PMI-100 Certify Associate Project Management Practice Exam Set 8

Every process monitoring status of the project to update project costs and managing changes to the cost baseline?


Options are :

  • Cost management plan
  • determine your budget
  • control costs
  • estimate of costs
  • None

Answer : control costs

The review is the sellers to make progress towards achieving the objectives of the extent and quality within cost and schedule compared to an agreement known as:


Options are :

  • Inspections and audits.
  • Work performance information.
  • Procurement performance reviews
  • Payment systems.
  • None

Answer : Procurement performance reviews

What inputs Manage Stakeholder engagement process is used to document the changes that occur during the project?


Options are :

  • Issue log
  • Issue log
  • expert assessment
  • change requests
  • None

Answer : Issue log

Every document describes the necessary information whether the project is worth the investment needed?


Options are :

  • cost baseline
  • service level agreement
  • None
  • a letter of intent
  • Case Study

Answer : Case Study

PMI-002 Certified Associate Project Management Practice Exam Set 14

Identify Stakeholders process is found, the process in which the Group?


Options are :

  • Design
  • None
  • showing
  • Monitoring and control of
  • commencement of

Answer : commencement of

Regression analysis, failure mode and effects analysis (FMEA), Fault Tree Analysis (FTA), and trend analysis are examples of that tool or technique?


Options are :

  • expert assessment
  • None
  • Earned Value Management
  • analytical techniques
  • evaluation methods

Answer : analytical techniques

Whose contribution to the risk management process plan provides information about a high level of risk?


Options are :

  • register of interest groups
  • Environmental factors
  • Organizational process assets
  • None
  • The project plan

Answer : The project plan

Input Cost management plan process is:


Options are :

  • The project plan,
  • Cost estimates.
  • Resource calendars,
  • Risk Register.
  • None

Answer : The project plan,

Each input provides clear objectives, requirements, and the results of your suppliers?


Options are :

  • exclamation conference
  • None
  • source selection
  • Procurement statement of work
  • purchase order

Answer : Procurement statement of work

By the input of stakeholders on the process data is internal or external parties related to the project?


Options are :

  • None
  • register of interest groups
  • The project plan
  • the procurement documents
  • a communication plan

Answer : The project plan

PMP Certification Questions

The process of creating policies, procedures, and documentation of the planning, development, management, execution and control the project schedule is known:


Options are :

  • To develop a project plan
  • Scope Management Plan.
  • Schedule Management Plan.
  • None
  • Develop a schedule

Answer : Schedule Management Plan.

The output process is to confirm Credits:


Options are :

  • The scope of the management plan.
  • A traceability requirements matrix.
  • None
  • change requests
  • Work performance reports

Answer : change requests

Market conditions and the published commercial information are examples, which are applied to estimate the cost of the process?


Options are :

  • risk register
  • Environmental factors
  • Organizational process assets
  • The extent of baseline
  • None

Answer : Environmental factors

The project manager is appointed full-time to the project and providing full-time administrative staff and full-time project team members. This situation illustrates the type of organizational structure?


Options are :

  • Projectized
  • weak matrix
  • balanced matrix
  • functional
  • None

Answer : Projectized

What is the object of a formal proposal to amend the document, outputs or baseline?


Options are :

  • documentation requirements
  • change request
  • The extent of baseline
  • None
  • Risk assessment of urgency

Answer : change request

In any process to determine risks, which may affect the project and documenting their characteristics?


Options are :

  • Planned Risk Responses
  • to manage the risks
  • The risk management plan
  • None
  • identify risks

Answer : identify risks

PMI-SP Scheduling Professional Practice Exam Set 2

That the process of developing options and actions to opportunities and reduce threats to project objectives?


Options are :

  • identify risks
  • to manage the risks
  • The risk management plan
  • None
  • Planned Risk Responses

Answer : Planned Risk Responses

Input plan for stakeholder management process is:


Options are :

  • None
  • Stakeholder analysis
  • The project plan.
  • The communication management plan.
  • A stakeholder analysis register.

Answer : A stakeholder analysis register.

What tool or technique is used in the scope of the plan management process?


Options are :

  • None
  • expert assessment
  • product analysis
  • document analysis
  • sightings

Answer : expert assessment

Every group is officially chartered and is responsible for reviewing, evaluating, approving, delaying or rejecting changes to the project and for recording and communicating decisions?


Options are :

  • The change control board
  • Target group
  • None
  • The project team
  • project stakeholders

Answer : The change control board

Planned Schedule Management is a process in which area of ??expertise?


Options are :

  • Project Time Management
  • Project Human Resource Management
  • The scope of the project management
  • Project Integration Management
  • None

Answer : Project Time Management

What type of addiction is by law or by agreement or the nature of the work, and often physical limitations?


Options are :

  • internal
  • None
  • discretionary
  • Obligatory
  • external

Answer : Obligatory

That there are changes in risk and uncertainty and the cost of changes to the life cycle of a typical project progresses?


Options are :

  • Risk and uncertainty reduction; changes in cost increases.
  • Risk and uncertainty reduction; changes in the cost is reduced.
  • Risk and uncertainty about growth; changes in the cost decreases,
  • None
  • Risk and uncertainty about growth; changes in cost increases.

Answer : Risk and uncertainty reduction; changes in cost increases.

The extent, timing and cost of the integrated parameters:


Options are :

  • None
  • Analysis of the project forecasts
  • Performance measurement output level.
  • Analysis of past performance.
  • Overview of the changes adopted at a time

Answer : Performance measurement output level.

What inputs Manage Stakeholder engagement process will guide you how stakeholders can best be involved in the project?


Options are :

  • communications management plan
  • Stakeholder management plan
  • None
  • stakeholder analysis
  • Feedback analysis

Answer : Stakeholder management plan

Input Manage project the process is:


Options are :

  • None
  • Activity resource requirements.
  • Enterprise environmental factors.
  • Work performance reports.
  • change requests

Answer : Work performance reports.

What tools or techniques used to plan, schedule management process?


Options are :

  • Statistical sampling, benchmarking, and meetings
  • Negotiations, pre-assignment and multi-criteria decision analysis
  • Expert assessment, analysis methods, and meetings
  • Benchmarking, expert analysis and analytical techniques
  • None

Answer : Expert assessment, analysis methods, and meetings

Which is the basic quality of the tool is most useful when collecting data attributes inspection to identify defects?


Options are :

  • None
  • Pareto diagrams
  • control Cards
  • Checksheets
  • Ishikawa diagrams

Answer : Checksheets

PMI-RMP PMI Risk Management Professional Practice Test Set 5

Perform Integrated Change Control process takes place in the method group?


Options are :

  • showing
  • Design
  • None
  • commencement of
  • Monitoring and control of

Answer : Monitoring and control of

during which the process is the project manager to review all previous data in order to ensure that all project work is complete and that the project has met its objectives?


Options are :

  • The extent of control
  • Near the project or phase
  • None
  • Perform quality assurance
  • To monitor and control project work

Answer : Near the project or phase

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions