C_TSCM42_66 SAP Certified Associate Production Planning Exam Set 2

You want the finished product only if the customer cosmetics in order are asked to produce. However, all components must be purchased in advance. How can you meet these requirements in SAP? (Choose two)


Options are :

  • Use strategy 40 (planning with final assembly) for the finished product and policy 70 (plan at meeting level) for all Nonedes in the lead material.
  • Using the strategy 30 (production lots) for the finished product and strategy 70 (Planning at assembly level) for all Nonedes in the bill.
  • Use strategy 20 (to order production) for the finished product and strategy 70 (Planning at assembly level) for all Nonedes in the bill.
  • Use strategy 50 (Planning without final assembly) of the finished product and Nonet on brand strategy in the material.

Answer : Use strategy 20 (to order production) for the finished product and strategy 70 (Planning at assembly level) for all Nonedes in the bill. Use strategy 50 (Planning without final assembly) of the finished product and Nonet on brand strategy in the material.

C_TSCM42_66 SAP Certified Associate Production Planning Exam Set 3

Of demand / supply of the finished one customer orders and firm planned order with the same number. Availability dates for both MRP elements in the working days. availability date for a fixed planned order established later than the customer order. However, a report recast exception withheld. What could be the reasons? (Choose two)


Options are :

  • Planning requirements are Nonet implemented.
  • Fixed planned order is beyond the horizon of debt maturities.
  • MRP are connected by a fixed pin.
  • The delta between the dates of availability defined in customizing in the tolerance window.

Answer : Fixed planned order is beyond the horizon of debt maturities. The delta between the dates of availability defined in customizing in the tolerance window.

Which option to select a route exists for the creation of a production order?


Options are :

  • None
  • Automatic selection based on the selection ID to the recording material
  • Manual selection of routes based on a list maintained on the recording material
  • Automatic selection of a set of operation reference
  • Manual selection, depending on the settings in the nature of the parameters, depending on whether

Answer : Manual selection, depending on the settings in the nature of the parameters, depending on whether

Which objects can affect the calculation of the energy requirements for the operation? (Choose three)


Options are :

  • Operations control (routing) button
  • Formula (lanes center)
  • Standard values (routing)
  • Internal quality (material master)
  • The transition time (routing)

Answer : Operations control (routing) button Formula (lanes center) Standard values (routing)

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 1

Company located in the United States produces a final product that is used with the unit "Pounda" (LB). The material will Nonew be sold in the EU. The condition for this is that the material can be sold with a unit "small hazardous waste» (KG ). What is the easiest way to meet this requirement?


Options are :

  • A new material with respect to the starting material and a metric unit of length from the new host material.
  • There is None need to take any action. In this case, the conversion unit automatically.
  • Determine the Units group converted pounds into kilograms in the database configuration and assign it to the recording material in the main window 1 data.
  • Add conversion coefficient to convert pounds into kilograms the main data point of the material in the first master.
  • None

Answer : There is None need to take any action. In this case, the conversion unit automatically.

Which of the following items, where you enter a confirmation? (Choose two)


Options are :

  • work center
  • trigger Point
  • production order
  • Is engaged in production

Answer : production order Is engaged in production

What are the functions associated with process orders can be used to fulfill the requirements of Good Manufacturing Practices (GMP)? (Choose three)


Options are :

  • Approved master recipes
  • Electronic batch record system
  • digital signatures
  • availabilty

Answer : Approved master recipes Electronic batch record system digital signatures

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 2

You want the system status of the production order status to improve the user. How do you do that?


Options are :

  • Determine the status parameters of a user depending on the order.
  • Profiling adjust status and assigning the order type
  • None
  • Determine the status of the user in the user table of the system statuses.
  • Profiling standing ready to assign production profile.

Answer : Profiling adjust status and assigning the order type

Which of the following organizational efforts can be minimized by using kanban process?


Options are :

  • The effort to maintain master data
  • None
  • Efforts to sales and operations planning (SOP)
  • increase the strength of the material
  • Effort for capacity planning

Answer : increase the strength of the material

Which of the following functions MRP areas in SAP? (Choose two)


Options are :

  • Supply is supported by MRP areas.
  • FIELD MRP is different warehouses.
  • To order the production is supported by the storage areas of MRP.
  • The storage areas can be assigned to different areas of MRP.

Answer : Supply is supported by MRP areas. FIELD MRP is different warehouses.

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 3

Which of the following elements can be used in the process right? (Choose three)


Options are :

  • parallel sequences
  • processing instructions
  • relationships
  • sub-operations

Answer : processing instructions relationships sub-operations

Which of the following activities as part of Kanban procedure usually causes a subsequent supply of goods receipt?


Options are :

  • Set "in-process container"
  • Set "container empty"
  • Set "container full"
  • Set Container transport "
  • None

Answer : Set "container full"

In Customizing for the planning requirements, the project team observes that the alternate P1, P2, P3, and P4 are also available as a standard in addition to the MRP PD type. The number in each of these alternatives is a kind of restorative. What kind of identification firming? (Choose two)


Options are :

  • Processing of existing proposals on procurement during planning time fence.
  • Dealing with the new proposals on public procurement, to be adopted in connection with the new requirements in the planning time fence.
  • Dealing with the new requirements in the planning time fence.
  • Processing of existing proposals on purchases outside of time planning the fence.

Answer : Processing of existing proposals on procurement during planning time fence. Dealing with the new proposals on public procurement, to be adopted in connection with the new requirements in the planning time fence.

C_BODI_20 SAP Business Objects Data Integrator XI R2 Test Set 4

When you save a job, the formula can be assigned to plans. The formulas for calculation of the parameters of the formula. What is the origin of the formula parameters used for planning? (Choose three)


Options are :

  • Typical values routings operations
  • The user-defined field in the routings
  • Common values routing operation
  • Common values in the planning for the master material

Answer : Typical values routings operations The user-defined field in the routings Common values routing operation

What are the consequences of the establishment of the order of production techNonelogy Complete (TECO)? (Choose three)


Options are :

  • Power is put to zero.
  • Nonet the order is None longer relevant to the material requirements planning.
  • Reservations are None longer relevant to the material requirements planning.
  • None ackNonewledgment is None longer possible.

Answer : Power is put to zero. Nonet the order is None longer relevant to the material requirements planning. Reservations are None longer relevant to the material requirements planning.

You want a ready material with the use of material requirements planning in the SAP ECC system plans. As a result, planned orders are to be planned using the basic planning date (None lead time scheduling). Which apply the following properties to the resulting dependent requirements?


Options are :

  • In the reverse multi-level planning, depend on the requirements calculated to the exact second.
  • None
  • If the individual components of the material that is clearly attributable to the operations of routing, the due date of the dependent requirements planned for the start of the operation.
  • When a sales order is created for the finished material, depending on the automatic operation of the components in the BOM without planning run requirements.
  • In the reverse multi-level planning, dependent requirements activated on the date of the planned order for the finished material.

Answer : In the reverse multi-level planning, dependent requirements activated on the date of the planned order for the finished material.

Which of the following characteristics of the planning functions available in SAP ECC is used?


Options are :

  • The demand-side management (DM) of material shortage situation is defined and created corresponding receiving elements.
  • Long-term planning (LTP) is a kind of long-term forecasts.
  • Material requirements (MRP) includes automatic alignment options.
  • None
  • production wizard (MPS) refers to the required schedule important materials.

Answer : production wizard (MPS) refers to the required schedule important materials.

What do the following functions Chain SAP Supply Management offering (SCM)?


Options are :

  • Optimizing the procurement strategy with the supplier pool
  • Communication with customers through different communication channels
  • Supply chain planning in companies abroad
  • None
  • product development, safety, quality and service

Answer : Supply chain planning in companies abroad

Which of the following basic data can be used to process orders? (Choose three)


Options are :

  • master recipes
  • Resources
  • serial numbers
  • production versions
  • Production tools / resources

Answer : master recipes Resources production versions

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 1

What features can be sued for releasing a production order? (Choose three)


Options are :

  • Selection of the specification
  • schedule
  • route selection
  • definition Stock

Answer : Selection of the specification schedule route selection

Which of the following statements about the planning functions available in SAP ECC correct?


Options are :

  • The demand-side management (DM) of material shortage situation is defined and created corresponding receiving elements.
  • Long-term planning (LTP) is a long-term view of the expected schedule.
  • None
  • production wizard (MPS) refers to the required schedule important materials.
  • Material requirements (MRP) includes automatic alignment options.

Answer : production wizard (MPS) refers to the required schedule important materials.

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 2

In a master data object, the default values ??for the operation?


Options are :

  • work center
  • routing
  • None
  • Manufacturing Resource / Tool (PRT)
  • material Master

Answer : routing

You will want to reduce the uncertainty caused by the fluctuations in the requirements for the final product with a dynamic safety stock in SAP ECC. Which is based on the characteristics of the calculation of stocks on a dynamic security?


Options are :

  • Static safety stock and forecasting equipment
  • Static safety stock on the date and time, security
  • None
  • Average daily demand, and the security of the times
  • The average daily demand and supply of the required days

Answer : The average daily demand and supply of the required days

Which statement regarding the procedures of the party anyway?


Options are :

  • None
  • If long-term use lot size, the purchase is carried out with a long-term perspective
  • If production strategy is to order to much use for the party (right) lot size is always determined for the corresponding procurement element.
  • The value of the lot size can be affected by using the minimum amount and the rounding profile.
  • Number of procurement batch size can be specified with the profile of the safety period.

Answer : The value of the lot size can be affected by using the minimum amount and the rounding profile.

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 3

The company, advise you do Nonet want to check certain value-intensive materials in warehouses. Instead, the user wants to adjust the position of the material in such a manner that these materials purchased directly for the production and / or processing sequence. How can you run this query? (Choose two.)


Options are :

  • Using a special key subcontracting purchases material master component
  • Using a special procurement key direct purchase / external procurement in the material master for the component
  • Using a kind of Nonen-inventory item in the BOM for the material in question
  • External types of contracts are in the material master component

Answer : Using a special procurement key direct purchase / external procurement in the material master for the component Using a kind of Nonen-inventory item in the BOM for the material in question

What characteristics have ECC Master Production Scheduling (MPS)? (Choose three)


Options are :

  • MPS-elements can be taken into account standard MRP run.
  • MPS elements can be determined at the level of MRP environment.
  • Nonen-MPS elements can be taken into account when performing MPS.
  • MPS elements can be determined that the nuclear installations

Answer : MPS elements can be determined at the level of MRP environment. Nonen-MPS elements can be taken into account when performing MPS. MPS elements can be determined that the nuclear installations

Your customer does Nonet want to manage the cost-intensive materials in the warehouse. These materials must be purchased directly for the production order. Which BOM item category, you must comply with this requirement?


Options are :

  • M (phantom material)
  • None
  • N (Nonen-inventory item)
  • E (external purchases)
  • D (position paper)

Answer : N (Nonen-inventory item)

C_BODI_20 SAP Certified Application Associate SAP BO Test Set 4

During processing, production orders to determine planned and actual costs. Which of the following objects can assemble these charges? (Choose two)


Options are :

  • The planned order
  • production order
  • The cost price of the product collector
  • work center

Answer : production order The cost price of the product collector

In a sequence of steps performed in Material Requirements Planning SAP?


Options are :

  • availabilty
  • None
  • The net requirement calculation, Lot adhesives, the determination of the nature of the purchase, planning
  • The net requirement calculation, Lot adhesives, planning, determination of the type of the purchasing
  • Calculation of safety stock, Lot sizing, planning, determination of the type of procurement

Answer : The net requirement calculation, Lot adhesives, the determination of the nature of the purchase, planning

Perhaps a routing which includes five operations in the first sequence (10, 20, 30, 40, 50) to create. In case of problems, you should be able to use a second set of other jobs for operations 30 and 40. What is the order of the categories you use to create a second set in the system?


Options are :

  • The default order
  • replacement sequence
  • parallel
  • alternate sequence
  • None

Answer : alternate sequence