Which statement regarding lot size procedures is correct?


Options are :

  • The lot size quantity can be influenced using a minimum quantity and the rounding profile. (Correct)
  • If a long-term lot size is in use, procurement is conducted with a long-term perspective
  • The procurement quantity of a lot size procedure can be specified using a safety time period profile.
  • If a make-to-order production strategy is in use, a lot for lot (exact) lot size is always determined for the corresponding procurement element.

Answer : The lot size quantity can be influenced using a minimum quantity and the rounding profile.

SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 2

Which of the following master data do you always have to make available for material replenishment using the KANBAN procedure? (Choose two.)


Options are :

  • Product cost collector
  • Control cycles (Correct)
  • Production supply areas (Correct)
  • Rate routings

Answer : Control cycles Production supply areas

Which of the following requirements for a manufacturing plant can be supported by using production orders? (Choose three.)


Options are :

  • Make-to-stock production. (Correct)
  • Variable calculation of material quantities (production output, material usage) and operation quantities.
  • Customer requirements-dependent production. (Correct)
  • Integrated display of documents (drawings, texts) in the production process. (Correct)

Answer : Make-to-stock production. Customer requirements-dependent production. Integrated display of documents (drawings, texts) in the production process.

The company that you advise does not want to manage certain value-intensive materials in the warehouse stock. Instead, the user wishes to control material provision in such a way that these materials are procured directly for the production and/or process order. How can you fulfill this request? (Choose two.)


Options are :

  • Using the procurement type external procurement in the material master for the component
  • Using the special procurement key direct procurement/external procurement in the material master for the component (Correct)
  • Using the item type non-stock item in the bill of material for the material in question (Correct)
  • Using the special procurement key subcontracting in the material master for the component

Answer : Using the special procurement key direct procurement/external procurement in the material master for the component Using the item type non-stock item in the bill of material for the material in question

SAP C_TB1200_88 Certified Associate SAP Business One Exam Set 3

A supply chain planning run is to be carried out in the SAP ECC system as an example. What would be the most effective sequence in which to run through the planning modules?


Options are :

  • 1. Long-term planning 2.Sales and Operations Planning 3. Demand management 4. Requirements planning5. Capacity planning
  • 1.Sales and Operations Planning 2. Demand management 3. Long-term planning 4. Requirements planning5. Capacity planning (Correct)
  • 1. Capacity planning 2. Sales and OperationsPlanning 3. Demand management 4. Longterm planning5. Requirements planning
  • 1. Demand management 2. Sales and Operations Planning 3. Capacity planning 4. Longterm planning5. Requirements planning

Answer : 1.Sales and Operations Planning 2. Demand management 3. Long-term planning 4. Requirements planning5. Capacity planning

In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type. What does a firming type define? (Choose two.)


Options are :

  • Handling existing procurement proposals within a planning time fence. (Correct)
  • Handling new procurement proposals that are to be created due to new requirements within the planning time fence. (Correct)
  • Handling new requirements within the planning time fence.
  • Handling existing procurement proposals outside the planning time fence.

Answer : Handling existing procurement proposals within a planning time fence. Handling new procurement proposals that are to be created due to new requirements within the planning time fence.

An enterprise based in the USA produces an end product that is used with the unit of measure "pound" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit kilogram (KG). Which of the following solutions does SAP ECC offer?


Options are :

  • In the basic data customizing, you create a unit of measure group that converts pounds to kilograms. You then assign this to the material master on basic data view 1.
  • There is no need to take any action. There is a general conversion in the central customizing of units of measurements, so that automatic conversion of pounds to kilograms takes place. (Correct)
  • You create a new material with a reference to the original material and assign the metric unit of measure to the new material master.
  • In the material master, you create a conversion factor for converting pounds to kilograms on basic data view 1.

Answer : There is no need to take any action. There is a general conversion in the central customizing of units of measurements, so that automatic conversion of pounds to kilograms takes place.

SAP C_THR12_66 Certified Associate - Human Capital Exam Set 3

In SAP ECC, a customer tests the firming options for planned orders. The customer first sets the manual firming date from the stock/requirements list to firm planned orders that shall occur in the short term. In the material master, a rolling planning time horizon with firming type 1 is active. Some planned orders have also been firmed manually already. Which statement applies for the resultant firming situation?


Options are :

  • The firming interval is specified by the planning time fence from the material master, because this always overrides the manual firming date; all the manually firmed planned orders are firmed independently of this.
  • The firming interval is specified by the firming mechanism that currently stretches further into the future; all the planned orders within this horizon are firmed only if they were previously firmed manually.
  • The firming interval is specified by the firming mechanism that currently stretches further into the future and which firms planned orders that are within it; all the manually firmed planned orders are firmed independently of this. (Correct)
  • The firming interval is specified by the manual firming date because it always overrides the planning time fence from the material master; all the manually firmed planned orders are firmed independently of this.

Answer : The firming interval is specified by the firming mechanism that currently stretches further into the future and which firms planned orders that are within it; all the manually firmed planned orders are firmed independently of this.

Which of the following possible errors would lead to the message shown? (Choose two.)


Options are :

  • The Customizing for the order type is set to manual routing selection and a valid routing exists.
  • In the material master, plan selection was set to production version. A production version was created and it is faulty. (Correct)
  • There are no valid routings or no routings available on the explosion date. (Correct)
  • The material master (product) is set to manual routing selection and valid routing exists.

Answer : In the material master, plan selection was set to production version. A production version was created and it is faulty. There are no valid routings or no routings available on the explosion date.

Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released?


Options are :

  • Activate the availability check and assign an overall profile in check control for the business function order release. (Correct)
  • Activate the availability check and assign an availability checking group to the material master for the product to be produced.
  • Activate the availability check and assign a checking rule to the work center for the operation to be checked.
  • Activate the availability check and assign the check control to the plant.

Answer : Activate the availability check and assign an overall profile in check control for the business function order release.

SAP C_TBIT44_71 Development Consultant Net Weaver Exam Set 1

In what order are the individual steps of material requirements planning performed in SAP ECC?


Options are :

  • 1. Net requirements calculation 2. Application of the lot-sizing procedure 3. Determination of the procurementtype 4. Scheduling (Correct)
  • 1. Net requirements calculation 2. Application of the lot-sizing procedure 3. Scheduling 4. Determination of the procurement type
  • 1. Availability check 2. Application of the lot-sizing procedure3. Determination of the procurement type 4. Scheduling
  • 1. Calculation of safety stock2. Application of the lot-sizing procedure 3. Scheduling 4. Determination of the procurement type

Answer : 1. Net requirements calculation 2. Application of the lot-sizing procedure 3. Determination of the procurementtype 4. Scheduling

In the course of a project phase, the customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system. Which of the following procurement type properties apply? (Choose two.)


Options are :

  • A material's procurement type can always be freely selected between E (in-house production), F (external procurement) and X (both procurement types).
  • Procurement types E (in-house production) and F (external procurement) have to be further refined with special procurement types.
  • If both procurement types are allowed with entry X, requirements planning assumes inhouse production. (Correct)
  • If procurement type E (in-house production) is set, external procurement may still be permissible. (Correct)

Answer : If both procurement types are allowed with entry X, requirements planning assumes inhouse production. If procurement type E (in-house production) is set, external procurement may still be permissible.

What are the consequences of a confirmation of an operation? (Choose two.)


Options are :

  • The produced and confirmed quantity is automatically posted to the warehouse stock as a receipt.
  • The operation's capacity requirements are reduced. (Correct)
  • Serial numbers are assigned for the confirmed quantity
  • Actual costs are posted for the production confirmed. (Correct)

Answer : The operation's capacity requirements are reduced. Actual costs are posted for the production confirmed.

SAP C_THR12_66 Certified Associate - Human Capital Exam Set 5

A customer wishes to only produce a finished product when customer orders for it are present. Final assembly should then be carried out at short notice in make-to-order production. Up until this point, the important assemblies needed in final assembly should already be available in stock. Provision of these assemblies should therefore be triggered by planning. Which options could you offer the customer as useful alternatives in SAP ECC? (Choose two.)


Options are :

  • The finished product uses strategy 20 (make-to-order production) and all the important assemblies in the bill of material for the finished product should have strategy 70 (planning at the assembly level). (Correct)
  • The finished product uses strategy 40 (planning with final assembly) and all the important assemblies in the bill of material for the finished product should have strategy 70 (planning at the assembly level).
  • The finished product uses strategy 30 (production by lots) and all the important assemblies in the bill of material for the finished product should have strategy 70 (planning at the assembly level).
  • The finished product uses strategy 50 (planning without final assembly) and all the assemblies in the bill of material for the finished product have no strategy. (Correct)

Answer : The finished product uses strategy 20 (make-to-order production) and all the important assemblies in the bill of material for the finished product should have strategy 70 (planning at the assembly level). The finished product uses strategy 50 (planning without final assembly) and all the assemblies in the bill of material for the finished product have no strategy.

In modeling in-house production using SAP ECC, bills of material (BOM) are to be recorded in the system. On which business levels can you create a BOM? (Choose two.)


Options are :

  • At the company code level
  • At the client level (Correct)
  • At the business area level
  • At the plant level (Correct)

Answer : At the client level At the plant level

What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)


Options are :

  • Approved master recipes (Correct)
  • Electronic batch record (Correct)
  • Digital signature (Correct)
  • Availability check

Answer : Approved master recipes Electronic batch record Digital signature

SAP C_TB1200_88 Certified Associate SAP Business One Exam Set 4

A customer has been using planning strategies 30 (production by lots) and 10 (anonymous make-to-stock production) in SAP ECC. The customer wishes to move in part to planning strategy 40 (planning with final assembly). The issue of consumption has an effect here for the first time. Which properties apply for consumption with planning strategy 40? (Choose two.)


Options are :

  • Consumption can reduce the originally planned production quantity.
  • onsumption creates a static and binding assignment, between the planned independent requirements recorded in advance and the customer requirements that arrive, for the entire procurement process.
  • Consumption can result in the subsequent specification and adjustment of planning elements in terms of quantity and date, by means of customer orders that arrive (Correct)
  • Consumption can lead to an increase of the originally planned overall production quantity. (Correct)

Answer : Consumption can result in the subsequent specification and adjustment of planning elements in terms of quantity and date, by means of customer orders that arrive Consumption can lead to an increase of the originally planned overall production quantity.

What options for selecting a routing exist when creating a production order? (Choose three.)


Options are :

  • Manual selection (Correct)
  • Selection on the basis of the routing number in the material master for the material to be produced
  • Selection on the basis of the production control profile (Correct)
  • Automatic selection, controlled via settings in Customizing (Correct)

Answer : Manual selection Selection on the basis of the production control profile Automatic selection, controlled via settings in Customizing

Which properties does ECC Master Production Scheduling (MPS) have? (Choose three.)


Options are :

  • MPS items can be defined on MRP Area level (Material Requirements Planning Area). (Correct)
  • MPS items can be taken into consideration by a standard MRP run (Material Requirements Planning).
  • Non-MPS items can be taken into consideration by an MPS run. (Correct)
  • MPS items can be defined on plant level. (Correct)

Answer : MPS items can be defined on MRP Area level (Material Requirements Planning Area). Non-MPS items can be taken into consideration by an MPS run. MPS items can be defined on plant level.

SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 2

The user you advise requests that you make it possible for the user to produce materials for stock, for customer orders, projects, orders and cost centers with production orders. Where can you make settings to ensure these options?


Options are :

  • Valuation variant.
  • Production scheduling profile.
  • Serial number profile.
  • Settlement profile. (Correct)

Answer : Settlement profile.

A new material with the following properties is to be recorded in SAP ECC. the material is kept in stock, is externally procured, and is used as a component in the bills of material for various final products. However, this material may not be purchased directly. Which standard SAP material type would you use?


Options are :

  • FERT (finished product)
  • ROH (raw material) (Correct)
  • NLAG (non-stock material)
  • HAWA (trading good)

Answer : ROH (raw material)

Which of the following functions occur when a production order is created? (Choose three.)


Options are :

  • Calculating the lead time for the production order (Correct)
  • Selecting and copying a routing (Correct)
  • Copying a document that is assigned to the material master for the product to be produced
  • Selecting and copying a bill of material (Correct)

Answer : Calculating the lead time for the production order Selecting and copying a routing Selecting and copying a bill of material

SAP C_TADM51_731 Certified Technology Associate System Exam Set 4

Which of the following aspects characterize repetitive manufacturing in a manufacturing plant? (Choose three.)


Options are :

  • Continuous material consumption, production flow and output (Correct)
  • Automatic line loading by capacity limits across all production lines
  • Period-based planning of the quantities to be produced (Correct)
  • Production without using production orders and without status management E. Shop fabrication (Correct)

Answer : Continuous material consumption, production flow and output Period-based planning of the quantities to be produced Production without using production orders and without status management E. Shop fabrication

Which of the following statements about consumption are correct? (Choose two)


Options are :

  • Consumption can take place between order reservations and planned independent requirements, depending on the strategy. (Correct)
  • Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group. (Correct)
  • Consumption takes place on the material level between the planned independent requirements and the planned orders.
  • Consumption is restructured with the planning run.

Answer : Consumption can take place between order reservations and planned independent requirements, depending on the strategy. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.

A material was planned in the context of SAP ECC material requirements planning and the MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares the two. Which of the following statements are true for the two lists at this stage? (Choose two.)


Options are :

  • The stock/requirements list displays the production order. (Correct)
  • The MRP list displays the production order.
  • The MRP list has the status "processed".
  • The stock/requirements list was updated at the precise time it was accessed. (Correct)

Answer : The stock/requirements list displays the production order. The stock/requirements list was updated at the precise time it was accessed.

SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 6

An enterprise wants to absorb the uncertainty caused by fluctuating demand for a finished product by means of a buffer variable in SAP ECC. They suggest a dynamic safety stock. What specifications are used to calculate the dynamic safety stock?


Options are :

  • The static safety stock per day and the safety time
  • The average daily demand and the safety time
  • The static safety stock and a material forecast
  • The average daily demand and the desired days supply (Correct)

Answer : The average daily demand and the desired days supply

For a specific end product, you want to use a planning time fence and fixing type 1 to ensure that the planning situation in SAP ECC calms down in a short-term time window. Two customer orders arrive at short notice and their receipts should really be within the planning time fence, due to their date/time. Which statement is true with this scenario?


Options are :

  • The MRP controller has no possibility of creating planned orders within the planning time fence.
  • Newly created planned orders cannot be created by requirements planning before the end of the planning time fence, at the earliest. (Correct)
  • Requirements planning only examines changes that are relevant to scheduling within the planning time fence; the customer orders are covered in time.
  • Within the planning time fence, the newly created planned orders are automatically frozen by requirements planning (roll forward).

Answer : Newly created planned orders cannot be created by requirements planning before the end of the planning time fence, at the earliest.

Which of the following statements is true for the simulation mode in the context of material requirements planning in SAP ECC?


Options are :

  • The simulation mode opens the analysis of the delay time. Manual rescheduling of the receipt in the finished product and subsequent requirements planning lead to a solution that is feasible from the requirements planning perspective. However, this solution may lead to a date/time violation in the finished product. (Correct)
  • Assuming a delay time in the critical path, the simulation mode triggers multilevel bottom-up scheduling through to the finished product, which therefore receives a delayed receipt.
  • The simulation mode is used in scenarios in which requirements planning created the procurement element prematurely in terms of demand.
  • The simulation mode represents an interactive multilevel form of planning, the result of which is automatically posted to the database after the planning run.

Answer : The simulation mode opens the analysis of the delay time. Manual rescheduling of the receipt in the finished product and subsequent requirements planning lead to a solution that is feasible from the requirements planning perspective. However, this solution may lead to a date/time violation in the finished product.

SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 2

The Service Desk is available as part of the SAP Solution Manager. Which functions are included in the scope of the Service Desk? (Choose two.)


Options are :

  • Process for processing messages (Correct)
  • Managing SAP Notes (Correct)
  • Troubleshooting
  • SAP Help

Answer : Process for processing messages Managing SAP Notes

Which of the following functions are available in the SAP ECC system for leveling overloads in individual work centers with the capacity planning tools? (Choose three.)


Options are :

  • Setup time reduction (Correct)
  • Midpoint scheduling (Correct)
  • Finite capacity scheduling (Correct)
  • Batch size optimization

Answer : Setup time reduction Midpoint scheduling Finite capacity scheduling