PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 3

At the beginning of the project, you have added some contingency reserve for the failure of the shoring wall. Right now, all the backfilling activities are done and the risk of the failure of the shoring wall became zero. What should you do about the contingency reserve regarding shore failure?


Options are :

  • Do nothing. If some other risks occur in the future, you may use this reserve for that risk.
  • Transfer this contingency reserve amount to another risk.
  • Remove this contingency reserve from the cost baseline.
  • Ask the customer what to do.

Answer : Remove this contingency reserve from the cost baseline.

PMI-100 Certify Associate Project Management Practice Exam Set 2

Communication management is one of the most important concepts of a large project. Which of the following options is not true about communications?


Options are :

  • Communications of the project should be efficient and it should only provide the needed information
  • Communications of the project should be effective
  • The format of the communication is not an important factor while communicating with stakeholders.
  • Multiple methods may be used while communicating with each other.

Answer : The format of the communication is not an important factor while communicating with stakeholders.

While planning a project, time and cost are determined and schedule and budget are developed. Which of the following options will be the next activity?


Options are :

  • You should plan the communications
  • You should held a kickoff meeting
  • You should determine the quality standards
  • You should create the change management plan

Answer : You should determine the quality standards

Which of the following options may not be an example of a communication blocker?


Options are :

  • Language
  • Noise
  • Hostility
  • Culture

Answer : Noise

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 2

You are a project manager for a website project. There is a problem and you would like to find the root cause of the problem. Which of the following options may help you in this situation better?


Options are :

  • Process Map
  • Tally Sheet
  • Ishikawa Diagram
  • Control Chart

Answer : Ishikawa Diagram

Which of the following options is not a Procurement Management process?


Options are :

  • Plan Procurement Management
  • Execute Procurements
  • Control Procurements
  • Conduct Procurements

Answer : Execute Procurements

You are a functional manager and you are searching for if the quality procedures are following as planned at the beginning of the Project or not. Which of the following is a result of this process?


Options are :

  • Process Improvement Plan
  • Quality Metrics
  • Updated Quality Systems
  • Verified Deliverables

Answer : Updated Quality Systems

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 5

Audit for quality may be conducted during which process?


Options are :

  • Quality Management
  • Plan Quality Management
  • Manage Quality
  • Control Quality

Answer : Manage Quality

Which of the following options is not a purpose of signing a contract?


Options are :

  • Defining roles and responsibilities
  • Mitigating or allocating risks
  • Selecting the seller company
  • Making works legally binding

Answer : Selecting the seller company

Team building activities are important activities that should take place throughout the project lifecycle. It is better if they are conducted:


Options are :

  • Whenever they are needed
  • Early stages in the project life cycle
  • In the middle of the project life cycle
  • At the end of the project life cycle

Answer : Early stages in the project life cycle

PMI-100 Certified Associate Project Management Practice Exam Set 5

Validate scope is a part of which process group?


Options are :

  • Planning Process Group
  • Executing Process Group
  • Monitoring and Controlling Process Group
  • Closing Process Group

Answer : Monitoring and Controlling Process Group

ABCONX, a huge construction company, awarded your company a very small project. Normally, your company is too big to do this kind of small projects, but you know, if you complete this project successfully, your chance of being awarded a huge project of ABCONX next year will be very high. Management of your company states that most important constraint of the project is quality. During the beginning of the project, a major problem with quality has occurred. Which of the following action is most suitable in this situation?


Options are :

  • Fixing the problem immediately
  • Asking ABCONX if they allow this kind of quality problems
  • Fixing the root cause of the problem even if it causes increased cost
  • Asking your sponsor what to do

Answer : Fixing the root cause of the problem even if it causes increased cost

Selecting a sample and doing tests on this sample instead of the entire population is always a preferable action. Which of the following is the main reason for this preference?


Options are :

  • Testing the entire population is mutually exclusive
  • Selecting a sample provides more detailed information
  • Testing the entire population is easier
  • Testing the entire population is time-consuming

Answer : Testing the entire population is time-consuming

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 8

You are about to determine which tools and techniques will be used for quality assurance for a software development project. Which of the following is not an appropriate selection for this situation?


Options are :

  • Process analysis
  • Tree diagrams
  • Delphi technique
  • Prioritization matrices

Answer : Delphi technique

Your team is about to create a plan for quality policy implementation. Which of the following is not needed to create this plan?


Options are :

  • Project charter
  • Stakeholder register
  • Risk register
  • Team performance assessments

Answer : Team performance assessments

Cost performance index required to complete the project within the budget is called:


Options are :

  • CPI
  • TCPI
  • ETC
  • EAC

Answer : TCPI

PMI-SP Scheduling Professional Certification Practical Exam Set 9

Which of the following options is not a tool and technique used during integrating change control?


Options are :

  • Expert judgment
  • Meetings
  • Change log
  • Change control tools

Answer : Change log

Generally, communications are divided into four categories. A presentation is an example of which category of communication?


Options are :

  • Formal written
  • Formal verbal
  • Informal written
  • Informal verbal

Answer : Formal verbal

You are a team member of a huge construction project. There are more than 200 personnel working on the same project. Your project manager asks you: «When will Joe, be released?». Joe is the substructures chief of the project. Which of the following is the best source for you to find this information?


Options are :

  • Project Schedule
  • Resource Histogram
  • Staffing Management Plan
  • RACI Chart

Answer : Staffing Management Plan

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 7

Michael was a project scheduler of the project. He had a very good technical background and he was very good at project scheduling. You decided to assign him as the project manager of a new project. After assigning him, you saw that he has lots of problems with his team. Now you start to think that assigning him to that position was a bad idea. Which of the following best names this situation?


Options are :

  • Pre-assignment
  • Halo effect
  • Multi-criteria decision analysis
  • Virtual membership

Answer : Halo effect

You are a scheduling team member of a project. You sent an e-mail to your project manager to clarify an issue. Your e-mail is an example of:


Options are :

  • Formal written communication
  • Indirect written communication
  • Informal written communication
  • Effective written communication

Answer : Informal written communication

In a project, there are 10 stakeholders other than you. Your project manager is asking you the number of communication channels. Which of the following is true about the number of communication channels?


Options are :

  • There are 12 people including project manager, therefore the number of communication channels is 66
  • There are 12 people including project manager, therefore the number of communication channels is 12
  • There are 11 people including project manager, therefore the number of communication channels is 11
  • There are 11 people including project manager, therefore the number of communication channels is 55

Answer : There are 11 people including project manager, therefore the number of communication channels is 55

PMI-RMP PMI Risk Management Professional Practice Test Set 6

Which of the following is not true about communications?


Options are :

  • A project manager spends 90% of his time for communication
  • A project manager is responsible for controlling all communications
  • Performance reporting is part of the manage communications process
  • Issue log is an input to the Monitor Communications process

Answer : A project manager is responsible for controlling all communications

Which of the following is useless while preparing a risk management plan?


Options are :

  • Project management plan
  • Project charter
  • Stakeholder register
  • Project staff assignments

Answer : Project staff assignments

Which of the following section is not found in a risk management plan?


Options are :

  • Budget
  • Roles and responsibilities
  • Stakeholder tolerances
  • Product validation

Answer : Product validation

PMI-SP Scheduling Professional Certification Practical Exam Set 1

Risk identification starts in which process group?


Options are :

  • Initiating
  • Planning
  • Executing
  • Monitoring & Controlling

Answer : Initiating

Risks are analyzed subjectively during:


Options are :

  • Perform quantitative risk analysis
  • Perform qualitative risk analysis
  • Monitor Risks
  • Plan Risk Management

Answer : Perform qualitative risk analysis

All defined risks should be sorted so that risks which require immediate response should be known. Which of the following may help you during this process?


Options are :

  • Tornado diagram
  • Expected monetary value analysis
  • Probability and impact matrix
  • Monte Carlo analysis

Answer : Probability and impact matrix

PMI Question Answers

While you are creating the short list of risks, you determined a risk which is categorized to be an urgent risk. As a project manager, which of the following will be the best action for you at this moment?


Options are :

  • Quantitative risk analysis should be done immediately
  • Risk should be moved immediately
  • Control the risk immediately
  • Take an advice from a senior project manager

Answer : Risk should be moved immediately

You are about to decide to do or not to do a technical choice. Before you make your decision, you want to consider for the future events. Which of the following may be used in this situation?


Options are :

  • Tornado diagram
  • Probability and impact matrix
  • Decision tree
  • Work breakdown structure

Answer : Decision tree

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions