Which of the following statement is true about strategic planning?


Options are :

  • None
  • Strategic planning defines these projects, which receive selected and funded
  • Strategic planning to determine which projects should be selected in order to achieve the objectives of the organization
  • All the above
  • Strategic planning to determine which projects are to achieve the principal objectives of the organization

Answer :All the above

Which of the following is not a form of leadership power?


Options are :

  • None
  • imperative
  • Jeopardize
  • Foimal
  • handicap

Answer :handicap

What did not provide the scope of the following?


Options are :

  • None
  • project justification
  • project product
  • project authority
  • The project goal

Answer :project authority

Which of them is true about bottom-up is expected?


Options are :

  • Used as a basis for the previous corresponding actual cost of the project cost of the current project.
  • The cost of individual work items and then rolling up costs to arrive at the total amount of the project.
  • The cost of quality can also be used to prepare the schedule activity cost estimate.
  • By using the project properties (or parameters) is a mathematical model to predict the cost.

Answer :The cost of individual work items and then rolling up costs to arrive at the total amount of the project.

When you add a project to develop estimates of individual estimates of activities that comprise each step. What kind of assessment method are you using?


Options are :

  • None
  • parametric estimation
  • The bottom-up assessment of the
  • Top-down estimates by
  • analog estimation

Answer :The bottom-up assessment of the

Which of the following statement is true about the project plan?


Options are :

  • Tells the newspapers and the media when the project ends
  • Tells who is the project sponsor
  • Tells who is project engineer
  • Provides a high level of effort and the definition of its stakeholders
  • None

Answer :Provides a high level of effort and the definition of its stakeholders

Which of the following is not part of the Plan Risk Management?


Options are :

  • Identification of risk classes
  • Updating the risk register
  • None
  • By developing a risk management plan
  • Determine the risk of the roles and responsibilities

Answer :Updating the risk register

Assumptions of the project will be _________.


Options are :

  • intelligible
  • None
  • No need to write
  • Written
  • not understandable

Answer :Written

The project baseline is _______.


Options are :

  • None
  • Important project's initial phase
  • Although initially foreseen, and the major changes approved
  • The preliminary estimate of the utilization of tasks and resources
  • Original plans as well as any amendments adopted

Answer :Original plans as well as any amendments adopted

ISO Stands __________.


Options are :

  • Indiana Standardized Organization
  • International Standardized Organization
  • None
  • n Standardized Organization
  • International Organization for Standardization

Answer :International Organization for Standardization

You are the project manager and the project team as part of the procurement process; to hire a new employee and give him your project team. According to Maslow's hierarchy of needs, you need to level he is most likely?


Options are :

  • safety
  • Safety and security
  • None
  • a physical need
  • social need

Answer :social need

How many channels of communication needed for the project, with 5 individual involved in?


Options are :

  • 12
  • 4
  • 5
  • None
  • 10

Answer :10

The purpose of the risk management process group is ________.


Options are :

  • Report project risks
  • None
  • Indicates a project deliverables
  • Hold the risks affecting the company
  • Increase the probability of positive results in the project

Answer :Increase the probability of positive results in the project

Which of the following is a conflict resolution technique?


Options are :

  • Foimal
  • imperative
  • None
  • handicap
  • Jeopardize

Answer :handicap

You are a project manager, and now in the midst of creating an RFP (Request for Proposal). RFP (Request for Proposal) are _______.


Options are :

  • close procurement
  • behavior procurement
  • None
  • manage procurement
  • procurement plan

Answer :procurement plan

You are the project manager for the project. If it is approved changes to the original scope of what you are doing for the old original scope?


Options are :

  • Saves older versions
  • The old version is not required
  • There is no need to save the old version
  • None
  • Scrap the old version

Answer :Saves older versions

Administrative closure is a process that ________.


Options are :

  • Includes all the activities that are needed to confirm the project's products and services
  • All the above
  • Closes all activities related to a specific project
  • None
  • Collect the user's approval of the project product or service

Answer :Closes all activities related to a specific project

You are the project manager of the project, which just went to the extinction mode. This means that the project __________.


Options are :

  • S ST '' cunning but lacking resources
  • Is closed due to lack of resources
  • None
  • None of the above
  • It is finished before the set target

Answer :It is finished before the set target

That threaten the answer is likely to be unforeseen reservations?


Options are :

  • Transfer
  • None
  • mitigate
  • Adoption
  • shaie

Answer :Adoption

Who is responsible for creating a plan for the thesis?


Options are :

  • Sponsor
  • Project manager
  • None
  • The project team
  • team leader

Answer :Project manager

You are the project manager of the project, which of the following is not your responsibility?


Options are :

  • quality organization
  • None
  • Obtaining HR resources to the project team
  • All the above
  • Overall responsibility for project risk

Answer :quality organization

Who is responsible for the quality of the plan?


Options are :

  • Project manager
  • project Coordinator
  • None
  • team lead
  • QA manager

Answer :Project manager

Which is not part of the project plan?


Options are :

  • cost management plan
  • Schedule management plan
  • The scope of the project management plan
  • None
  • The project plan

Answer :The project plan

Which of the following project plan is best suited for the cost of monitoring resources?


Options are :

  • None
  • P'sk Breakdown Structure
  • Organizational Breakdown Structure
  • work breakdown structure
  • Resource Breakdown Structure

Answer :work breakdown structure

Delivery times and availability can be found in the details of __________.


Options are :

  • The project scope
  • None
  • work breakdown structure
  • sow
  • The project plan

Answer :work breakdown structure

Which relates to methods for the selection of projects to decide to accept or reject the project?


Options are :

  • The project sponsor
  • Senior management
  • None
  • Project manager
  • The project team

Answer :The project sponsor

What is the communication channel delta if the communication plan members grow 5-10?


Options are :

  • 15
  • 75
  • 35
  • 5
  • None

Answer :35

Ishikawa diagram Pareto diagram of the control schematics, and examples of statistical sampling are ________.


Options are :

  • quality Guidelines
  • Quality control
  • None
  • CMM
  • quality Insurance

Answer :Quality control

Which of the following subsidiary plan includes quality objectives of the project?


Options are :

  • Quality management plan
  • None
  • QA checklist
  • the quality of the basic level
  • process improvement plan

Answer :the quality of the basic level

During the design phase of the project, the project team members have found another way to carry out part of the project scope. This method is a safer project, but the cost may be to the customer. This is an example of _______.


Options are :

  • selection
  • product analysis
  • " 'S ^ evaluation
  • None
  • alternative identification

Answer :alternative identification

Risk Register is part of the ________.


Options are :

  • Project scheduling plan
  • The project scope
  • None
  • Project Management plan
  • The project plan

Answer :Project Management plan

You have been in the organization; you constantly hear rumors of a certain CAPM CAPM failing to live up to the code. What should be done?


Options are :

  • You can collect as much information as possible before you continue
  • To confront the person immediately
  • ^ Ass along rumors
  • None
  • Ignore rumors

Answer :You can collect as much information as possible before you continue

Work partition is ________.


Options are :

  • Set and does not change throughout the project
  • as part of the necessary project plan
  • None
  • [Necessary as part of the scope of the project
  • Used to break down the project size chunks

Answer :Used to break down the project size chunks

Every document is best suited for the task to monitor all resources to specific tasks in the project?


Options are :

  • RACI MAL, X
  • None
  • Staffing management plan
  • 0 CPI
  • sow

Answer :RACI MAL, X

You are the project manager MKTG Project. The project is estimated to cost $ 200,000 is expected to last for 2 years. The project is now 20 percent complete, and is on schedule. What is BAC?


Options are :

  • None
  • $200.00
  • $50,000
  • $0
  • None of the above

Answer :$0

Assumptions are factors that, for planning purposes, will be held ______.


Options are :

  • verbal
  • None
  • True, real or uncertain
  • Real
  • True, real, or certain

Answer :True, real, or certain

Which of the following inputs define scope?


Options are :

  • Requirements document created to collect the claim process
  • The project plan
  • Project files from previous projects
  • None
  • All the above

Answer :All the above

Requirement document is __________ input method?


Options are :

  • To monitor and control project work
  • None
  • Collect requirements
  • define scope
  • Integrated management of change

Answer :define scope

You are managing a project that will introduce a new retail software package. You have set your resources and want to keep in the loop IT manager informing him or her of your decision. What type of organizational structure you're working on?


Options are :

  • functional
  • Matrix weak
  • strong Matrix
  • Pi'ojectized
  • None

Answer :strong Matrix

Which has granted the project plan?


Options are :

  • None
  • nianagement
  • the project sponsor
  • Project manager
  • Team lead

Answer :the project sponsor

_________ is an international organization that controls the standards for quality.


Options are :

  • BIG
  • CAPM
  • None
  • PMI
  • iSCN

Answer :BIG

Which of the following techniques to identify the root cause of the problem and take action to prevent the occurrence?


Options are :

  • None
  • audits
  • quality audits
  • root cause analysis
  • project audits

Answer :root cause analysis

If a project which is SPI 1.8, what you tell?


Options are :

  • None
  • The project behind schedule
  • The project is running ahead of schedule
  • Nothing
  • Resources allocated to the project cost 1.8 units

Answer :The project is running ahead of schedule

Project quality management includes:


Options are :

  • None
  • Customer satisfaction
  • All the above
  • Prevention over inspection
  • Continuous improvement

Answer :All the above

Do-or-buying services to measure the cost of each option. What are the two options?


Options are :

  • Direct ar | d Indirect
  • Tactical and strategic
  • Management and project
  • 0nly Tactical
  • None

Answer :Direct ar | d Indirect