C_TSCM42_66 SAP Certified Associate Production Planning Exam Set 5

In SAP ECC, you want to give the production in-house again for the total production of the magazine. Fields in many size-dependent should be in the building production time filled in when creating a material master record for the final product. These fields can be saved by upgrading to a scheduling result for the given route. Nonew that you think might be significant changes in the production time in the routing and make a decision on updating the material. What are the problems that can cause it?


Options are :

  • During important data plans with planning requirements, depending on the requirements of the requesting component materials accounts at the wrong time.
  • Requirements Planning meets a message exception in the main scheduling data, as the material master settings do Nonet match the result of the planning of the route.
  • Subsequent capacity planning is None longer possible due to outdated planning parameters.
  • None
  • Turnaround planning, which is converted at the time of the planned order to place a production order (appearance), can Nonet be based on inaccurate important data.

Answer : During important data plans with planning requirements, depending on the requirements of the requesting component materials accounts at the wrong time.

In your business planning strategy is used in the management of SAP ECC question, which is based on consumption. Which of the following statements is true about consumption? (Choose two.)


Options are :

  • Consumption can be between order bookings planned independent requirements, depending on the strategy.
  • Consumption situation is dynamic and always rebuilt from the planning run.
  • Consumption always occurs at product level between the planned independent requirements and planned orders.
  • Parameters consumption (mode interval consumption and consumption) can be included in the main component or material in the MRP group installed.

Answer : Consumption can be between order bookings planned independent requirements, depending on the strategy. Parameters consumption (mode interval consumption and consumption) can be included in the main component or material in the MRP group installed.

C_TSCM42_66 SAP Certified Associate Production Planning Exam Set 6

What data are the basis for calculating the required capacity for the operation? (Choose three.)


Options are :

  • Formula (lanes center)
  • Internal quality (material master)
  • Standard values (routing)
  • Operations control (routing) button

Answer : Formula (lanes center) Standard values (routing) Operations control (routing) button

Material is planned within SAP MRP. The planner then manually material conversion functions planned order processing order in production. MRP controller Nonew access the current stock / requirements list and the MRP list for the material and compares these two lists. What you need to consider the two lists at the moment? (Choose two)


Options are :

  • MRP list shows the production sequence.
  • Statement of needs / stocks shows a production order.
  • MRP List has the status of "processed".
  • Program requirements / inventory is updated at the time it was opened.

Answer : Statement of needs / stocks shows a production order. Program requirements / inventory is updated at the time it was opened.

What you need to consider consumption? (Choose two)


Options are :

  • Use takes place in the material between the planned independent requirements and planned orders.
  • Consumption range from booking order planned independent requirements, depending on the strategy.
  • Parameters consumption (mode interval consumption and consumption) can be mounted on the main recording material or MRP group.
  • Consumption rebuilt with planning run.

Answer : Consumption range from booking order planned independent requirements, depending on the strategy. Parameters consumption (mode interval consumption and consumption) can be mounted on the main recording material or MRP group.

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 1

In the analysis of the SAP order report for a planned order for the finished product, you will Nonetice that one of the Nonedes will Nonet be available in time for the planned final assembly due to the automatic planning for the future. Which planning procedures you will use to address the problem with a view to a solution that will allow for the planning needs?


Options are :

  • Total online scheduling
  • Multi-level scheduling a call with the option simulation mode
  • None
  • Interactive planning a trip to the delayed assembly
  • Multi-level planning issue the results are displayed for saving option

Answer : Multi-level scheduling a call with the option simulation mode

What are the names of the objects for the integration of production orders? (Choose two)


Options are :

  • Instructions
  • control recipes
  • control instructions
  • PI sheets

Answer : Instructions control instructions

You choose the basic data for production orders using production versions. What information is included in the production version?


Options are :

  • Control parameters for the selection of routes and specifications
  • None
  • The standard to use
  • The date of the explosion to a routing and specification
  • Alternative routing capabilities and specifications that will be used

Answer : Alternative routing capabilities and specifications that will be used

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 2

The company recommends to automatically check the availability of the material in the production order at different points in time. Which of the following would you recommend? (Choose two.)


Options are :

  • Proof of order produced product
  • Create production order
  • Release Production Order
  • Confirmation of the operation that shall be assigned to the tested materials

Answer : Create production order Release Production Order

Which of the following requirements are supported with the order?


Options are :

  • None
  • documents by order of the bond
  • Using the product / resource tool
  • Using a set of standard operations
  • production documentation electronic batch record

Answer : production documentation electronic batch record

During processing, production orders to determine planned and actual costs. Which of the following objects can assemble these charges? (Choose two)


Options are :

  • production order
  • The cost price of the product collector
  • The planned order
  • work center

Answer : production order The cost price of the product collector

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 3

Which of the following requirements for the manufacturer to be supported by the production process? (Choose three.)


Options are :

  • Production in charge amounts.
  • Variable calculation amount of material (yield, the use of the material).
  • Material requirements planning for the production of raw materials.
  • Master recipe based on production.

Answer : Production in charge amounts. Variable calculation amount of material (yield, the use of the material). Master recipe based on production.

From which point you can None longer use the basic user data PP in the production order?


Options are :

  • Once the print order of documents.
  • After the appointment component quantity of material confirmed by checking the availability of conductive material.
  • None
  • With the release of the production order.
  • After the initial publication of the movement of goods or confirmation

Answer : After the initial publication of the movement of goods or confirmation

The company wants to follow SAP ECC requirement planning NETPL procedure (net change planning in the planning horizon). The planning horizon should be set the same for all standard equipment. However, some materials have to have a different time horizon. What procedure do you recommend for installation planning horizon?


Options are :

  • Set the planning horizon in the MRP groups in Customizing and store records in a different material molds for the relevant materials.
  • Set assign the planning horizon in the plant parameters in Customizing and abNonermal uptake via MRP groups for the respective materials.
  • None
  • Set the planning horizon in the plant parameters in Customizing and store records in a different material molds for the relevant materials.
  • Set the planning horizon in the MRP groups and assign different recording by setting main parameters in Customizing.

Answer : Set assign the planning horizon in the plant parameters in Customizing and abNonermal uptake via MRP groups for the respective materials.

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 4

What types of objects can be changed by changing the Bureau of Engineering? (Choose three.)


Options are :

  • material Master
  • bill of materials
  • To do list
  • work center

Answer : material Master bill of materials To do list

Check the availability of the process of creating the production order, using different scale test than during order release. How can you meet this requirement?


Options are :

  • Support the relevant rules for checking the availability of the nature of the parameters depending on the sequence.
  • Maintain the corresponding group in the material availability inputs.
  • Maintain current regulations availability in production profile.
  • Maintaining appropriate rules validation check control for order creation and order release.
  • None

Answer : Maintaining appropriate rules validation check control for order creation and order release.

You use the planning time fence and close type 1. You receive a sales order with the material availability date in the fence planning. What to consider in this scenario?


Options are :

  • Planning requirements considers only changes the schedule within the planning time fence are relevant.
  • None
  • Planned orders shifted by planning requirements to the end of the planning time fence.
  • Planned orders are created within the planning time fence and zhdaetsya automatically scheduling needs.
  • MRP controller can Nonet create planned orders for sampling planning time.

Answer : Planned orders shifted by planning requirements to the end of the planning time fence.

Which of the following objects, which can be activated to backwash components if you want to use this feature during the order confirmation? (Choose three.)


Options are :

  • Material Master (component)
  • routing
  • work center
  • The planning of the production profile

Answer : Material Master (component) routing work center

Which of the following basic data necessary for creating material for the production of orders?


Options are :

  • None
  • production versions
  • Material master records
  • Production tools / resources
  • routings

Answer : Material master records

Where you can determine the actual recipients of the costs of the production order?


Options are :

  • None
  • In the embodiment, the calculation
  • calculated profile
  • In the embodiment, evaluation
  • The production profile

Answer : calculated profile

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 1

What kind of data can be placed directly through the interface Plant data acquisition (PP-PDC)?


Options are :

  • Nonetification of maintenance
  • receipt of goods
  • goods issues
  • recognition
  • None

Answer : recognition

You will want to reduce the uncertainty caused by the fluctuations in the requirements for the final product with a dynamic safety stock in SAP ECC. Which is based on the characteristics of the calculation of stocks on a dynamic security?


Options are :

  • None
  • Static safety stock and forecasting equipment
  • The average daily demand and the required coverage range
  • Average daily demand, and the security of the times
  • Static safety stock on the date and time, security

Answer : The average daily demand and the required coverage range

What to consider when using long-term planning SAP (LTP)? (Choose two)


Options are :

  • LTP focuses on the operational planning of major components.
  • LTP creates purchase orders for external procurement.
  • planning scenario must be released before it can be used in the LTP.
  • Sequencing planned point materials can be incorporated in LTP.

Answer : planning scenario must be released before it can be used in the LTP. Sequencing planned point materials can be incorporated in LTP.

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 2

What is supported by production orders?


Options are :

  • Automatic selection of the work in the release order
  • Automatic printing of the order of documents on the establishment of order
  • Automatic reading master data with PP order release
  • Automatic creation of transfer orders when you release order
  • None

Answer : Automatic creation of transfer orders when you release order

Which statement is correct for the ESA-term plan (LTP)? (Choose two.)


Options are :

  • Sequencing planned point materials can be incorporated into the ongoing planning.
  • Long-term planning is usually the operational planning of major components.
  • scenario planning should be released for use in long-term planning.
  • In the case of external procurement, long-term planning generates purchase orders.

Answer : Sequencing planned point materials can be incorporated into the ongoing planning. scenario planning should be released for use in long-term planning.

Which of the following is correct the following statements about the SAP Solution Manager?


Options are :

  • None
  • Solution Manager is a satellite system in the system landscape.
  • Solution Manager is an add-industry solution.
  • Solution Manager is part of the SAP system.
  • Solution Manager is a standalone system that interacts with other systems in the system landscape.

Answer : Solution Manager is a standalone system that interacts with other systems in the system landscape.

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 3

Which is a feature in SAP ECC mode needs Simu-translational material planning?


Options are :

  • It calculates the delay that may occur in the planning process.
  • This is true with the exception of messages from the component to the end product.
  • It sends the planning results to the database automatically.
  • None
  • It is planning a multi-level bottom-up.

Answer : It calculates the delay that may occur in the planning process.

Which of the following activities needed to check for containers, which can be performed automatically when the production order is released?


Options are :

  • Activate allocate the availability and the overall profile of the production profile.
  • Set the final planning indicator and assign a validation rule should be checked in the workplace for work.
  • None
  • Designate an appropriate rule to check the availability of the recording material for the product.
  • Activate availability and a common profile for the control combination for checking the type / plant.

Answer : Activate availability and a common profile for the control combination for checking the type / plant.

What element controls the Customizing definition of the planned costs in production orders?


Options are :

  • cost option
  • profile calculation
  • None
  • calculation procedure
  • Accounting type

Answer : cost option

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 4

In a sequence of steps performed in Material Requirements Planning SAP?


Options are :

  • 1. The net-demand calculation 2. Lot dimensioning 3. Scheduling 4. Determination of the nature of the procurement
  • 1. The net requirements calculation 2. Lot sizing 3. Determine the type of procurement 4. Planning
  • None
  • 1. Calculation of safety stock dimensioning 2. Offer 3. Planning 4. Determination of the nature of the procurement
  • 1. Check availability 2. Lot sizing 3. Determine the type of procurement 4. Planning

Answer : 1. The net requirements calculation 2. Lot sizing 3. Determine the type of procurement 4. Planning