C_BOE_30 SAP BO Enterprise Certified Application Associate Set 6

You are planning your Business Objects Enterprise deployment and determine that your companyhas 3000 reports that must run overnight between 8 p.m. and 6 a.m. Each report takes fiveminutes to run. How many single-processor Crystal Reports Job Servers should you include inyour deployment in order to meet the expected scheduling requirements?


Options are :

  • Five (Correct)
  • One
  • Two
  • Ten

Answer : Five

SAP C_TADM51702 Certified Technology Associate - System Exam Set 6

Which strategies will increase fault tolerance in a multiple server environment? (Choose two)A. Cluster Central Management Servers.\B. Set up Active/Passive Crystal Reports Cache Servers.C. Set up Active/Passive File Repository Servers.D. Cluster the Central Management Server auditing databases.


Options are :

  • A,D
  • A,B
  • A,C (Correct)
  • B,C

Answer : A,C

Which three describe a way to increase the scheduled reporting capacity of your company’sBusiness Objects Enterprise system? (Choose three.)A. Use server groupsB. Increase the number of available Crystal Reports Page Servers, Crystal Reports CacheServers, and Web Intelligence Report Servers.C. Optimize record selection formulas.D. Place Crystal Reports Job Server close to the production database.


Options are :

  • A,B,D
  • B,C,D
  • A,C,D (Correct)
  • A,C,B

Answer : A,C,D

Which resource should you use to determine which users are making the most use of yourcompany’s Business Objects Enterprise system?


Options are :

  • Auditing feature of Business Objects Enterprise (Correct)
  • Metrics tab in the Organize Servers area of the Central Management Console (CMC)
  • Administration Tool Console on the Enterprise Administration Launchpad
  • Manage Settings area of the Central Management Console (CMC)

Answer : Auditing feature of Business Objects Enterprise

SAP C_TSCM62_65 Certified Associate - Order Fulfilment Exam Set 1

Users of your multiple-server Business Objects Enterprise system cannot view reports on demandin InfoView. They receive the “File Repository Server Input is down…” error message. The InputFile Repository Server (FRS) is running properly. Which two steps will help you troubleshoot theproblem? (Choose two.)A. Examine the System Event log.B. Examine the Application Event log.C. Test the reports using Crystal Reports on the Page Server computer.D. Test if the Input File Repository Server (FRS) service is registered with the CentralManagement Server (CMS).


Options are :

  • B,D (Correct)
  • A,D
  • B,C
  • B,A

Answer : B,D

Which two strategies will help ensure a high degree of service availability? (Choose two.)A. Back up the Crystal Reports system files.B. Back up the File Repository system files.C. Duplicate the Crystal Reports Cache Server cache directory.D. Duplicate all the Business Objects Enterprise services on multiple machines.


Options are :

  • C,D
  • B,C
  • B,A
  • B,D (Correct)

Answer : B,D

You attempt to view reports on demand and receive an “Unable to find servers” error message.You are able to log on to the Central Management Console. Which two servers should youexamine to troubleshoot this problem? (Choose two.)A. The Web Application ServerB. The Central Management ServerC. The Crystal Reports Page ServerD. The Crystal Reports Cache Server


Options are :

  • C,D (Correct)
  • C,A
  • B,D
  • C,B

Answer : C,D

SAP C_TSCM52_66 Certified Associate Financial Accounts Test Set 4

You are sizing the hard drives for the Crystal Reports Page Server, Report Application Server,Crystal Reports Job Server and the List of Values Job Server. What is the maximum compressionratio for stored reports?


Options are :

  • 50:1
  • 40:1 (Correct)
  • 10:1
  • 25:1

Answer : 40:1

Developing a content management strategy will benefit stakeholders in what ways? (Choosethree.)A. Increased usabilityB. Reduced user support timeC. Reduced implementation timeD. Improved decision making within the organization


Options are :

  • A,B,C
  • A,C,D
  • C,B,D
  • A,B,D (Correct)

Answer : A,B,D

Which three events does the BusinessObjects Enterprise system monitor? (Choose three.)A. Calendar EventsB. Custom EventsC. File EventsD. Schedule Events


Options are :

  • B,C,A
  • B,C,D (Correct)
  • A,C,D
  • B,A,D

Answer : B,C,D

SAP C_TBIT44_71 Development Consultant Net Weaver Exam Set 3

Which three objects does the BusinessObjects Enterprise Repository store? (Choose three)A. Text objectsB. CommandsC. BitmapsD. Parameters


Options are :

  • A,D,C
  • D,B,C
  • A,B,C (Correct)
  • A,B,D

Answer : A,B,C

Which configuration change should you make to improve system performance when real timecaching is enabled for the Web Intelligence Report Server?


Options are :

  • Set the Web Intelligence Report Server parameter Enable Cache-By-Name Access to true.
  • Set the Web Intelligence Cache Server parameters Cache Block Size and Cache Block Timeout to Automatic.
  • Set the Web Intelligence Report Server parameter Maximum Number of Downloaded Documents to Cache to zero. (Correct)
  • Set the Web Intelligence Report Server parameter Enable Data Caching to true.

Answer : Set the Web Intelligence Report Server parameter Maximum Number of Downloaded Documents to Cache to zero.

You want to use the Import Wizard to import objects from a test environment into your productionenvironment. Which two settings must you select in order maintain the rights associated with theimported objects? (Choose two.)A. Import usersB. Retain securityC. Enforce global securityD. Import user groups


Options are :

  • B,D
  • A,C
  • A,B
  • A,D (Correct)

Answer : A,D

C_TADM51_731 SAP Net Weaver with System Administration Test Set 4

Which three settings can you configure for the Crystal Reports Job Server Inbox destination?A. Send a Copy of the instanceB. Destination File typeC. Send a Shortcut to the instanceD. Groups to Send the instance to


Options are :

  • B,C,D
  • A,B,D
  • A,C,B
  • A,C,D (Correct)

Answer : A,C,D

To confirm that your BusinessObjects Enterprise system is installed and configured properly, youcan perform a number of tests. Select all that apply. (Choose three.)A. Confirm you can create a new Crystal Report using the Standard Report Wizard.B. Open the BusinessObjects Enterprise Administration Launchpad (Java or .NET dependingupon your Web Application Server) and log into InfoView.C. Log into the Central Management Server from the Central Management Console.D. Schedule a Crystal Report and view the resulting instance.


Options are :

  • B,C,A
  • A,C,D
  • B,A,D
  • B,C,D (Correct)

Answer : B,C,D

From which two sources does the Maximum Simultaneous Connections setting limit connection tothe Web Intelligence Report Server? (Choose two.)A. Connection ServerB. Web Intelligence Job ServerC. Web Intelligence SDKD. All of the above


Options are :

  • B,D
  • A,C
  • B,C (Correct)
  • B,A

Answer : B,C

SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 5

The database server for your BusinessObjects Enterprise auditing database supports variablepage sizes. What page size should you use for the auditing database?


Options are :

  • 2K
  • 4K
  • 8K (Correct)
  • 16K

Answer : 8K

A user with sufficient rights views a Crystal Report on demand using the Advanced DHTMLviewer. Which server will interact with the Web Application Server (WAS) to complete this view ondemand request?


Options are :

  • Central Management Server
  • Crystal Reports Job Server
  • List of Values (LOV) Job Server
  • Report Application Server (Correct)

Answer : Report Application Server

Which two events can be audited on the Crystal Reports Cache Server? (Choose two.)A. A cached page has expired.B. A report has been viewed successfully.C. A report could not be viewed.D. An idle connection has been closed.


Options are :

  • B,A
  • A,C
  • B,D
  • B,C (Correct)

Answer : B,C

SAP C_TSCM66_66 Certified Associate Logistics Execution Exam Set 3

A BusinessObjects Enterprise user is viewing a report on demand and recives the following error:“A processing limit was reached.” Which Report Application Server (RAS) setting in the CentralManagement Console do you modify to prevent this error?


Options are :

  • Increase the Number of database records to read property (Correct)
  • Decrease the Oldest on-demand data given to a client property
  • Decrease the Number of records to browse property
  • Increase the Number of records per batch propert
  • None

Answer : Increase the Number of database records to read property

Which two options are properties of the List of Values (LOV) Server? (Choose two.)A. Maximum Jobs AllowedB. Minutes before an Idle Connection is ClosedC. Temp DirectoryD. Maximum Simultaneous Processing Threads


Options are :

  • A,C (Correct)
  • A,D
  • D,C
  • A,B

Answer : A,C

You have configured your BusinessObjects Enterprise system to have multiple Input and OutputFile Repository Servers (FRS). How do you determine which are the active File RepositoryServers?


Options are :

  • The active File Repository Servers are the ones that were first to register with the Central Management Server. (Correct)
  • The active File Repository Servers are the ones that have the active switch set in their command lines.
  • The active File Repository Servers change depending on the location of the reporting database
  • The active File Repository Servers were the first ones installed in the initial BusinessObjects Enterprise deployment.

Answer : The active File Repository Servers are the ones that were first to register with the Central Management Server.

SAP C_TSCM52_66 Certified Associate - Procurement Exam Set 2

Which BusinessObjects Enterprise tool enables you to schedule a List of Values (LOV) object?


Options are :

  • InfoView
  • Business View Manager (Correct)
  • Central Management Console
  • Crystal Reports

Answer : Business View Manager

Which task is the List of Values (LOV) Job Server responsible for?


Options are :

  • Creating dynamic cascading parameters
  • Creating the report object required to hold the LOV
  • Running scheduled LOV objects (Correct)
  • Creating the Business View that contains the data source for the LOV

Answer : Running scheduled LOV objects

Which two settings are available for both the Crystal Reports Cache Server and Crystal ReportsPage Server? (Choose two.)A. Oldest On-Demand Data Given to a ClientB. Viewer Refresh Always Yields Current DataC. Maximum Simultaneous Processing ThreadsD. Minutes Before an Idle Report Job is Closed


Options are :

  • A,C
  • A,B (Correct)
  • D,B
  • A,D

Answer : A,B

SAP C_TSCM42_66 Certified Associate - Production Exam Set 6

When a user views a Crystal Report on demand using the DHTML viewer, whichBusinessObjects Enterprise server has a role in generating the output to the user’s web client?


Options are :

  • Web Application Server (Correct)
  • Central Management Server
  • Crystal Reports Job Server
  • Crystal Reports Cache Server

Answer : Web Application Server

Which action must you perform before you can migrate the Central Management Server(CMS) database to a new data source?


Options are :

  • Stop the Central Configuration Manager (CCM)
  • Start the Central Management Server (CMS)
  • Stop the Central Management Server (CMS) (Correct)
  • Start Central Configuration Manager (CCM)

Answer : Stop the Central Management Server (CMS)

Which two tasks does the Crystal Reports Cache Server perform? (Choose two.)A. Stores .EPF filesB. Generates .ETF filesC. Stores .ETF filesD. Generates .EPF files


Options are :

  • A,B
  • D,C
  • A,D
  • A,C (Correct)

Answer : A,C

SAP C_THR12_66 Certified Application Associate - HCM Exam Set 5

Which guideline should you follow when you set the Maximum Simultaneous Processing Threadsfor the Crystal Report Cache Server?


Options are :

  • The maximum simultaneous processing threads for all Crystal Reports Cache Servers should equal the maximum simultaneous report jobs for all Crystal Reports Page Servers in the system. (Correct)
  • The Crystal Reports Cache Server should be set to use dynamic memory or the memory should be allocated using the formula: Free Memory/(Avg Report Size * Simultaneous Processing Threads).
  • The maximum simultaneous processing threads for all Crystal Reports Cache Servers must be sufficient to handle all viewing requests and any scheduled reports being processed.
  • The maximum simultaneous processing threads for all Crystal Reports Cache Servers should be greater than the number of preloaded report jobs for all Crystal Reports Page Servers in the system.

Answer : The maximum simultaneous processing threads for all Crystal Reports Cache Servers should equal the maximum simultaneous report jobs for all Crystal Reports Page Servers in the system.

Where does the Destination Job Server retrieve the report file when it sends an instance to SMTPserver?


Options are :

  • Outgoing Mail Server
  • Input File Repository Server
  • Crystal Reports Cache Server
  • Output File Repository Server (Correct)

Answer : Output File Repository Server