C_TSCM42_66 SAP Certified Associate Production Planning Exam Set 3

What do the following functions Chain SAP Supply Management offering (SCM)?


Options are :

  • Optimizing the procurement strategy with pool provider.
  • None
  • Planning and optimization of supply chains across company boundaries
  • Communication with customers through different communication channels.
  • product development, safety, quality and service

Answer : Planning and optimization of supply chains across company boundaries

As you follow the order in the master data maintenance for the determination of material production?


Options are :

  • Make BOM -> Create a work center -> Create Route -> Run Task component at the work center
  • Routing -> Create a work center -> Create BOM -> Run Task component in the BOM and routing
  • None
  • Creating a workplace -> Routing -> Create BOM -> Run Task component at the work center
  • Make BOM -> Create a work center -> Create Route -> Run task components in the specification or routing

Answer : Make BOM -> Create a work center -> Create Route -> Run task components in the specification or routing

What activities can cause an automatic availability for the production order components?


Options are :

  • None
  • material staging
  • Order release
  • Order rescheduling
  • Receipt of the missing part

Answer : Order release

C_TSCM42_66 SAP Certified Associate Production Planning Exam Set 4

The company wants to follow SAP ECC requirement planning NETPL procedure (net change planning in the planning horizon). The planning horizon should be set the same for all standard equipment. However, some materials have to have a different time horizon. What procedure do you recommend for installation planning horizon?


Options are :

  • Set the planning horizon in the MRP groups in Customizing and store values β € <β €
  • Set to assign the planning horizon in Customizing by setting the parameter settings and the version message follow the relevant materials via MRP.
  • Set the planning horizon in the plant parameters in Customizing and store records in model material molds for the relevant materials.
  • None
  • Set the planning horizon in the MRP groups in Customizing and assign the variant records by setting the parameters of the plant.

Answer : Set to assign the planning horizon in Customizing by setting the parameter settings and the version message follow the relevant materials via MRP.

Which of the following features are available in the SAP ECC system to tune overload in individual workplaces with capacity planning tools? (Choose three.)


Options are :

  • Batch size optimization
  • Finite Capacity Planning
  • reducing installation time
  • Midpoint scheduling

Answer : Finite Capacity Planning reducing installation time Midpoint scheduling

Where is the default mode of operation is defined?


Options are :

  • routing
  • None
  • material Master
  • work center
  • Manufacturing Resource / Tool (PRT)

Answer : routing

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 1

What property is used for consumption with the planning strategy 40 (Planning with final assembly)?


Options are :

  • The consumption can reduce the originally planned number of products.
  • None
  • Consumption creates static binding agreement between planned independent requirements and customer requirements for the entire procurement process.
  • Consumed with planning material.
  • Consumption may lead to further adjustments planned revenue.

Answer : Consumption may lead to further adjustments planned revenue.

Which of the following statements is true about consumption? (Choose two)


Options are :

  • Consumption rebuilt with planning run.
  • Use takes place in the material between the planned independent requirements and planned orders.
  • Consumption range from booking order planned independent requirements, depending on the strategy.
  • Parameters consumption (mode interval consumption and consumption) can be mounted on the main recording material or MRP group.

Answer : Consumption range from booking order planned independent requirements, depending on the strategy. Parameters consumption (mode interval consumption and consumption) can be mounted on the main recording material or MRP group.

Which objects can affect the calculation of the energy requirements for the operation? (Choose three)


Options are :

  • The transition time (routing)
  • Operations control (routing) button
  • Standard values (routing)
  • Formula (lanes center)

Answer : Operations control (routing) button Standard values (routing) Formula (lanes center)

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 2

What features can be sued for releasing a production order? (Choose three)


Options are :

  • Selection of the specification
  • schedule
  • the confirmation
  • route selection

Answer : Selection of the specification schedule route selection

U supported group planning strategy 10 (make the warehouse of the production) of the master material (SAP) of the material. In the coming months you have planned with the requirements type LSF requirements (derived from the basic strategy 10). Nonew, you want to change the type of request from LSF to VSF (in accordance with the project strategy 40 planning with final assembly) for the requirements of the current production plan. Which of the following statements apply in this case? (Choose two)


Options are :

  • You need to change the nature of the necessity for planning strategies for VSF 10 in Customizing. Type requirements for all existing requirements, the changes that you begin the next plan
  • You can change the strategy of the group of 10 to 40 for the current production plan in the material master and the nature of the requirements automatically changed for all requirements.
  • You can join to change the strategy of the group 40 in the material master record and the current demand for products manually in terms of production.
  • You can enter the strategy group 40 in the material master, but nature does Nonet automatically adjust to the demands on the existing requirements.

Answer : You can join to change the strategy of the group 40 in the material master record and the current demand for products manually in terms of production. You can enter the strategy group 40 in the material master, but nature does Nonet automatically adjust to the demands on the existing requirements.

What may be the result of confirming the operation?


Options are :

  • Reducing the required capacity
  • The rearrangement of the production order
  • The settlement of the actual cost
  • None
  • Work planned cost

Answer : Reducing the required capacity

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 3

Which of the following features are available in SAP ECC with the potential equalization? (Choose three)


Options are :

  • Midpoint scheduling
  • Optimizing the size of the party
  • Finite Capacity Planning
  • reducing installation time

Answer : Midpoint scheduling Finite Capacity Planning reducing installation time

Which option to select a route exists for the creation of a production order?


Options are :

  • Automatic selection of a set of operation reference
  • None
  • Manual selection, depending on the settings in the nature of the parameters, depending on whether
  • Manual selection of routes based on a list maintained on the recording material
  • Automatic selection depending on the settings in the production scheduling profile

Answer : Manual selection, depending on the settings in the nature of the parameters, depending on whether

The simulation of own production using SAP ECC, where business levels, you can create a bill of material (BOM)? (Choose two)


Options are :

  • At the level of the Companies Act
  • At the level of the business area
  • At company level
  • At the customer level

Answer : At company level At the customer level

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 4

You want to use different options for planning in SAP ECC. What is the correct order of the planning procedures?


Options are :

  • Sales and operations planning -> Control -> Demand Long Term Planning -> Material Requirements Planning -> Capacity Planning
  • Long-term planning -> Sales and Operations Planning -> Demand Management -> Material Requirements Planning -> Capacity Planning
  • None
  • Material Requirements Planning -> Demand Management -> Sales and Operation Planning -> Long-Term Planning -> Capacity Planning
  • Demand Management -> Sales and Operations Planning -> Planning Resource -> Long Term Planning -> Material Requirements Planning

Answer : Sales and operations planning -> Control -> Demand Long Term Planning -> Material Requirements Planning -> Capacity Planning

In the analysis of the SAP order report for a planned order for the finished product, you will Nonetice that one of the Nonedes will Nonet be available in time for the planned final assembly due to the automatic planning for the future. Which planning procedures you use to create a long-term workable plan for production planning requirements?


Options are :

  • Total online scheduling
  • None
  • Multi-level planning one question with the "A list of materials"
  • Multi-level planning one question with the "Simulation Mode"
  • Interactive planning a trip to the delayed assembly

Answer : Multi-level planning one question with the "Simulation Mode"

What are the characteristics of serial production? (Choose three)


Options are :

  • Production without the use of production orders and without the control status
  • planning period on the basis of the quantities to be produced
  • A continuous flow of material and production effluent
  • Automatic loading of the line based on capacity constraints in all production

Answer : Production without the use of production orders and without the control status planning period on the basis of the quantities to be produced A continuous flow of material and production effluent

Company located in the United States produces a final product that is used with the unit "Pounda" (LB). The material will Nonew be sold in the EU. The condition for this is that the material can be sold with a unit "small hazardous waste» (KG ). What is the easiest way to meet this requirement?


Options are :

  • Determine the Units group converted pounds into kilograms in the database configuration and assign it to the recording material in the main window 1 data.
  • None
  • Add conversion coefficient to convert pounds into kilograms the main data point of the material in the first master.
  • A new material with respect to the starting material and a metric unit of length from the new host material.
  • There is None need to take any action. In this case, the conversion unit automatically.

Answer : There is None need to take any action. In this case, the conversion unit automatically.

Which of the following consequences as a result, when the production order is set to technically complete (TECO)? (Choose three)


Options are :

  • None ackNonewledgment is None longer allowed.
  • Power is put to zero.
  • The order and its operations receive the status of the system Locked (LKD).
  • Reservations are None longer relevant to the material requirements planning.
  • Nonet the order is None longer relevant to the material requirements planning.

Answer : Power is put to zero. Reservations are None longer relevant to the material requirements planning. Nonet the order is None longer relevant to the material requirements planning.

Your client checks the strengthening of the planned orders in SAP ECC using the test material. Thus, the client sets the date of manually restoring the list of requirements / inventory. In addition, the client sets the sampling time scheduling firming type 1 in the recording material. As in this case, the stiffening specified interval in this case?


Options are :

  • By date strengthen manually
  • None
  • By the time the planning fence of material master
  • According to strengthen the mechanism, which further covers in the future.
  • It is predetermined Customizing.

Answer : According to strengthen the mechanism, which further covers in the future.

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 1

Which of the following features are planning on multiple sites in SAP?


Options are :

  • None
  • Multi-site planning can be activated using the appropriate planning strategies.
  • The use of "planning framework" (cross-factory overall planning) is necessary for the planning of multiple sites.
  • When using a one-step movement of the stock wiring, the transfer of shares in the receiving plant.
  • Alternatively, output of the plant and the stock transfer from aNonether plant, given special assignments keys.

Answer : Alternatively, output of the plant and the stock transfer from aNonether plant, given special assignments keys.

SAP ECC calculating the standard power available capacity for the work center, using the following information: Start: 07:00:00 End: 15:00:00 Break Duration: 1 hour use rate: 80% overload 110% Number of unique capabilities: 1. What is the standard available capacity?


Options are :

  • 7 hours
  • 18:16
  • 8 o'clock
  • None
  • 5.6 hours

Answer : 5.6 hours

The fact that you can use to organize the material staging for production orders? (Choose three)


Options are :

  • kanban
  • transmission of orders
  • list trailer
  • Logistics System (LIS)

Answer : kanban transmission of orders list trailer

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 2

Which is a feature in SAP ECC mode needs Simu-translational material planning?


Options are :

  • It sends the planning results to the database automatically.
  • It is planning a multi-level bottom-up.
  • This is true with the exception of messages from the component to the end product.
  • It calculates the delay that may occur in the planning process.
  • None

Answer : It calculates the delay that may occur in the planning process.

What does SAP ERP?


Options are :

  • None
  • SAP ERP is a hardware system modules for purchasing, sales and distribution, materials management, production, and so covers.
  • SAP ERP is the techNonelogy platform for customer-specific extensions can be introduced.
  • SAP ERP is the application that can use the company for effective business process management.
  • SAP ERP system is a scheduling where the advanced planning processes can be displayed.

Answer : SAP ERP is the application that can use the company for effective business process management.

Where you can determine the actual recipients of the costs of the production order?


Options are :

  • None
  • calculated profile
  • The production profile
  • In the embodiment, evaluation
  • In the embodiment, the calculation

Answer : calculated profile

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 3

Which of the following requirements are supported with the order?


Options are :

  • production documentation electronic batch record
  • Using the product / resource tool
  • None
  • Using a set of standard operations
  • documents by order of the bond

Answer : production documentation electronic batch record

In SAP ECC, the client controls the gain of the planned orders. The client first establishes a hand-date, the strengthening of the list / inventory of planned orders for companies that need to happen in the short term. In the recording material, rolling planning period to gain Type 1 active. Some planned orders also strengthened done by hand. Which statement is true to the resultant firming situations?


Options are :

  • Firming sets dating strengthen manually, as it always has priority over the planning time fence from the master of the material; all manually strengthened planned orders from these independent strengthened.
  • Strengthening of the reinforcing interval is Nonew set by the mechanism also including further in the future; all planned orders within this horizon strengthened only if it strengthens his hand earlier.
  • None
  • Strengthening the Nonew reinforcing interval set by the mechanism also included in the future and which fixed planned orders in it; all manually strengthened planned orders from these independent strengthened.
  • Firming specified time interval sampling plan of the host material, because it always strengthens a priority date side; all manually strengthened planned orders from these independent strengthened.

Answer : Strengthening the Nonew reinforcing interval set by the mechanism also included in the future and which fixed planned orders in it; all manually strengthened planned orders from these independent strengthened.

Which of the following types of planning can be used for capacity planning?


Options are :

  • center
  • forward
  • None
  • Only the required bandwidth
  • backwards

Answer : center