SAP C_TSCM42_66 Certified Associate - Production Exam Set 8

Which of the following master data can be used with process orders? (Choose three)


Options are :

  • Master recipies (Correct)
  • Production versions (Correct)
  • Serial numbers
  • Resources (Correct)

Answer : Master recipies Production versions Resources

A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists. Which of the following statements are true for the two lists at this stage? (Choose two)


Options are :

  • The stock/requirements list displays the production order. (Correct)
  • The MRP list displays the production order.
  • The stock/requirements list was updated at the precise time it was accessed. (Correct)
  • The MRP list has the status "processed".

Answer : The stock/requirements list displays the production order. The stock/requirements list was updated at the precise time it was accessed.

Which of the following statements regarding ATP checks in SAP ECC that are triggered from customer orders is correct?


Options are :

  • The ATP quantity is the available quantity, which can be used to confirm incoming customer orders.
  • An ATP check creates fixed links between customer orders and their confirmed receipts.
  • If the ATP check determines non-availability. It then checks in the next step whether it is possible to procure or produce in time. (Correct)
  • The ATP check does not take stocks and receipts into account. It checks consumption of planned independent requirements.

Answer : If the ATP check determines non-availability. It then checks in the next step whether it is possible to procure or produce in time.

SAP P_HCMTM_64 Certified Professional - HCM Talent Mngt Exam Set 3

Which types of objects can be changed with Engineering Change Management (ECM)? (Choose three)


Options are :

  • Production version
  • Task list (Correct)
  • Bill of material (Correct)
  • Material master (Correct)

Answer : Task list Bill of material Material master

You select the master data for production orders via production versions. Which information is contained in a production version?


Options are :

  • The control parameters for selecting routings and BOM
  • The default order type to be used
  • The routing and BOM alternatives to be used (Correct)
  • The explosion dates for the routing and BOM

Answer : The routing and BOM alternatives to be used

Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)


Options are :

  • Rescheduling the operation
  • Confirming the operation (Correct)
  • Setting the status technically complete (TECO) (Correct)
  • Reducing the order quantity (Correct)

Answer : Confirming the operation Setting the status technically complete (TECO) Reducing the order quantity

SAP C_TSCM66_66 Certified Associate Logistics Execution Exam Set 4

The stock/requirements list for a finished product contains only one customer order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date of the fixed planned order is set to a later date compared to the one of the customer order. However, a corresponding rescheduling exception message does not occur. What could be the reason? (Choose two)


Options are :

  • Requirement planning has not been carried out.
  • The MRP elements are linked via fixed pegging.
  • The fixed planned order is outside the rescheduling horizon. (Correct)
  • The delta between the availability dates falls within the tolerance window defined in Customizing. (Correct)

Answer : The fixed planned order is outside the rescheduling horizon. The delta between the availability dates falls within the tolerance window defined in Customizing.

The availability check during production order creation should use a different scope of check than during order release. How can you fulfill this requirement?


Options are :

  • Maintain appropriate checking rules in checking control for order creation and order release. (Correct)
  • Maintain appropriate availability checking rules in the production scheduling profile.
  • Maintain an appropriate availability checking group in the material master.
  • Maintain appropriate availability checking rules in the order type-dependent parameters.

Answer : Maintain appropriate checking rules in checking control for order creation and order release.

Which statements regarding SAP ECC long-term planning (LTP) are correct? (Choose two)


Options are :

  • Reorder point planned materials can be included in LTP. (Correct)
  • A planning scenario must be released to use it in LTP. (Correct)
  • Generally, LTP is operational planning of important components.
  • In case of external procurement, LTP creates purchase requisitions.

Answer : Reorder point planned materials can be included in LTP. A planning scenario must be released to use it in LTP.

SAP C_TSCM66_66 Certified Associate Logistics Execution Exam Set 1

Which repetitive manufacturing options can you use to carry out line loading in the SAP ECC system and thus generate run schedule quantities (RSQ) from normal planned orders? (Choose three)


Options are :

  • Manual assignment of planned production quantities in a planning table (Correct)
  • Automatic selection of the production version by applying quota arrangement records in material requirements planning (MRP) (Correct)
  • A suitable repetitive manufacturing profile that contains an option for automatic line selection
  • Automatic selection of the production version in material requirements planning (MRP) using selection methods setting (Correct)

Answer : Manual assignment of planned production quantities in a planning table Automatic selection of the production version by applying quota arrangement records in material requirements planning (MRP) Automatic selection of the production version in material requirements planning (MRP) using selection methods setting

Which of the following efforts can be minimized using the KANBAN procedure?


Options are :

  • Effort for master data maintenance
  • Organizational effort for capacity planning
  • Effort for Sales and Operations Planning (SOP)
  • Organizational effort for material staging (Correct)

Answer : Organizational effort for material staging

Which of the following elements can be used in a process order? (Choose three)


Options are :

  • Process instructions (Correct)
  • Phases (Correct)
  • Suboperations
  • Relationships (Correct)

Answer : Process instructions Phases Relationships

SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 2

You want to create a new material with the following properties: the material is kept in stock, is externally procured, and is used as a component in the bills of material for various final products. The material must not be sold directly. Which standard SAP material type do you use?


Options are :

  • FERT (finished product)
  • NLAG (non-stock material)
  • ROH (raw material) (Correct)
  • HAWA (trading good)

Answer : ROH (raw material)

Which Customizing element controls the determination of planned costs in production orders?


Options are :

  • Settlement profile
  • Calculation procedure
  • Accounting type
  • Costing variant (Correct)

Answer : Costing variant

Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?


Options are :

  • Set "Container in transport"
  • Set "Container empty"
  • Set "Container in process"
  • Set "Container full" (Correct)

Answer : Set "Container full"

SAP C_TFIN52_66 Certify Associate Financial Accounting Exam Set 5

Where in the SAP ECC system can you define production versions?


Options are :

  • In the bill of material
  • In the work center
  • In the routing
  • In the material master (Correct)

Answer : In the material master

What is SAP Solution Manager?


Options are :

  • A managed system in a system landscape
  • An add-on industry solution
  • A stand-alone system that communicates with other systems in a system landscape (Correct)
  • A part of the SAP ECC System

Answer : A stand-alone system that communicates with other systems in a system landscape

You want to send production order-related data like confirmations, goods receipts, goods issues, and other user-specific actual data from an external process control system to SAP ECC. How can you fulfill this requirement?


Options are :

  • Use the PI-PCS interface. (Correct)
  • Use the service application interface (SAPI).
  • Use the PP-PDC interface.
  • Use the core interface (CIF).

Answer : Use the PI-PCS interface.

Which master data is necessary for the creation of material reservations for production orders?


Options are :

  • Material master records (Correct)
  • Routings
  • Production/resource tools
  • Production versions

Answer : Material master records

Which of the following features are offered by MRP areas in SAP ECC? (Choose two)


Options are :

  • A storage location may be assigned to different MRP areas.
  • Subcontracting is supported by MRP areas. (Correct)
  • An MRP area may include different storage locations. (Correct)
  • Make-to-order production is supported by storage location MRP areas.

Answer : Subcontracting is supported by MRP areas. An MRP area may include different storage locations.

You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling). Which of the following statements is true for the resulting dependent requirements?


Options are :