PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 6

PDCA (Plan-Do-Check-Act) is an iterative project management method used for controlling and continuously improving the processes and products. Which of the following options says that it is the basis for quality improvement?


Options are :

  • 80/20 Principle
  • Gantt Cycle
  • Edwards Deming
  • Zero Defect

Answer : Edwards Deming

PMI-100 Certified Associate Project Management Practice Exam Set 5

You as a project manager, are assigned to an ongoing project. The ex-project manager of the same project is your friend and he told you: "I don't know why, but there are a lot of problem with the budget." To find the root cause of the problem, you start to examine the budget. There are 3 estimations made for each activity: pessimistic, optimistic and most likely. Estimations are done by team members. Among the estimations, most likely estimation is assumed to be the cost of the activity. Then it is used to calculate the budget. CPI is 1.24 and SPI is 0.98. Which of the following best describes the problem about the budget?


Options are :

  • Estimations should not be made by team members. It is project manager’s responsibility. Since team members don’t know the project management concepts, they probably make mistakes while estimating.
  • To stay on the safe side, the pessimistic estimation should be used instead of most likely estimation.
  • Since CPI is 1.24, everything is fine. You don’t need to worry about the budget.
  • Three-point estimating is not made properly and this should be the main reason for the problems.

Answer : Three-point estimating is not made properly and this should be the main reason for the problems.

As the budget manager of a large construction company, you are preparing the budget of a new hospital project. The project is new and all information you have is: "It is going to be almost similar to another hospital project." Since you don’t have any other information, you decide to use the cost data of that project directly. This is an example of which of the following? 


Options are :

  • Parametric Estimating
  • Monte Carlo Simulation
  • Three Point Estimating
  • Analogous Estimating

Answer : Analogous Estimating

Generally, project selection methods are divided into two groups: Comparative Approach and Mathematical Approach. Which of the following options is not an example of the Mathematical Approach?


Options are :

  • Linear programming
  • Integer programming
  • Multi-objective programming
  • EVM programming

Answer : EVM programming

PMI-002 Certify Associate Project Management Practice Exam Set 8

Present Value of $50,000.00 income received 1 year from now is $48,543.69. There will be a $10,000.00 of outcome 2 years from now and the Present Value of this outcome is $9,425.96. Assuming interest rate to be 3, what is the Net Present Value?


Options are :

  • $40,000.00
  • $60,000.00
  • $57,969.65
  • $39,117.73

Answer : $39,117.73

You are about to choose the best project to invest. Payback Period of Project A is 3 years, Payback Period of Project B is 4 years, Payback Period of Project C is 2 years and Payback Period of Project D is 3.5 years. Which project is the best project?


Options are :

  • Project A
  • Project B
  • Project C
  • Project D

Answer : Project C

Which of the following is not needed while developing the project charter?


Options are :

  • Agreements
  • Project scope statement
  • Enterprise environmental factors
  • Organizational process assets

Answer : Project scope statement

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 7

The budget for your project is $100,000.00. You have made the performance calculations and obtain the following results: CPI = 1.15; SPI = 1.25. Now you are about to make an estimation of the total cost of the project when it is completed. What would be your answer?


Options are :

  • $100,000.00
  • $86,956.52
  • $80,000.00
  • $88,312.24

Answer : $86,956.52

According to the given data, calculate the Estimate At Completion.

AC = $500,000;

EV = $400,000;

BAC = $600,000;

SPI = 0.95.

(Assume current cost performance is atypical for future.)


Options are :

  • $300,000
  • $700,000
  • $750,000
  • $500,000

Answer : $700,000

According to given network diagram, what is the critical path?


Options are :

  • A-B-D-F-H
  • A-B-F-H
  • A-E-H
  • A-C-G-H

Answer : A-B-D-F-H

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 12

You have the following performance indexes of two projects;

Project 1: CPI=0.70 TCPI=1.20

Project 2: CPI=0.90 TCPI=1.20

By only considering these variables, which of the following is true about these projects?


Options are :

  • Both projects are under budget
  • Project 1’s probability of completion within the budget is higher than Project 2
  • Project 2’s probability of completion within the budget is higher than Project 1
  • AC is greater than EV for Project 1

Answer : AC is greater than EV for Project 1

Fill in the blank: To ___________ you will need project management plan, project documents (including lessons learned register, requirements documentation and requirements traceability matrix), work performance data and organizational process assets.


Options are :

  • Control Scope
  • Validate Scope
  • Control Quality
  • Define Scope

Answer : Control Scope

Fill in the blanks: Perform Integrated Change Control process is a process grouped in ______________ and it is performed ______________.


Options are :

  • First Blank: “Executing Process Group”; Second Blank: “throughout the project”
  • First Blank: “Monitoring and Controlling Process Group”; Second Blank: “in project scope management”
  • First Blank: “Executing Process Group”; Second Blank: “in change management knowledge area”
  • First Blank: “Monitoring and Controlling Process Group”; Second Blank: “throughout the project”

Answer : First Blank: “Monitoring and Controlling Process Group”; Second Blank: “throughout the project”

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 5

The successor activity starts 10 days before the predecessor activity ends. This “10 days” is called:


Options are :

  • Crash
  • Lag
  • Sunk
  • Lead

Answer : Lead

Which of the following is not a configuration management activity included in the Perform Integrated Change Control process?


Options are :

  • Configuration identification
  • Configuration status accounting
  • Configuration documentation
  • Configuration verification and audit

Answer : Configuration documentation

You are the Project manager of an ongoing website development project. You are currently using a software named SoftX to do the most of the work. A team member says: "If we use the software EasyX instead of SoftX, this will fasten all of the work since it is more user-friendly and easy to use." You know the EasyX before and you think that the team member may be right. What should you do?


Options are :

  • Since you know he is right, tell him: "You may start to use the software EasyX"
  • Since the project has already been started, you should reject this request
  • You should ask for a change request
  • You should check how this choice would affect other constraints first

Answer : You should check how this choice would affect other constraints first

PMI-002 Certify Associate Project Management Practice Exam Set 8

As a functional manager, which of the following is the best place (or source) for learning about changes in a project?


Options are :

  • Change Control Board
  • Enterprise Environmental Factors
  • Organizational Process Assets
  • Change Log

Answer : Change Log

 In which condition, Closing Project or Phase process may not be applied?


Options are :

  • After completing the project properly
  • If a project is terminated, then it may not be applied
  • If the project is stopped because of the customer, then it may not be applied
  • Closing project or phase process should always be applied

Answer : Closing project or phase process should always be applied

You are a project manager for an electrical project. The customer asks you about a change and you know that this change will fasten the project. What should you do first?


Options are :

  • Apply the change since it will fasten the project
  • Explain customer the impacts of this change
  • Tell the customer, you cannot apply the change since it is not written in the project scope statement
  • Talk about all the alternatives with your sponsor

Answer : Talk about all the alternatives with your sponsor

PMI Question Answers

A new project is about to start. You are assigned to be the project manager of this new project. Project charter has been approved and all stakeholders are identified. Which of the following is the first thing to do?


Options are :

  • Create Work Breakdown Structure of the project
  • Create Work Breakdown Dictionary of the project
  • Determine all activities and create the activity list
  • Determine your roadmap for creating the project plan

Answer : Determine your roadmap for creating the project plan

Which of the following options is not a part of Scope Management?


Options are :

  • Determining the requirements in detail
  • Creating the activity list
  • Creating the WBS and the WBS dictionary
  • Request changes

Answer : Creating the activity list

One of the main objectives of creating a work breakdown structure is ensuring the communication.  Communication is:


Options are :

  • Between project manager and team
  • Between project manager and customer
  • Between a stakeholder with other stakeholders
  • Between customer and team

Answer : Between a stakeholder with other stakeholders

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 4

One of your team members sent you the project schedule. You notice that milestones are missing and you ask her to add them and send it back again. Which of the following is not true about a milestone?


Options are :

  • A milestone is a «Work» activity and it is part of the project schedule
  • Milestones are generally used for emphasizing the checkpoints of the project
  • Milestones have zero duration
  • You expect to see the summary of milestones in the project charter

Answer : A milestone is a «Work» activity and it is part of the project schedule

“Construction of 2nd floor may only start after completing the construction of 1st floor because it is impossible to start next floor’s construction without completing the previous floor’s construction.” This sentence is an example of which of the following dependencies?


Options are :

  • Hard Logic
  • Discretionary Dependency
  • External Dependency
  • Soft Logic

Answer : Hard Logic

During a project, you will decide to use a material for a specific work package. There are two options. Buying the first material will cost you $100,000 and buying the second material will cost you $120,000. Since it is cheaper, you have decided to use the first material. 10 months later, the project ends and the end-product of the project is produced. Your company notices that the maintenance cost of the first material is $15,000 each year. If the second material had been chosen instead of first material, the maintenance cost would be $5,000 each year. In ten years, due to this decision, your company will have to pay $100,000 more for maintenance. Which of the following is the main reason of the company to pay more?


Options are :

  • Value analysis is not done
  • Life cycle costing is missed
  • Cost of quality is not considered
  • Bottom-up estimating is not done

Answer : Life cycle costing is missed

PMI-RMP PMI Risk Management Professional Practice Test Set 1

Michelle has completed the performance calculations. She obtained the following results:

CPI=0.85; SPI=0.90;

If Budget at Completion is $500,000, which of the following statements is wrong about this project?


Options are :

  • The project should be accelerated to complete the work on time
  • TCPI value is greater than 1
  • ETC value is less than 0
  • The project is over budget

Answer : ETC value is less than 0

You have subcontracted a specific work package of your project by signing a fixed price contract. Which of the following does not explain why you have preferred fixed price type of contract?


Options are :

  • The scope is detailed and clear
  • Seller will try to work more carefully since every extra cost of him will decrease his profit
  • Risk of the seller is minimized
  • Risk of the buyer is minimized

Answer : Risk of the seller is minimized

To buy some material, you have agreed on a unilateral contract. Which of the following is an example of a unilateral contract?


Options are :

  • Cost Contract
  • Fixed Price Economic Price Adjustment
  • Purchase Order
  • Time & material

Answer : Purchase Order

PMI-RMP PMI Risk Management Professional Practice Test Set 9

You have signed a fixed price incentive fee contract. If the following information is known about this contract, calculate the Point of Total Assumption.

Target cost: $500,000.00

Share ratio: 70/30

Target fee: $50,000.00

Ceiling price: $600,000.00


Options are :

  • $571,428.57
  • $550,000.00
  • $666,666.67
  • $578,245.44

Answer : $571,428.57

At the end of a project, the total cost is agreed to be above the Point of Total Assumption. What may be the main reason for this result and who is responsible for this situation?


Options are :

  • The ceiling price is low; buyer is responsible for this situation
  • Target fee is low; buyer is responsible for this situation
  • Because of mismanagement; Project manager of the buyer is responsible for this situation
  • Because of mismanagement; Project manager of the seller is responsible for this situation

Answer : Because of mismanagement; Project manager of the seller is responsible for this situation