SAP C_TSCM42_66 Certified Associate - Production Exam Set 7

You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you should be able to use a second sequence on other work centers for operations 30 and 40. What sequence category do you use to create the second sequence in the system?


Options are :

  • Substitute sequence
  • Standard sequence
  • Parallel sequence
  • Alternative sequence (Correct)

Answer : Alternative sequence

What does SAP ERP mean?


Options are :

  • SAP ERP is a technological platform, on the basis of which customer-specific extensions can be imported.
  • SAP ERP is a planning system in which extended planning processes can be mapped.
  • SAP ERP is a system hardware that includes modules for purchasing, sales and distribution, materials management, production and so on.
  • SAP ERP is an application that an enterprise can use to manage its business processes efficiently. (Correct)

Answer : SAP ERP is an application that an enterprise can use to manage its business processes efficiently.

SAP C_TADM51702 Certified Technology Associate - System Exam Set 6

Which of the following consequences result when a production order is set to Technically Complete (TECO)? (Choose three)


Options are :

  • Reservations are no longer relevant for material requirements planning. (Correct)
  • Capacity requirements are set to null. (Correct)
  • The order and its operations receive the system status Locked (LKD).
  • The order is no longer relevant for material requirements planning. (Correct)
  • Confirmations are no longer permitted.

Answer : Reservations are no longer relevant for material requirements planning. Capacity requirements are set to null. The order is no longer relevant for material requirements planning.

Which of the following properties applies to multi-site planning in SAP ECC?


Options are :

  • When using one-step stock transfer posting, transfer stock is created in the receiving plant.
  • The use of "scope of planning" (cross-plant total planning) is mandatory for multi-site planning.
  • Multi-site planning can be activated using the corresponding planning strategy.
  • Both withdrawal from alternative plant and stock transfer from another plant are defined via special procurement keys. (Correct)

Answer : Both withdrawal from alternative plant and stock transfer from another plant are defined via special procurement keys.

In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data: Start: 7:00:00 a.m. End: 3:00:00 p.m. Break duration: 1 hour Rate of utilization: 80% Overload: 110% Number of individual capacities: 1 How large is the standard available capacity?


Options are :

  • 6.16 hours
  • 8 hours
  • 5.6 hours (Correct)
  • 7 hours

Answer : 5.6 hours

SAP C_THR12_66 Certified Application Associate - HCM Exam Set 5

When modeling in-house production using SAP ECC, on which business levels can you create a bill of material (BOM)? (Choose two)


Options are :

  • At the business area level
  • At the plant level (Correct)
  • At the company code level
  • At the client level (Correct)

Answer : At the plant level At the client level

What can you use to organize material staging for production orders? (Choose three)


Options are :

  • Logistics Information System (LIS)
  • Pull list (Correct)
  • Transfer orders (Correct)
  • KANBAN (Correct)

Answer : Pull list Transfer orders KANBAN

Which property applies for consumption with planning strategy 40 (planning with final assembly)?


Options are :

  • Consumption takes place with the planning material.
  • Consumption can result in subsequent adjustments of planned receipts. (Correct)
  • Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.
  • Consumption can reduce the originally planned production quantity.

Answer : Consumption can result in subsequent adjustments of planned receipts.

SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 8

Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)


Options are :

  • Lot size optimization
  • Midpoint scheduling (Correct)
  • Setup time reduction (Correct)
  • Finite capacity scheduling (Correct)

Answer : Midpoint scheduling Setup time reduction Finite capacity scheduling

You want to use the function "Read PP master data" in the production order. However, while calling the function you receive an error message. What could be the reason?


Options are :

  • The material availability check has been performed.
  • Order papers have been printed.
  • The production order has been released.
  • Goods movements have been posted. (Correct)

Answer : Goods movements have been posted.

Where can you define the default storage location for the material component of a production order? (Choose three)


Options are :

  • Production version (product) (Correct)
  • Routing
  • Production supply area of a work center (Correct)
  • Material master (component) (Correct)

Answer : Production version (product) Production supply area of a work center Material master (component)

SAP C_TSCM62_65 Certified Associate - Order Fulfilment Exam Set 1

During the processing of production orders planned and actual costs are determined. On which of the following objects can you collect these costs? (Choose two)


Options are :

  • Production order (Correct)
  • Work center
  • Product cost collector (Correct)
  • Planned order

Answer : Production order Product cost collector

You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand. How can you fulfill these requirements in SAP ECC? (Choose two)


Options are :

  • Use strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material. (Correct)
  • Use strategy 40 (planning with final assembly) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
  • Use strategy 50 (planning without final assembly) for the finished product and no strategy for all assemblies in the bill of material. (Correct)
  • Use strategy 30 (production by lots) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.

Answer : Use strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material. Use strategy 50 (planning without final assembly) for the finished product and no strategy for all assemblies in the bill of material.

The final assembly of a finished product should only be triggered when a customer order arrives. Which planning strategy for the finished product do you use?


Options are :

  • Planning at the assembly level (strategy 70) (Correct)
  • Planteps of material requirements planning performed in SAP ECC?


    Options are :

    • Calculation of safety stock, Lot sizing, Scheduling, Determination of the procurement type
    • Availability check
    • Net requirements calculation, Lot sizing, Determination of the procurement type, Scheduling (Correct)
    • Net requirements calculation, Lot sizing, Scheduling, Determination of the procurement type

    Answer : Net requirements calculation, Lot sizing, Determination of the procurement type, Scheduling

    Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order. Which BOM item category must you set to fulfill this requirement?


    Options are :

    • N (non-stock item) (Correct)
    • D (document item)
    • E (external procurement)
    • M (phantom material)

    Answer : N (non-stock item)

    Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master. How is the resulting firming interval specified in this scenario?


    Options are :

    • By the planning time fence from the material master
    • By the manual firming date
    • It is predefined in Customizing.
    • By the firming mechanism that spans further into the future. (Correct)

    Answer : By the firming mechanism that spans further into the future.

    SAP C_TADM51702 Certified Technology Associate - System Exam Set 3

    For which of the following objects can you enter a confirmation? (Choose two)


    Options are :

    • Production order (Correct)
    • Work Center
    • Production order operation (Correct)
    • Trigger Point

    Answer : Production order Production order operation

    Which objects can affect the calculation of capacity requirements for an operation? (Choose three)


    Options are :

    • Standard values (routing) (Correct)
    • Transport time (routing)
    • Formulas (work center) (Correct)
    • Operation control key (routing) (Correct)

    Answer : Standard values (routing) Formulas (work center) Operation control key (routing)

    Which activity can trigger an automatic availability check for the components of a production order?


    Options are :

    • Order release (Correct)
    • Order rescheduling
    • Goods receipt for a missing part
    • Material staging

    Answer : Order release

    C_TADM51_731 SAP Net Weaver with System Administration Test Set 3

    During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system. Which of the following procurement type properties are valid? (Choose two)


    Options are :

    • If procurement type E (in-house production) is set, external procurement may still be possible depending on the material type. (Correct)
    • A material's procurement type can be freely selected between E (in-house production), F (external procurement) and X (both procurement types) independent of material type.
    • Procurement types E (in-house production) and F (external procurement) have to be further refined with special procurement types.
    • If both procurement types are allowed with entry X (both procurement types), requirements planning assumes in-house production. (Correct)

    Answer : If procurement type E (in-house production) is set, external procurement may still be possible depending on the material type. If both procurement types are allowed with entry X (both procurement types), requirements planning assumes in-house production.

    SAP C_TSCM52_66 Certified Associate Financial Accounts Test Set 6

    You want to enhance the system statuses of a production order with user statuses.How do you do this?


    Options are :

    • Define the user statuses in the order type-dependent parameters. (Correct)
    • Define the user statuses in the Customizing table of the system statuses.
    • Define a status profile in Customizing and assign it to the production scheduling profile.
    • Define a status profile in Customizing and assign it to the order type.

    Answer : Define the user statuses in the order type-dependent parameters.

    When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three)


    Options are :

    • General values from work scheduling view of the material master
    • User-defined fields in the operation of routings (Correct)
    • Standard values in the operations of routings (Correct)
    • General operation values of routings (Correct)

    Answer : User-defined fields in the operation of routings Standard values in the operations of routings General operation values of routings

    Which function is supported by production orders?


    Options are :

    • Automatic printing of order documents at order creation
    • Automatic selection of a work center at order release
    • Automatic creation of transfer orders at order release (Correct)
    • Automatic reading of PP master data at order release

    Answer : Automatic creation of transfer orders at order release

    SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 4

    In which of the following objects can you activate backflushing for production orders? (Choose three)


    Options are :

    • Material master (component) (Correct)
    • Work center (Correct)
    • Material master (finished product)
    • Routing (Correct)
    • Production scheduling profile

    Answer : Material master (component) Work center Routing

    What functions can you use for suboperations? (Choose two)


    Options are :

    • Production/Resource tools allocation
    • Capacity planning (Correct)
    • Costing (Correct)
    • Material component allocation

    Answer : Capacity planning Costing

    Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released?


    Options are :

    • Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.
    • Assign an appropriate availability checking rule to the material master for the product.
    • Activate the availability check and assign an overall profile in the production scheduling profile.
    • Activate the availability check and assign an overall profile in checking control for the business function order release. (Correct)

    Answer : Activate the availability check and assign an overall profile in checking control for the business function order release.

    SAP C_TSCM66_66 Certified Associate Logistics Execution Exam Set 5

    Which of the following statements about ATP (Available To Promise) checks for material components are correct? (Choose two)


    Options are :

    • ATP checks are automatically performed during Material Requirements Planning (MRP) runs.
    • ATP checks can be adjusted to also consider future requirements and receipts. (Correct)
    • ATP checks are used to evaluate the free capacity on a certain work center
    • ATP checks can be carried out automatically when releasing a production order. (Correct)

    Answer : ATP checks can be adjusted to also consider future requirements and receipts. ATP checks can be carried out automatically when releasing a production order.

    Which of the following items of master data are needed for repetitive manufacturing? (Choose three)


    Options are :

    • Production version (Correct)
    • Product cost collector (Correct)
    • Repetitive manufacturing profile (Correct)
    • Production supply area

    Answer : Production version Product cost collector Repetitive manufacturing profile

    What data can be posted directly via the Plant Data Collection (PP-PDC) interface?


    Options are :

    • Confirmations (Correct)
    • Goods receipts
    • Maintenance notifications
    • Goods issues

    Answer : Confirmations