PMI-100 Certify Associate Project Management Practice Exam Set 7

What tool or technique is the study of characteristics of the industry and how certain vendors?


Options are :

  • independent forecasts
  • None
  • Bidder conferences
  • market research (Correct)
  • analytical techniques

Answer : market research

The procedure, which ensures the availability of human resources and to have the team necessary to complete the project activities are known:


Options are :

  • Plan for Human Resource Management.
  • None
  • Manage project team.
  • To develop the project team.
  • Acquire project team. (Correct)

Answer : Acquire project team.

A large part of the budget of projects is typically consumed in the processes in which the process group?


Options are :

  • None
  • Closure
  • showing
  • Monitoring and control of
  • Design (Correct)

Answer : Design

Planned stakeholder management process belongs to which group process?


Options are :

  • None
  • Design (Correct)
  • commencement of
  • showing
  • Monitoring and control of

Answer : Design

PMI-SP Scheduling Professional Practice Exam Set 6

The project manager of information to the right audience, in the right format, at the right time is an example of the type of communication?


Options are :

  • Effective
  • Pull
  • Push
  • effective (Correct)
  • None

Answer : effective

Process for obtaining an early stage of the feedback requirements by providing a working model of the expected product before actually building are known:


Options are :

  • prototyping (Correct)
  • Benchmarking.
  • In connection with the diagrams.
  • Brainstorming
  • None

Answer : prototyping

The project charter is the output of the method group?


Options are :

  • None
  • commencement of (Correct)
  • Design
  • Closure
  • showing

Answer : commencement of

Is the organizational tool that Project Human Resource Management process?


Options are :

  • Plan for Human Resource Management (Correct)
  • manage Project Team
  • Develop Project Team
  • acquire Project Team
  • None

Answer : Plan for Human Resource Management

Each input can affect the quality of work should be monitored within the framework of the system configuration management?


Options are :

  • documentation requirements
  • project documents (Correct)
  • The extent of baseline
  • None
  • Work performance information

Answer : project documents

Output project to develop a process to:


Options are :

  • Organizational charts and descriptions of the location.
  • Enterprise environmental factors updates. (Correct)
  • The project personnel tasks.
  • Organizational process assets.
  • None

Answer : Enterprise environmental factors updates.

PMI-RMP PMI Risk Management Professional Practice Test Set 6

Check-in is used in the development of communications management plan are:


Options are :

  • Interaction Models.
  • Organizational Communication,
  • None
  • Organization of Cultural and styles.
  • Environmental factors (Correct)

Answer : Environmental factors

The method used for the cause and degree of difference between the baseline and the actual performance is:


Options are :

  • Document analysis,
  • Analysis of variance (Correct)
  • Decomposition.
  • Product Analysis.
  • None

Answer : Analysis of variance

Every stakeholder classification model groups of stakeholders based on their level of authority to the project and their active participation?


Options are :

  • Power / interest grid
  • None
  • salience model
  • Power / influence grid (Correct)
  • The effect / impact on the grid

Answer : Power / influence grid

What is the target input to the Define Activities process?


Options are :

  • None
  • activity list
  • schedule data
  • risk register
  • The extent of baseline (Correct)

Answer : The extent of baseline

Input Develop a project plan is a / an:


Options are :

  • Cost Forecast.
  • Action in the list.
  • None
  • The project management plan.
  • Case Study. (Correct)

Answer : Case Study.

Environmental factors are income, which in the process?


Options are :

  • Collect requirements
  • None
  • The scope of the plan Management (Correct)
  • The extent of control
  • define scope

Answer : The scope of the plan Management

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 8

The process to identify and document project roles, responsibilities, required skills, and reporting relationships and create a personnel management plan known as:


Options are :

  • Plan for Human Resource Management. (Correct)
  • Acquire project team.
  • To develop the project team.
  • None
  • Manage project team.

Answer : Plan for Human Resource Management.

When the alternative dispute resolution (ADR) is necessary, which tool or technique should be used?


Options are :

  • interactive communication
  • Conflict management
  • performance reporting
  • claims administration (Correct)
  • None

Answer : claims administration

Perform quality assurance process takes place in the method group?


Options are :

  • showing (Correct)
  • Monitoring and control of
  • Design
  • None
  • commencement of

Answer : showing

Element project scope statement is:


Options are :

  • High-level risks.
  • A stakeholder analysis list.
  • Summary of the budget,
  • None
  • Accreditation criteria. (Correct)

Answer : Accreditation criteria.

What plan schedule management tool or technique may be associated with choosing strategic options to evaluate and schedule of the project?


Options are :

  • Analysis of variance
  • analytical techniques (Correct)
  • expert assessment
  • facilitation techniques
  • None

Answer : analytical techniques

The only method of group containing processes, which typically take place from the beginning to the end of the project life cycle:


Options are :

  • The monitoring and control. (Correct)
  • None
  • Design.
  • Closure
  • showing

Answer : The monitoring and control.

The iterative and interactive nature of the process creates the need for groups of processes, in which area of ??expertise?


Options are :

  • None
  • project Risk Management
  • Project Communications Management
  • Project Integration Management (Correct)
  • The scope of the project management

Answer : Project Integration Management

Change requests are processed for review and investment, according to which method?


Options are :

  • To monitor and control project work
  • The extent of control
  • None
  • Quality control
  • Perform Integrated Change Control (Correct)

Answer : Perform Integrated Change Control

The project, which will move the scope, time and cost of delivery is determined as early as possible follow a life cycle that is:


Options are :

  • adaptable
  • None
  • iterative
  • incremental
  • Anticipatory (Correct)

Answer : Anticipatory

That the quality of management and control instrument is useful for visualizing the parent-child relationship in any degradation of the hierarchy, which uses a systematic set of rules which define the nests in a relationship?


Options are :

  • network diagram
  • The interaction between combinations of letters
  • the affinity diagram
  • None
  • tree diagram (Correct)

Answer : tree diagram

What tool or technique is a powerful project, which physically is not a service or leads?


Options are :

  • product analysis (Correct)
  • None
  • decomposition
  • Analysis of variance
  • inspection

Answer : product analysis

to evaluate the process, the type and amount of material, personnel, equipment, or supplies required to perform each activity is called:


Options are :

  • Estimate Activity Durations
  • None
  • Estimate Activity Resources. (Correct)
  • Conduct procurement.
  • Collect Requirements.

Answer : Estimate Activity Resources.

PMI-100 Certified Associate in Project Management Test Set 2

What is the schedule performance index (SPI) if the planned (PV) is $ 100 for the actual cost (AC) is $ 150 and earned value (EV) 50 $?


Options are :

  • 0.67
  • 2
  • 1.5
  • None
  • 0.5 (Correct)

Answer : 0.5

Which defines how the project is executed, monitored and controlled, and closed?


Options are :

  • The project management plan (Correct)
  • None
  • strategic plan
  • service level agreement
  • The project plan

Answer : The project management plan