Which of the following options is classified as a hygiene factor?


Options are :

  • Relationships at work
  • Responsibility
  • Professional growth
  • Problem solving

Answer : Relationships at work

Which of the following options is not a Communication Management process?


Options are :

  • Plan Communications Management
  • Manage Communications
  • Monitor Communications
  • Close Communications

Answer : Close Communications

Plan Procurement Management is one of the procurement management processes. Which of the following activities are not done during this process?


Options are :

  • Project scope statement is created
  • Make or buy analysis are done
  • Source selection criteria is determined
  • Procurement statement of work is created

Answer : Project scope statement is created

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 3

Contract negotiations are completed and the contract is about to be signed. This is a construction project and there are some drawings which are exactly showing how should be the final product. What type of procurement statement of work is most probably used?


Options are :

  • Fixed price
  • Functional
  • Time and material
  • Design

Answer : Design

You are about to sign a contract. The contract price is $2,000,000. You will get an additional $50,000 for each month early the project is finished. This contract is what type?


Options are :

  • Cost plus award fee
  • Cost plus incentive fee
  • Fixed price award fee
  • Fixed price incentive fee

Answer : Fixed price incentive fee

Basic communication model is the most commonly known communication model. Which one of the following is not one of the main parts of the basic communication model?


Options are :

  • Sender
  • Receiver
  • Words
  • Message

Answer : Words

PMI PGMP Program Management Professional Practice Test Set 2

You are living in a country where the yearly inflation rates are so high. The deadline for the project is 48 months as of today. CPI is 1.1 and SPI is 0.9. If you are the seller company, what type of contract will be more advantageous for you in this situation?


Options are :

  • Fixed price incentive fee contract
  • Fixed price award fee contract
  • Fixed price economic price adjustment
  • Purchase order

Answer : Fixed price economic price adjustment

For which kind of contract, negotiation after receipt of the seller’s price is not needed?


Options are :

  • Fixed price
  • Time and material
  • Cost-reimbursable
  • Design

Answer : Fixed price

A report, describing what has been accomplished is called a:


Options are :

  • Variance report
  • Status report
  • Progress report
  • Trend report

Answer : Progress report

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 3

During a procurement negotiation, which of the following options is generally negotiated lastly?


Options are :

  • Scope
  • Responsibilities
  • Schedule
  • Price

Answer : Price

Which of the following statements about contracts is not correct?


Options are :

  • A contract may be both verbal or written
  • Numbers are more effective than words in a contract
  • “Industry use of term” is more effective than “common use of term” in a contract
  • Fixed price, unit price and cost reimbursable contracts are the generally accepted types of contracts

Answer : Numbers are more effective than words in a contract

You are about to select the seller for a specific work package. Which process is this?


Options are :

  • Plan Procurement Management Process
  • Conduct Procurements Process
  • Control Procurements Process
  • Close Procurements Process

Answer : Conduct Procurements Process

PMI-SP Scheduling Professional Certification Practical Exam Set 10

There are four stakeholder management processes. Which of the following options is not a stakeholder management process?


Options are :

  • Identify Stakeholders
  • Plan Stakeholder Engagement
  • Execute Stakeholder Management
  • Monitor Stakeholder Engagement

Answer : Execute Stakeholder Management

Stakeholder management is one of the knowledge areas of project management. Stakeholder management begins in which process group?


Options are :

  • Starting
  • Initiating
  • Planning
  • Monitoring and controlling

Answer : Initiating

Which document formally authorizes a project?


Options are :

  • Initiation Plan
  • Project Management Plan
  • Project Charter
  • Project Scope of Works

Answer : Project Charter

PMI-RMP PMI Risk Management Professional Practice Test Set 4

Fill in the blank: …………… is the time required for the invested money to be repaid.


Options are :

  • Payback period
  • To Complete Performance Index
  • Net present value
  • Present value

Answer : Payback period

Which one of the followings is not needed to develop a project schedule?


Options are :

  • Project Schedule Network Diagrams
  • Resource Calendars
  • Milestone List
  • Schedule Data

Answer : Schedule Data

All the information about stakeholders can be found in the stakeholder register. Stakeholder register is created as a result of which process?


Options are :

  • Stakeholder management
  • Planning
  • Monitoring & Controlling
  • Identify Stakeholders

Answer : Identify Stakeholders

PMI-SP Scheduling Professional Certification Practical Exam Set 2

You have just been hired to a project as a project team member. You want to know who is responsible for what. You should look at which of the followings?


Options are :

  • Stakeholder Analysis
  • Stakeholder Register
  • Stakeholder Description
  • Stakeholder List

Answer : Stakeholder Register

Which of the following actions is more suitable for a high interest high influence stakeholder who is also a supporter of the project?


Options are :

  • Only send the reports to inform the stakeholder
  • Invite the stakeholder to join the team officially
  • Not only report to stakeholder but also involve this stakeholder in the team meetings
  • Invite this stakeholder to take a role on the risk management process

Answer : Not only report to stakeholder but also involve this stakeholder in the team meetings

Your project manager wants you to calculate the current performance of the project. Which of the following techniques helps you to calculate the project performance?


Options are :

  • Three point estimating
  • Expert judgment
  • Parametric estimating
  • Earned Value Measurement

Answer : Earned Value Measurement

PMI-100 Certified Associate in Project Management Test Set 1

You want to address how the communication will be held between stakeholders. Your aim is to manage their engagements and expectations. Which of the following plans should you prepare?


Options are :

  • Communication Management Plan
  • Organization Communication Plan
  • Stakeholder Management Plan
  • Communication Description Plan

Answer : Stakeholder Management Plan

You will subcontract some of the work packages of the project. You are about to send the tender packages, including all the information needed to bid, to multiple vendors. To ensure everything is clear for everyone, what should you do?


Options are :

  • Send the tender packages only by e-mail
  • Only send the tender packages to the companies you know
  • Don’t let anyone ask you question
  • You should hold a bidder conference

Answer : You should hold a bidder conference

Which of the following risk management processes is not part of Planning Process Group?


Options are :

  • Monitor Risks
  • Identify Risks
  • Plan Qualitative Risk Analysis
  • Plan Quantitative Risk Analysis

Answer : Monitor Risks

PMI PGMP Program Management Professional Practice Test Set 9

You are preparing your project’s schedule. You have calculated your project finish date to be 3 months later than the project’s deadline. Which technique or techniques may help you in this situation? 


Options are :

  • Monte Carlo Analysis and Delphi Technique
  • Resource Smoothing and Resource Leveling
  • Crashing and Fast Tracking
  • Resource Leveling and Schedule Network Analysis

Answer : Crashing and Fast Tracking

If there is a change in the scope, it is important to track it until it is implemented. This activity is a part of which of the following processes?


Options are :

  • Monitor and Control Project Work
  • Perform Integrated Change Control
  • Direct and Manage Project Work
  • Validate Scope

Answer : Perform Integrated Change Control

During a project, you need to shorten the total duration of the project. While doing that, you shouldn't change the scope. Which of the following techniques may help you in this situation?


Options are :

  • Monte Carlo
  • Crashing
  • Resource Leveling
  • Reserve Analysis

Answer : Crashing

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 2

Which of the following options is not needed for identifying stakeholders?


Options are :

  • Project Charter
  • Enterprise Environmental Factors
  • Agreements
  • Stakeholder Register

Answer : Stakeholder Register

It is the end of the project. If you make EVM calculations right now, what do you calculate the earned value to be?


Options are :

  • Equal to 1
  • Equal to 0
  • Equal to TCPI
  • Equal to PV

Answer : Equal to PV

Which of the following options is not a type of procurement document?


Options are :

  • Proposal review
  • Request for tender
  • Invitation for bid
  • Request for quotation

Answer : Proposal review