costing (Correct)
  • Work center costing

Answer : Product price collectibles In order costing

Which of the following is necessary to check the ability to be carried out automatically when the production order is released?


Options are :

  • None
  • Activate availability check and specify the check control factory.
  • Activate availability check and determine the overall profile in check control business function, the degree of release. (Correct)
  • Activate availability check and determine the checking rule Work Center for the activities reviewed.
  • Activate the scan and determine the availability checking the availability of the material master group of the product can be prepared.

Answer : Activate availability check and determine the overall profile in check control business function, the degree of release.

The customer wants to produce a finished product when the customer orders it is present. The final assembly should then be implemented at short notice, make an order production. Until now, the important configurations required for final assembly should already be available in stock. The provision of these assemblies would trigger the design. What would you give the customer options useful options SAP ECC? (Choose two.)


Options are :

  • The finished product is using a strategy 20 (make-to-order production) and all the important configurations of the bill of material of the final product should be a strategy 70 (Planning Assembly level). (Correct)
  • The finished product is using a strategy 50 (Planning without final assembly) and all configurations of the bill of material of the end product is not a strategy. (Correct)
  • The finished product is using a strategy 30 (production lot) and all the important configurations of the bill of material of the final product should be a strategy 70 (Planning Assembly level).
  • The final product is using a strategy 40 (design and final assembly) and all the important configurations of the material decline in the finished product should be a strategy 70 (Planning is an assembly level).

Answer : The finished product is using a strategy 20 (make-to-order production) and all the important configurations of the bill of material of the final product should be a strategy 70 (Planning Assembly level). The finished product is using a strategy 50 (Planning without final assembly) and all configurations of the bill of material of the end product is not a strategy.

Wherein the order of individual steps in designing a material that is carried out in SAP?


Options are :

  • 1. Calculation of the safety stock2. The application of batch sizing procedure 3. Timing 4. Determination of the acquisition type
  • 1. Balance Amendment 2. The application of batch sizing procedure3. 4. Determination of the type of acquisition timing
  • 1. Net Requirements Calculation 2. The application of batch sizing procedure 3. Timing 4. Determination of the acquisition type
  • 1. Net Requirements Calculation 2. The application of batch sizing procedure 3. Determination of procurementtype 4. Timing (Correct)
  • None

Answer : 1. Net Requirements Calculation 2. The application of batch sizing procedure 3. Determination of procurementtype 4. Timing

What is offered the following Areas MRP (Material Requirements Planning Areas)? (Choose two.)


Options are :

  • Make your subscription supports the production storage location MRP areas.
  • MRP, may include different memory locations. (Correct)
  • The preset can be given different MRP areas.
  • Subcontracting supports the MRP areas. (Correct)

Answer : MRP, may include different memory locations. Subcontracting supports the MRP areas.

The company is based in the United States to produce the final product, which is used as a unit of measurement "pounds" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold in kilograms (KG). Which of the following SAP solutions can not offer?


Options are :

  • None
  • Creating a new material, which refers to the original material and provides a metric unit of measurement of a host of new material.
  • There is no need to take any action. It is a common conversion central customizing, units for the automatic conversion of pounds pounds occurs. (Correct)
  • Material host, create a conversion factor to convert pounds kilograms of basic view 1.
  • In the basic customization, you create a unit of measure group that convert pounds to kilograms. Then transfer this material to master basic view 1.

Answer : There is no need to take any action. It is a common conversion central customizing, units for the automatic conversion of pounds pounds occurs.

SAP C_TSCM66_66 Certified Associate Logistics Execution Exam Set 3

Your company, design strategy is used the SAP, which allows the common design for all MRP schedule configurations of the final product to trigger the acquisition of these configurations. It is important to ensure that the end product is formed only when the customer's order is present. When a customer order is received, the production of the finished product should go make an order in the form of design and production. Every design strategy covers this scenario?


Options are :

  • Planning with final assembly (strategy 40)
  • The design is assembly level (strategy 70)
  • Planning without final assembly (strategy 50) (Correct)
  • None
  • Design of make-to-stock (strategy 10)

Answer : Planning without final assembly (strategy 50)

In the task list, will have the opportunity to work with suboperations. What you can do in more detail using suboperations? (Choose two.)


Options are :

  • scheduling
  • capacity Planning (Correct)
  • Material component allocation
  • pay (Correct)

Answer : capacity Planning pay

The company wants to use SAP requirements planning, together with the procedure NETPL (net change planning in planning horizon). The planning horizon is given equally to all media by default. However, some materials must be given a different design cycle. What procedure would you recommend the project team to set the planning horizon of the system?


Options are :

  • None
  • Planning horizon is set using the adaptation of the plant option and variant parameters specified in entries via MRP materials groups. (Correct)
  • Planning horizon is set at the factory and adjustment of parameters variant entries are stored in the material master materials.
  • The planning horizon is located on the MRP defined in Customizing variant groups and entries through the factory parameter settings.
  • The planning horizon is located in the MRP from the adaptation and variation values are stored in the material masters materials in question.

Answer : Planning horizon is set using the adaptation of the plant option and variant parameters specified in entries via MRP materials groups.

Master data of in-house production process is established by the SAP system. To do this, you should create the appropriate routing, which plans to begin operation of a five-order (10, 20, 30, 40, 50). There should be a possibility to relocate their activities 30 and other workstations 40 second sequence if capacity bottlenecks. In what order would you use to create the type of the second period in the system?


Options are :

  • standard order
  • substitute sequence
  • None
  • An alternative sequence (Correct)
  • parallel sequence

Answer : An alternative sequence

Where the production characteristics can no longer be carried out after the order is released?


Options are :

  • Switching sequences. (Correct)
  • The posting of the goods receipt from production to storage.
  • Read PP master data.
  • None
  • The posting of the goods issue stock for the production order.

Answer : Switching sequences.

During the project the customer raises questions concerning the parameters of the type of acquisition in the material master in SAP ECC system. Which of the following type of contracts relating to the characteristics? (Choose two.)


Options are :

  • Procurement types E (own production) and F (external procurement) need to be finalized special procurement types.
  • If Procurement type E (own production) has been set, the external procurement may still be allowed. (Correct)
  • If both procurement types are permitted entry requirements X design is based on inhouse production. (Correct)
  • Material supply type can always choose freely between the E (in-house production), F (external supply) and X (the two types of supply).

Answer : If Procurement type E (own production) has been set, the external procurement may still be allowed. If both procurement types are permitted entry requirements X design is based on inhouse production.

SAP C_TBIT44_71 Development Consultant Net Weaver Exam Set 3

The customer has used the design strategies 30 (Production lots) and 10 (unnamed make-to-stock production) SAP. The customer wants to move part of its strategy 40 (design and final assembly). Question consumption affects here for the first time. What characteristics apply for the consumption of its strategy 40? (Choose two.)


Options are :

  • Consumption may lead later in the specification and design of the control elements by means of the amount and date, the customer orders that arrive (Correct)
  • onsumption creates static and binding function, namely, the planned independent requirements entered in advance and the customer's requirements, which arrive, the entire procurement process.
  • Consumption may result in an increase originally volume of total output. (Correct)
  • Consumption can reduce the initial production volume.

Answer : Consumption may lead later in the specification and design of the control elements by means of the amount and date, the customer orders that arrive Consumption may result in an increase originally volume of total output.

Which operations process your order you can fill in Good Manufacturing Practices (GMP) standard? (Choose three.)


Options are :

  • Digital signature (Correct)
  • batch record (Correct)
  • Identifying and reconciliation Material (Correct)
  • Availability check

Answer : Digital signature batch record Identifying and reconciliation Material

Which works would reduce the capacity requirement for the individual to work the middle of a book? (Choose three.)


Options are :

  • Posting goods receipt for the production order
  • A restructuring operation
  • By reducing the amount of the order (Correct)
  • confirming the operation (Correct)
  • By setting the status technically completed (TECO) (Correct)

Answer : By reducing the amount of the order confirming the operation By setting the status technically completed (TECO)

SAP ECC, you can calculate the available standard capacity of a work center capacity the following information: start: 7:00:00, head. 3:00:00 p.m., the pause duration: 1 hour, duty cycle: 80%, overload. 110%, the number of individuals: 1. How large is the standard available capacity?


Options are :

  • 7 hours
  • 8 hours
  • 6.16 hours
  • None
  • 5.6 hours (Correct)

Answer : 5.6 hours

Which of the following statements ATP (available to promise) to ensure the material components are correctly? (Choose two.)


Options are :

  • ATP checks can be carried out automatically, when the release of the production order. (Correct)
  • ATP checks can also be adjusted to consider the demands of the future and receipts. (Correct)
  • ATP checks will be used to evaluate the free capacity in a particular work center.
  • ATP checks are performed automatically in connection with the MRP (material requirements planning) passes.

Answer : ATP checks can be carried out automatically, when the release of the production order. ATP checks can also be adjusted to consider the demands of the future and receipts.

Which of the following statements is true simulation of the state of connection with the material requirements planning in SAP ECC?


Options are :

  • None
  • Assuming the delay time of the critical path, the simulation mode is triggered by a bottom-up level of the timing of the finished product, which thus receives the delayed receipt.
  • Simulation mode represents an interactive multi-level shape design, the result of which is automatically posted to the database when the planning run.
  • Simulation mode opens the analysis of the delay. Manual reorganization within the final product and the design of the following requirements will lead to a solution that is feasible requirements for the design point of view. However, this solution can result in date / time violation in the final product. (Correct)
  • Simulation mode is used in situations where the requirements of the design created a procurement element prematurely in terms of demand.

Answer : Simulation mode opens the analysis of the delay. Manual reorganization within the final product and the design of the following requirements will lead to a solution that is feasible requirements for the design point of view. However, this solution can result in date / time violation in the final product.

SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 1

Which of the following scheduling types can not set the default order type (production order)?


Options are :

  • Forward
  • None
  • Only capacity requirements
  • Backwards
  • midpoint (Correct)

Answer : midpoint

The material was designed in connection with the SAP material requirements planning and MRP controller further processed material manually by changing the order of certain of the proposed production order. MRP now controller accesses the storage status / a list of requirements and MRP list substance and compares the two. Which of the following conditions applies to the two lists at this point? (Choose two.)


Options are :

  • MRP list status is "processed".
  • Stocks / requirements list updated on the exact date it was opened. (Correct)
  • Stocks / requirements list displays the production order. (Correct)
  • The MRP list shows the production order.

Answer : Stocks / requirements list updated on the exact date it was opened. Stocks / requirements list displays the production order.

SAP system, a material is produced by means of production orders. Although originally used for interest-based design only, the design of the table is used to design this material. On the Home screen planning table, choose this material, and then see a message informing you that you can use in the design table to this material. Which one of the following reasons, this message about?


Options are :

  • None
  • Serial production indicator has not been set.
  • There are no planned orders or production orders presence.
  • There are not any requirements of the present.
  • There is no valid production version of this material. (Correct)

Answer : There is no valid production version of this material.

Master data stored in the logistics process is the SAP system. In this context, you will need later production versions of the design and production. You know the mass maintenance event that you can use here. Where else in the SAP could be defined as production versions?


Options are :

  • The line routing.
  • The work center.
  • Material host. (Correct)
  • None
  • There is a recurring Editing Manufacturing

Answer : Material host.

Which of the following efforts can be minimized by using the KANBAN procedure?


Options are :

  • Effort sales and operations planning (SOP)
  • The master data maintenance effort
  • Organizational effort for capacity planning
  • Organizational effort to phase material (Correct)
  • None

Answer : Organizational effort to phase material

Which of the following possible errors would lead to a visible message? (Choose two.)


Options are :

  • Material Master (product) is set to manual routing selection and valid routing exists.
  • The application of the order type is selected in manual routing selection and a valid routing exists.
  • Material master, plan selection set production version. The production version has been created and it is defective. (Correct)
  • There are no valid routings or routings not available by the explosion. (Correct)

Answer : Material master, plan selection set production version. The production version has been created and it is defective. There are no valid routings or routings not available by the explosion.

SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 5

The new material has the following properties are important SAP. material is kept in stock is externally acquired, and bills of material are used as component a variety of end products. This material may not be purchased directly. What standard SAP type of material you use?


Options are :

  • None
  • HAWA (trading good)
  • ROH (raw material) (Correct)
  • NLAG (non-raw material)
  • FERT (finished product)

Answer : ROH (raw material)

Which of the following master data you need to always make available material replenishment using KANBAN procedure? (Choose two.)


Options are :

  • Rate routings
  • Product price Collector
  • Production, distribution areas (Correct)
  • control cycles (Correct)

Answer : Production, distribution areas control cycles

What are the selection of routing options exists when creating a production order? (Choose three.)


Options are :

  • Automatic selection, controlled settings Editing (Correct)
  • Selection on the basis of production control profile (Correct)
  • Selection on the basis of the routing number for the production of material of the master material,
  • manual selection (Correct)

Answer : Automatic selection, controlled settings Editing Selection on the basis of production control profile manual selection

Year client project, you are confronted with SAP ECC, the error message is displayed below the 1000. A large number of test design tool plant materials is already available in the plant 1000. In the first step in solving a problem, activated by the requirements of the adaptation of urban planning plants 1000. What further action has been take before you can put the design tool plant in 1000 introduction of SAP ECC?


Options are :

  • - Activate the requirements of the design value adjustment of MRP areas of a plant 1000 to set parameters for the plant design requirement of plants 1000 views
  • - Implement theplanning files Customizing- to set parameters for the plant design requirement of plants 1000 views
  • None
  • - Establish design files Customizing- Set the parameters of the plant 1000 plants edit
  • - Create planning file Define Customizing- plant parameters plant adaptation in 1000 (Correct)

Answer : - Create planning file Define Customizing- plant parameters plant adaptation in 1000

What SAP ERP mean?


Options are :

  • SAP ERP is the technological basis of the customer-specific extensions can be introduced.
  • SAP ERP is the design of a system with extended designing processes can be mapped.
  • SAP ERP is a system, apparatus, which includes modules for purchasing, sales and distribution, materials management, production, and so on.
  • None
  • SAP ERP is the application that the company can use to manage business processes more effectively. (Correct)

Answer : SAP ERP is the application that the company can use to manage business processes more effectively.

Comment / Suggestion Section