SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 5

The company that you specify does not want to manage consume a certain value materials warehouse stock. Instead, the user wants to control the provision of the material so that these materials are sourced directly from the production and / or process sequence. How do you respond to this request? (Choose two.)


Options are :

  • Using a special key acquisition sub-contracting material master component
  • Use item type, the bill-stock item as the material of the material
  • Using the procurement type External procurement material master component
  • Using a special key acquisition direct supply / external supply component material to the master

Answer : Use item type, the bill-stock item as the material of the material Using a special key acquisition direct supply / external supply component material to the master

SAP ECC, customer testing options for firming planned orders. Customer first set the manual firming since the stock / requirements list from strength to planned orders, that is, at least in the short term. Material master, moving planning horizon with firming type 1 is active. Some of the planned orders has also strengthened the hand already. What is the result of the firming situation?


Options are :

  • None
  • The curing time interval is defined in the firming process mechanism, which currently extends further in the future; all planned orders this horizon is only confirmed if they have been previously verified by hand.
  • Firming interval is defined in the manual firming date, because it always overrides the planning time fence functions material all by hand master planned orders are confirmed independently confirmed this.
  • Firming interval is defined planning time fence material master, because this always overrides the manual firming date; all hand confirmed the planned orders have independently confirmed this.
  • Firming interval is defined firming mechanism, which now extends further into the future and which companies planned orders that are within it; all hand confirmed the planned orders have independently confirmed this.

Answer : Firming interval is defined firming mechanism, which now extends further into the future and which companies planned orders that are within it; all hand confirmed the planned orders have independently confirmed this.

Final assembly of the finished product should be used only when a customer order has been received. Every strategy of the finished product do you use?


Options are :

  • Design of make-to-stock (strategy 10)
  • Planning with final assembly (strategy 40)
  • Planning without final assembly (strategy 50)
  • None
  • The design is assembly level (strategy 70)

Answer : The design is assembly level (strategy 70)

What functions can be done before releasing a production order? (Choose three)


Options are :

  • scheduling
  • Confirmation
  • Dial routing
  • BOM Selection

Answer : scheduling Dial routing BOM Selection

Which feature applies to the consumption of 40 strategy (design and final assembly)?


Options are :

  • None
  • Consumption takes place in the planning material.
  • Consumption creates static and binding function independent from the planned requirements and customer requirements throughout the procurement process.
  • Consumption may lead to subsequent adjustments to the planned receipts.
  • Consumption can reduce the initial production volume.

Answer : Consumption may lead to subsequent adjustments to the planned receipts.

SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 6

What could be the result of the confirmation of the operation?


Options are :

  • Restructuring of production order
  • the actual costs of disputes
  • None
  • The update planned costs
  • The capacity reduction requirements

Answer : The capacity reduction requirements

When modeling your production SAP ECC, with business levels you will be able to create a Bill of Material (BOM)? (Choose two)


Options are :

  • At the industry level
  • The factory level
  • The workstation level
  • At the company code level

Answer : The factory level The workstation level

Which of the following statements in the planning functions of SAP is the right one?


Options are :

  • None
  • Long-term planning (LTP) is in the form of a forecast long-term planning.
  • The master production scheduling (MPS) refers to the primary design of important materials.
  • Demand Management (DM) lack of material situations are identified and the corresponding receipt elements are created.
  • Material Requirements Planning (MRP) includes an automatic leveling capacity.

Answer : The master production scheduling (MPS) refers to the primary design of important materials.

Where can configure the default storage location of the component material production order? (Choose three)


Options are :

  • routing
  • Material master (Component)
  • Center for Production supply area work
  • The production version of the (product)

Answer : Material master (Component) Center for Production supply area work The production version of the (product)

What is characteristic of state si-regulation and content requirements planning in SAP ECC?


Options are :

  • It calculates the delay that may occur in the design.
  • It is triggered by a multi-level bottom-up scheduling.
  • None
  • It posts the design results in a database automatically.
  • It turned exception messages to the finished component.

Answer : It calculates the delay that may occur in the design.

During the processing of production orders, planned and actual costs are determined. Which of the following items, you can collect these costs? (Choose two)


Options are :

  • production orders
  • Product price Collector
  • work center
  • planned order

Answer : production orders Product price Collector

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 1

Which of the following functions are available in SAP for capacity leveling? (Choose three)


Options are :

  • lot size optimization
  • The focal point of scheduling
  • Setup time reduction
  • A finite capacity scheduling

Answer : The focal point of scheduling Setup time reduction A finite capacity scheduling

What SAP ERP mean?


Options are :

  • SAP ERP is the application that the company can use to manage business processes more effectively.
  • SAP ERP is the technological basis of the customer-specific extensions can be introduced.
  • SAP ERP is the design of a system with extended designing processes can be mapped.
  • None
  • SAP ERP is a system, apparatus, which includes modules for purchasing, sales and distribution, materials management, production, and so on.

Answer : SAP ERP is the application that the company can use to manage business processes more effectively.

Which of the following objects to enter the confirmation? (Choose two)


Options are :

  • Production order operation
  • The trigger point
  • work center
  • production orders

Answer : Production order operation production orders

The company wants to absorb the uncertainty caused by fluctuating demand of the finished product by means of the SAP buffer variable. They suggest the dynamic safety stock. What are the requirements used for the calculation of the dynamic safety stock?


Options are :

  • Static safety equipment and material forecast
  • None
  • The average daily demand and the backup time
  • Static safety stock and safety time per day
  • The average daily demand and the desired days of consumption

Answer : The average daily demand and the desired days of consumption

What features are ECC Master Production Scheduling (MPS) is? (Choose three.)


Options are :

  • MPS items can be defined at the level of the plant.
  • MPS items may also be considered a normal MRP run (Material Requirements Planning).
  • MPS to be taken into account in an MPS term.
  • MPS also can be defined as MRP area level (Material Requirements Planning Area).

Answer : MPS items can be defined at the level of the plant. MPS to be taken into account in an MPS term. MPS also can be defined as MRP area level (Material Requirements Planning Area).

What are the consequences confirmation of the operation? (Choose two.)


Options are :

  • The serial numbers will be given for the amount fixed
  • Actual costs are posted established production.
  • Produced and confirmed the amount is automatically posted to the warehouse stock receipt.
  • The mission capacity requirements are reduced.

Answer : Actual costs are posted established production. The mission capacity requirements are reduced.

The supply chain planning run is carried out SAP system as an example. What would be the most efficient order in which to run design modules?


Options are :

  • 1.Sales and operations planning Demand management 2. 3. 4. Long-term planning requirements planning5. capacity Planning
  • 1. Demand management 2. Sales and operations planning 3. Capacity Planning 4. Long-term planning5. requirements planning
  • 1. Capacity Planning 2. Sales and OperationsPlanning 3. Demand management 4. Long-term planning5. requirements planning
  • None
  • 1. Long-term planning 2.Sales and operations planning Demand management 3. 4. Requirements planning5. capacity Planning

Answer : 1.Sales and operations planning Demand management 2. 3. 4. Long-term planning requirements planning5. capacity Planning

Which of the following master data is required for the production order processing, when the material provisions and requirements of the capacity for action should be created automatically? (Choose two.)


Options are :

  • Output record material (product and the material component)
  • audit properties
  • document structure
  • routing

Answer : Output record material (product and the material component) routing

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 2

The Service Desk is available as part of SAP Solution Manager. What are the features included in the Service Desk? (Choose two.)


Options are :

  • Managing SAP Notes
  • Note SAP
  • for processing messages
  • problems karttoittaminen

Answer : Managing SAP Notes for processing messages

Which of the following is characterized by repetitive manufacturing plant? (Choose three.)


Options are :

  • Period, based on the design of the quantities produced
  • Automatic line loading within the limits of the capacity of all production lines
  • Production without orders and without state control E. workshop manufacturing
  • Continuous material consumption, production flow and yield

Answer : Period, based on the design of the quantities produced Production without orders and without state control E. workshop manufacturing Continuous material consumption, production flow and yield

a member of the project team analyzed the situation following SAP has stock / requirements to the final product list: there is only one customer order and one with a fixed planned order is equal to the number. The customer's order and a planned order both have deadlines on work days, but not on the same working day; the planned order is postponed. The project team member can find a reorganization of the message refers to a mismatch of this period stock / requirements list. What reasons could there be a missing message? (Choose two.)


Options are :

  • The requirement coverage element is outside of the reorganization of the horizon.
  • The need for calculation has not yet been carried out to update the schedule of changes in the message.
  • Time offset adjustment of a defined tolerance range.
  • The elements are interconnected by a fixed binding.

Answer : The requirement coverage element is outside of the reorganization of the horizon. Time offset adjustment of a defined tolerance range.

The Company wishes to advise that control the availability check is so that when the production and / or process is ordered, the following inputs or issues are addressed: designing, purchasing, production orders, reservations, dependent requirements. In the production and / or process order is released, the only equipment that is currently freely available should be taken into account. How do you respond to this request?


Options are :

  • Please enter a valid checking the availability of constitutional order type.
  • None
  • Differentiated made of two different checking rules under control supervision.
  • Please enter a valid checking the availability of a group of master material.
  • Activate freely available in stock within the scope of the check.

Answer : Differentiated made of two different checking rules under control supervision.

In the adaptation of the requirements of the design, the project team discovers that the options P1, P2, P3 and P4 is supplied, as standard, in addition to the MRP type PD. The amount of each of these options represents a firming type. What Firming Define? (Choose two.)


Options are :

  • Handling of existing procurement proposals outside the planning time fence.
  • Handling of existing procurement planning proposals at the fence.
  • Handling the new requirements within the planning time fence.
  • Handling new procurement proposals that have been created due to the new requirements within the planning time fence.

Answer : Handling of existing procurement planning proposals at the fence. Handling new procurement proposals that have been created due to the new requirements within the planning time fence.

Which of the following conditions must be fulfilled assignments are transferred via the data entry system the company's plant data collection (PDC PP) interface? (Choose three.)


Options are :

  • Execution Steps were used to store instructions for the operation.
  • The order has been released.
  • The application of the PP-PDC interface is activated, so that the type of production order.
  • The order includes at least one operation, which includes the work of the central subsystem to the group.

Answer : The order has been released. The application of the PP-PDC interface is activated, so that the type of production order. The order includes at least one operation, which includes the work of the central subsystem to the group.

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 3

Which data are included in the production of versions to select routings and bills of material?


Options are :

  • Explosion date on which the validity of the routing and bill of material is checked
  • The institution to which the routing and the BOM is created
  • None
  • All control parameters are selected bills of material and routing
  • A routing and BOM alternatives can be used for the production of

Answer : A routing and BOM alternatives can be used for the production of

Jumping to a final product that you want to use the planning time fence and mounting type 1, in order to calm down the situation in the design of SAP in a short time window. Two customer orders arrive on short notice and their income should really be inside the planning time fence, due to their date / time. Which of them is true in this scenario?


Options are :

  • Planning function examines only the changes that are relevant within the framework of scheduling planning time fence, the customer orders processed time.
  • Newly created planned orders can not be to create a planning tool before the end of the planning time fence, the earliest.
  • MRP controller does not have the possibility of creating planned orders within the planning time fence.
  • Within the planning time fence, just created planned orders are automatically frozen in requirements planning (roll forward).
  • None

Answer : Newly created planned orders can not be to create a planning tool before the end of the planning time fence, the earliest.

Modeling own production using SAP, bills of material (BOM) are logged on. With business levels you will be able to create a BOM? (Choose two.)


Options are :

  • At the company code level
  • The workstation level
  • At the industry level
  • The factory level

Answer : The workstation level The factory level

Which of the following are characteristics of ECC multi-site design? (Choose two.)


Options are :

  • When using a two-step stock transport order with delivery, the host plant is defined as a customer.
  • The extent of the use of the design (cross-plant total design) is mandatory for Multi-Site Planning.
  • When using a one-step stock transfer posting, transfer of stock is created in the host plant.
  • Both the pullout of alternative crops and the withdrawal of another plant is defined through a special procurement keys.

Answer : When using a two-step stock transport order with delivery, the host plant is defined as a customer. Both the pullout of alternative crops and the withdrawal of another plant is defined through a special procurement keys.

Which of the following functions occurs when the production order is created? (Choose three.)


Options are :

  • When calculating the lead time in production order
  • Select and copy routing
  • The selection and copying bill of material
  • The original document, addressed to the master of the material of the product can be prepared

Answer : When calculating the lead time in production order Select and copy routing The selection and copying bill of material