What is the SAP Solution Manager?


Options are :

  • A standalone system that communicates with other systems in the system landscape (Correct)
  • Controlled system in the system landscape
  • None
  • Part of the SAP System
  • The add-industry solution

Answer : A standalone system that communicates with other systems in the system landscape

You choose the master data channel assignments through the production versions. Which data are included in the production version?


Options are :

  • Explosion dates routing and Bom
  • type used in the default order
  • A routing and BOM alternatives for use (Correct)
  • None
  • Control of parameters selected routes and BOM

Answer : A routing and BOM alternatives for use

Which of the following activities, which are usually triggered by KANBAN procedure later in stock sending the receipt of the goods?


Options are :

  • Set "Container transport"
  • Set "Container full" (Correct)
  • Set "container in the process"
  • Set "Container empty"
  • None

Answer : Set "Container full"

What action would reduce the capacity requirements for the operation? (Choose three)


Options are :

  • A restructuring operation
  • By reducing the amount of the order (Correct)
  • By setting the status technically completed (TECO) (Correct)
  • confirming the operation (Correct)

Answer : By reducing the amount of the order By setting the status technically completed (TECO) confirming the operation

SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 3

Which of the following statements ATP (available to promise) to ensure the material components are correctly? (Choose two)


Options are :

  • ATP checks will be used to evaluate the free capacity in a particular work center
  • ATP checks can be carried out automatically, when the release of the production order. (Correct)
  • ATP checks can also be adjusted to consider the demands of the future and receipts. (Correct)
  • ATP checks is carried out automatically during the Material Requirements Planning (MRP) passes.

Answer : ATP checks can be carried out automatically, when the release of the production order. ATP checks can also be adjusted to consider the demands of the future and receipts.

Which of the following objects can be activated to backflushing assignments? (Choose three)


Options are :

  • Material master (Component) (Correct)
  • routing (Correct)
  • Material master (finished product)
  • Production scheduling profile
  • work center (Correct)

Answer : Material master (Component) routing work center

Every basic information needed to create a reserve of material production orders?


Options are :

  • material output record (Correct)
  • production versions
  • None
  • routings
  • Production / resource tools

Answer : material output record

What types of items can be changed change management (ECM)? (Choose three)


Options are :

  • material master (Correct)
  • the production version
  • To-do list (Correct)
  • Bill of material (Correct)

Answer : material master To-do list Bill of material

Which of the following statements on the size of the batch procedures is correct?


Options are :

  • None
  • the entire amount of the item can be influenced using the minimum lot size and a rounding profile. (Correct)
  • Number of the contracting procedure for the whole lot can be determined using the time profile of safety.
  • If you make an order production strategy is used only for the lot-for-lot (exact) size of the item may be subject.
  • If the size of the long-term tranche of the procurement is conducted using a long-term perspective.

Answer : the entire amount of the item can be influenced using the minimum lot size and a rounding profile.

To plan the final material by means of the value of the material requirements planning SAP system. As a result, the planned orders should be scheduled based on date scheduling (not lead to a schedule). Which of the following statements is true for the result depends on the requirements?


Options are :

  • When a customer's order to create a finished material, depending on the requirements of the bill automatically trigger the components of the material without planning run.
  • If the individual material components are specifically addressed to the routing operation, the requirement dates depend on the requirements of each scheduled start date of the operation.
  • None
  • Multi-level backward scheduling, depend on the requirements of trips start date of a planned order of the finished material. (Correct)
  • Multi-level backward scheduling, depend on the requirements of calculated the exact second.

Answer : Multi-level backward scheduling, depend on the requirements of trips start date of a planned order of the finished material.

SAP P_HCMTM_64 Certified Professional - HCM Talent Mngt Exam Set 3

Which of the following is offered MRP areas in SAP ECC? (Choose two)


Options are :

  • The preset can be given different MRP areas.
  • Make your subscription supports the production storage location MRP areas.
  • MRP area may belong to different memory locations. (Correct)
  • Subcontracting supports the MRP areas. (Correct)

Answer : MRP area may belong to different memory locations. Subcontracting supports the MRP areas.

During the project phase, the client raises questions concerning the type of acquisition parameters for the material master SAP system. Which of the following procurement type characteristics are valid? (Choose two)


Options are :

  • supply of material type can be selected freely between E (in-house production), F (external supply), and X (both acquisition s) independent of the type of material.
  • If both procurement types are permitted entry X (both procurement types), requirements planning based on own production. (Correct)
  • If the acquisition of type E (own production) has been set, an external supplies may be possible depending on the material type. (Correct)
  • Procurement types E (own production) and F (external procurement) need to be finalized special procurement types.

Answer : If both procurement types are permitted entry X (both procurement types), requirements planning based on own production. If the acquisition of type E (own production) has been set, an external supplies may be possible depending on the material type.

To create a new material with the following characteristics: a material stored in a warehouse, is externally acquired and bills of material are used as component a variety of end products. The material may not be sold directly. What standard SAP type of material do you use?


Options are :

  • None
  • ROH (raw material) (Correct)
  • NLAG (non-raw material)
  • HAWA (trading good)
  • FERT (finished product)

Answer : ROH (raw material)

What problem can occur if the lot size dependent's own production of the material time the host is not updated after changing the routing?


Options are :

  • Dependent on the requirements to request the components used at the wrong times of the basic material of a list of scheduling dates. (Correct)
  • Lead time scheduling can take place.
  • Requirements for the design gets the proper exception to the basic message scheduling dates.
  • None
  • The resulting design production capacity is no longer possible due to outdated timing parameters.

Answer : Dependent on the requirements to request the components used at the wrong times of the basic material of a list of scheduling dates.

Availability inspection during the production creation would be to use a different scope than the check during order release. How can you meet this requirement?


Options are :

  • Maintain adequate checking the availability of the rules of production scheduling profile.
  • Maintain adequate checking the availability of the rules depend on the parameters of the order type.
  • To maintain appropriate monitoring rules, check the control creation and order release. (Correct)
  • None
  • Keep checking the availability of the appropriate group of master material.

Answer : To maintain appropriate monitoring rules, check the control creation and order release.

Where the SAP system, you can specify the production versions?


Options are :

  • Material master (Correct)
  • routing list
  • The invoice material
  • The work center
  • None

Answer : Material master

SAP P_HCMTM_64 Certified Professional - HCM Talent Mngt Exam Set 3

You are using a planning time fence and the attachment type 1. For a customer order material availability date within the planning time fence. What you need to consider in this scenario?


Options are :

  • Requirements planning to keep only the changes that are relevant to scheduling within the framework of the planning time fence.
  • The planned orders are created planning time fence and automatically establishes requirements for design
  • The planned orders created by the requirements of the design is transferred to the end of the planning time fence. (Correct)
  • None
  • MRP controller can create planned orders within the planning time fence.

Answer : The planned orders created by the requirements of the design is transferred to the end of the planning time fence.

You want to send the data relating to production order, including confirmations, receipts of goods, goods issues, and other user-specific real external process control system SAP ECC. How can you meet this requirement?


Options are :

  • Use the PI-PCS interface. (Correct)
  • None
  • Use the PP-PDC interface.
  • Use of the service application interface (SAPI).
  • Use the core interface (CIF).

Answer : Use the PI-PCS interface.

Any statements of SAP's long-term planning (LTP) are correct? (Choose two)


Options are :

  • Reorder point designed materials can be included in the LTP. (Correct)
  • In the case of external procurement LTP creates purchase requisitions.
  • A planning consent scenario must be released to the LTP. (Correct)
  • In general, LTP is the operational planning of important components.

Answer : Reorder point designed materials can be included in the LTP. A planning consent scenario must be released to the LTP.

Which recur in the manufacturing of options you can use to make a line loading of SAP ECC system and thus produces a run schedule quantities (RSQ) of the normal planned orders? (Choose three)


Options are :

  • Automatic selection of the production version of the application of a quota arrangement book content requirements planning (MRP) (Correct)
  • Suitable repetitive manufacturing a profile that includes an alternative automatic line selection
  • Automatic selection of the production version of the material requirements planning (MRP) using the selection methods of setting (Correct)
  • Manual planned order sheet production volumes are planning table (Correct)

Answer : Automatic selection of the production version of the application of a quota arrangement book content requirements planning (MRP) Automatic selection of the production version of the material requirements planning (MRP) using the selection methods of setting Manual planned order sheet production volumes are planning table

Every adaptation element controls designed for the determination of the cost of production orders?


Options are :

  • pays variant (Correct)
  • operation
  • Settlement profile
  • accounting type
  • None

Answer : pays variant

Which of the following statements ATP checks which trigger the SAP customer orders is correct?


Options are :

  • ATP amount is available for the quantity that can be used to confirm the incoming customer orders.
  • None
  • ATP check does not take into account inventory and receipts. It will check the consumption of the planned independent requirements.
  • If the ATP check to determine the non-availability. It then checks the next step, whether it is possible to buy or prepare in time. (Correct)
  • ATP amendment establishes fixed connections to customer orders and confirmed their receipts.

Answer : If the ATP check to determine the non-availability. It then checks the next step, whether it is possible to buy or prepare in time.

SAP C_TSCM66_66 Certified Associate Logistics Execution Exam Set 7

In the adaptation of the requirements of the design, the project team discovers that the options P1, P2, P3 and P4 is supplied, as standard, in addition to the MRP type PD. The amount of each of these options represents a firming type. What Firming Define? (Choose two)


Options are :

  • Handling proposals for new purchases that have been created due to the new requirements within the planning time fence. (Correct)
  • Handling of existing procurement planning proposals at the fence. (Correct)
  • Handling of existing procurement proposals outside the planning time fence.
  • Handling the new requirements within the planning time fence.

Answer : Handling proposals for new purchases that have been created due to the new requirements within the planning time fence. Handling of existing procurement planning proposals at the fence.

What information can be sent directly to the Plant Data Collection (PDC PP) interface?


Options are :

  • Maintenance notifications
  • reinforcements (Correct)
  • Goods issues
  • None
  • Goods receipts

Answer : reinforcements

Which of the following items of master data needed for the production of repetitive? (Choose three)


Options are :

  • Repetitive Manufacturing (Correct)
  • Product price Collector (Correct)
  • the production version (Correct)
  • Production supply area

Answer : Repetitive Manufacturing Product price Collector the production version

What can be used to process orders with the following master data? (Choose three)


Options are :

  • master recipes (Correct)
  • resources (Correct)
  • production versions (Correct)
  • serial numbers

Answer : master recipes resources production versions

Which of the following elements can be used in the process in order? (Choose three)


Options are :

  • Interpersonal relationships (Correct)
  • process steps (Correct)
  • stages of (Correct)
  • suboperations

Answer : Interpersonal relationships process steps stages of

Stocks / requirements to the final product list contains only a single customer's order and one fixed planned order by the same amount. Availability dates for both the MRP elements are in working days. Availability date fixed planned order is set later compared to a single customer order. However, the corresponding reorganization exception message does not occur. What could be the reason? (Choose two)


Options are :

  • The need for the calculation has not been completed.
  • MRP elements are interconnected by a solid tie.
  • availability dates between Delta includes editing the tolerance range specified. (Correct)
  • The fixed planned order is out of the reorganization of the horizon. (Correct)

Answer : availability dates between Delta includes editing the tolerance range specified. The fixed planned order is out of the reorganization of the horizon.

SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 2

Material designed in connection with the SAP material requirements planning. MRP controller further processed material manually by changing the order of certain of the proposed production order. Now MRP controller accesses the storage situation / requirements list and the MRP inventory This material and compares these two lists. Which of the following conditions applies to the two lists at this point? (Choose two)


Options are :

  • Stocks / requirements list displays the production order. (Correct)
  • The MRP list shows the production order.
  • Stocks / requirements list updated on the exact date it was opened. (Correct)
  • MRP list status is "processed".

Answer : Stocks / requirements list displays the production order. Stocks / requirements list updated on the exact date it was opened.

Which supports the function assignments?


Options are :

  • Automatic printing of documents in order to create a
  • Automatic reading grade PP master data release
  • Automatic creation of transfer orders to order release (Correct)
  • None
  • Automatic selection of the work center in order release

Answer : Automatic creation of transfer orders to order release

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions