SAP C_TSCM42_66 Certified Associate - Production Exam Set 2

You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40. Which sequence category do you use to create the second sequence in the system?


Options are :

  • Finish-start relationship
  • Parallel sequence
  • Alternative sequence (Correct)
  • Standard sequence

Answer : Alternative sequence

SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 1

During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system. Which of the following procurement type properties are valid? (Choose two)


Options are :

  • If procurement type E (in-house production) is set, external procurement may still be possible, depending on the material type. (Correct)
  • Procurement types E (in-house production), F (external procurement), or X (both procurement types) can be selected for a material independent of the material type.
  • If both procurement types are allowed with entry X (both procurement types), requirements planning assumes in-house production. (Correct)
  • Procurement types E (in-house production) and F (external procurement) always have to be further refined with special procurement types.

Answer : If procurement type E (in-house production) is set, external procurement may still be possible, depending on the material type. If both procurement types are allowed with entry X (both procurement types), requirements planning assumes in-house production.

In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data: - Start: 7:00:00 a.m. - End: 3:00:00 p.m. - Break duration: 1 hour - Rate of utilization: 80% - Overload: 110% - Number of individual capacities: 1 How large is the standard available capacity?


Options are :

  • 7 hours
  • 5.6 hours (Correct)
  • 8 hours
  • 6.16 hours

Answer : 5.6 hours

What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)


Options are :

  • Reservations are no longer relevant for material requirements planning. (Correct)
  • Confirmations are no longer possible.
  • Capacity requirements are set to null. (Correct)
  • The order is no longer relevant for material requirements planning. (Correct)

Answer : Reservations are no longer relevant for material requirements planning. Capacity requirements are set to null. The order is no longer relevant for material requirements planning.

SAP C_TSCM52_66 Certified Associate Financial Accounts Test Set 1

Which of the following master data can be used with process orders? (Choose three)


Options are :

  • Master recipes (Correct)
  • Production/resource tools
  • Resources (Correct)
  • Production versions (Correct)
  • Serial numbers

Answer : Master recipes Resources Production versions

What can you use to organize material staging for production orders? (Choose three)


Options are :

  • Material documents
  • Pull list (Correct)
  • KANBAN (Correct)
  • Transfer orders (Correct)

Answer : Pull list KANBAN Transfer orders

In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type. What does a firming type define? (Choose two)


Options are :

  • Handling new procurement proposals that need to be created due to new requirements within the planning time fence. (Correct)
  • Handling existing procurement proposals within a planning time fence. (Correct)
  • Handling new requirements within the planning time fence.
  • Handling existing procurement proposals outside the planning time fence.

Answer : Handling new procurement proposals that need to be created due to new requirements within the planning time fence. Handling existing procurement proposals within a planning time fence.

SAP C_TSCM62_65 Certified Associate - Order Fulfilment Exam Set 2

You want to use the function "Read PP master data" in the production order. However, while calling the function you receive an error message. What could be the reason?


Options are :

  • Goods movements have been posted. (Correct)
  • The production order has been released.
  • Order papers have been printed.
  • The material availability check has been performed.

Answer : Goods movements have been posted.

What is SAP Solution Manager?


Options are :

  • A transaction in the SAP ECC system
  • A managed system in a system landscape
  • An add-on industry solution
  • A standalone system that communicates with other systems in a system landscape (Correct)

Answer : A standalone system that communicates with other systems in a system landscape

Which of the following features are offered by MRP areas in SAP ECC? (Choose two)


Options are :

  • Make-to-order production is supported by storage location MRP areas.
  • An MRP area may include different storage locations. (Correct)
  • A storage location may be assigned to different MRP areas.
  • Subcontracting is supported by MRP areas. (Correct)

Answer : An MRP area may include different storage locations. Subcontracting is supported by MRP areas.

SAP C_TADM51_731 Certified Technology Associate System Exam Set 7

In which of the following objects can you activate back flushing for production orders? (Choose three)


Options are :

  • Material master (component) (Correct)
  • Routing (Correct)
  • Material master (finished product)
  • Work center (Correct)

Answer : Material master (component) Routing Work center

SAP C_TSCM42_66 Certified Associate Production Planning Exam Set 5

When modeling in-house production using SAP ECC, on which business levels can you create a bill of material (BOM)? (Choose two)


Options are :

  • At the company code level
  • At the plant level (Correct)
  • At the business area level
  • At the client level (Correct)

Answer : At the plant level At the client level

The company you advise wants to carry out the material availability check automatically in the production order at various points in time. Which of the following options would you recommend? (Choose two.)


Options are :

  • Goods receipt for the product produced with the order
  • Confirmation of the operation that the materials being checked are assigned to
  • Release of the production order (Correct)
  • Creation of the production order (Correct)

Answer : Release of the production order Creation of the production order

What are characteristics of repetitive manufacturing? (Choose three)


Options are :

  • Continuous material consumption, production flow and output (Correct)
  • Period-based planning of the quantities to be produced (Correct)
  • Production without using production orders and without status management (Correct)
  • Shop fabrication
  • Automatic line loading based on capacity limits across all production lines

Answer : Continuous material consumption, production flow and output Period-based planning of the quantities to be produced Production without using production orders and without status management

SAP C_TSCM52_66 Certified Associate Financial Accounts Test Set 3

Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order. Which BOM item category must you set to fulfill this requirement?


Options are :

  • D (document item)
  • M (phantom material)
  • N (non-stock item) (Correct)
  • E (external procurement)

Answer : N (non-stock item)

Which function is supported by production orders?


Options are :

  • Automatic creation of transfer orders at order release (Correct)
  • Automatic printing of order documents at order creation
  • Automatic selection of a work center at order release
  • Automatic reading of PP master data at order release

Answer : Automatic creation of transfer orders at order release

Which repetitive manufacturing options can you use to carry out line loading in the SAP ECC system, and thus generate run schedule quantities (RSQ) from normal planned orders? (Choose three)


Options are :

  • Automatic selection of the production version in material requirements planning (MRP) using the selection methods setting (Correct)
  • Automatic selection of the production line assigned to the MRP group used during material requirements planning (MRP)
  • Manual assignment of planned production quantities in a planning table (Correct)
  • Automatic selection of the production version by applying quota arrangement records in material requirements planning (MRP) (Correct)

Answer : Automatic selection of the production version in material requirements planning (MRP) using the selection methods setting Manual assignment of planned production quantities in a planning table Automatic selection of the production version by applying quota arrangement records in material requirements planning (MRP)

SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 2

What do you have to consider when you use SAP ECC long-term planning (LTP)? (Choose two)


Options are :

  • LTP creates purchase requisitions for external procurement.
  • Reorder point planned materials can be included in LTP. (Correct)
  • LTP focuses on the operational planning of important components.
  • A planning scenario must be released before it can be used in LTP. (Correct)

Answer : Reorder point planned materials can be included in LTP. A planning scenario must be released before it can be used in LTP.

Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)


Options are :

  • Setting the status technically complete (TECO) (Correct)
  • Confirming the operation (Correct)
  • Reducing the order quantity (Correct)
  • Rescheduling the operation
  • Posting the goods receipt for the production order

Answer : Setting the status technically complete (TECO) Confirming the operation Reducing the order quantity

Which of the following functions does SAP Supply Chain Management (SCM) offer?


Options are :

  • Product development, safety, quality, and maintenance
  • Communication with customers through different interaction channels
  • Planning of supply chains across company boundaries (Correct)
  • Optimization of the procurement strategy with the supplier pool

Answer : Planning of supply chains across company boundaries

SAP C_TFIN52_66 Certify Associate Financial Accounting Exam Set 3

Which Customizing element controls the determination of planned costs in production orders?


Options are :

  • Settlement profile
  • Calculation procedure
  • Accounting type
  • Costing variant (Correct)

Answer : Costing variant

In what sequence are the steps of material requirements planning performed in SAP ECC?


Options are :

  • 1. Calculation of safety stock 2. Lot sizing 3. Scheduling 4. Determination of the procurement type
  • 1. Net requirements calculation 2. Lot sizing 3. Determination of the procurement type 4. Scheduling (Correct)
  • 1. Availability check 2. Lot sizing 3. Determination of the procurement type 4. Scheduling
  • 1. Net requirements calculation 2. Lot sizing 3. Scheduling 4. Determination of the procurement type

Answer : 1. Net requirements calculation 2. Lot sizing 3. Determination of the procurement type 4. Scheduling

What functions can you use for sub operations? (Choose two)


Options are :

  • Costing (Correct)
  • Material component allocation
  • Capacity planning (Correct)
  • Production/Resource tools allocation

Answer : Costing Capacity planning

SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 5

The availability check during production order creation should use a different scope of check than during order release. How can you fulfill this requirement?


Options are :

  • Maintain appropriate availability checking rules in the production scheduling profile.
  • Maintain appropriate checking rules in checking control for order creation and order release. (Correct)
  • Maintain an appropriate availability checking group in the material master.
  • Maintain appropriate availability checking rules in the order type-dependent parameters.

Answer : Maintain appropriate checking rules in checking control for order creation and order release.

Which of the following are characteristics of ECC master production scheduling (MPS)? (Choose three)


Options are :

  • MPS items can be defined on plant level. (Correct)
  • Non-MPS items can be taken into consideration by an MPS run. (Correct)
  • MPS items are planned in a standard MRP run.
  • The planning of MPS and non-MPS items is always carried out in one planning run.
  • MPS items can be defined on MRP area level. (Correct)

Answer : MPS items can be defined on plant level. Non-MPS items can be taken into consideration by an MPS run. MPS items can be defined on MRP area level.

What sequence do you follow in master data maintenance to define the production of a material?


Options are :

  • Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
  • Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing (Correct)
  • Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing
  • Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center

Answer : Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing

SAP C_TB1200_88 Certified Associate SAP Business One Exam Set 5

Which of the following master data is necessary for the creation of material reservations for production orders?


Options are :

  • Routings
  • Production/resource tools
  • Material master records (Correct)
  • Production versions

Answer : Material master records

What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)


Options are :

  • Approved master recipes (Correct)
  • Availability check
  • Electronic batch record (Correct)
  • Digital signature (Correct)

Answer : Approved master recipes Electronic batch record Digital signature

Where in the SAP ECC system can you define production versions?


Options are :

  • In the material master (Correct)
  • In the work center
  • In the bill of material
  • In the routing

Answer : In the material master

SAP C_TADM51702 Certified Technology Associate - System Exam Set 5

An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon should be set equally for all materials by default. However, some materials need to have a different planning horizon. Which procedure do you recommend for setting the planning horizon?


Options are :

  • Set the planning horizon in the MRP groups and assign deviant entries via the plant parameter settings in Customizing.
  • Set the planning horizon in the plant parameters in Customizing and store deviant entries in the material masters for corresponding materials.
  • Set the planning horizon in the MRP groups in Customizing and store deviant entries in the material masters for the corresponding materials.
  • Set the planning horizon in the plant parameters in Customizing and assign deviant entries via the MRP groups for the corresponding materials. (Correct)

Answer : Set the planning horizon in the plant parameters in Customizing and assign deviant entries via the MRP groups for the corresponding materials.