The project manager who communicates project team though email to use which type of communication?


Options are :

  • horizontal
  • Unofficial
  • None
  • Unofficial
  • Formal

Answer : Unofficial

By correlating and contextualized information on how precisely the scope is maintained with respect to the scope base level is inside:


Options are :

  • change requests.
  • update project documents.
  • work performance information.
  • project management plan updates.
  • None

Answer : work performance information.

Variance and trend analysis is a tool and technique used in that process?


Options are :

  • None
  • to manage the risks
  • Planned Risk Responses
  • Perform Qualitative Risk Analysis
  • quantitative risk analysis

Answer : to manage the risks

The question is a log entry, which the Project Human Resource Management process?


Options are :

  • manage Project Team
  • Develop Project Team
  • None
  • acquire Project Team
  • Plan for Human Resource Management

Answer : manage Project Team

PMI Practice Questions

Effects on other areas of the organization, the level of service, and acceptance criteria are typical components of which document?


Options are :

  • None
  • work breakdown structure
  • Case Study
  • documentation requirements
  • risk register

Answer : documentation requirements

The component has a risk management plan that documents how risky activity recorded is called:


Options are :

  • tracking
  • None
  • cropping
  • defining
  • timing

Answer : tracking

Grouping the stakeholders based on their level of concern over the authorities and their level of project results which describes the classification model for stakeholder analysis?


Options are :

  • salience model
  • The effect / impact on the grid
  • Power / interest grid
  • Power / influence grid
  • None

Answer : Power / interest grid

The tools and techniques are used to direct and manage project work are:


Options are :

  • None
  • Expert assessment and meetings
  • Development discussions and meetings
  • Process analysis and expert judgment
  • The methods of analysis and project management information system

Answer : Expert assessment and meetings

Whose approval may be needed for change requests after the change (CCB) approval?


Options are :

  • None
  • functional leaders
  • subject matter experts
  • business Partners
  • Customers or sponsors

Answer : Customers or sponsors

When the business objectives of the organization change, the objectives of the project will be:


Options are :

  • None
  • controlled
  • realigned
  • improved
  • completed

Answer : realigned

PMI-SP Scheduling Professional Practice Exam Set 8

Every element of the project plan does contain?


Options are :

  • None
  • management reserves
  • register of interest groups
  • stakeholder list
  • work breakdown structure

Answer : stakeholder list

Every process is carried out from the beginning of the project when filling and is ultimately the responsibility of the project manager?


Options are :

  • To monitor and control project work
  • Perform Integrated Change Control
  • Quality control
  • None
  • The extent of control

Answer : Perform Integrated Change Control

Project managers who lead by example and to comply with the commitments they make to show the key interpersonal skill:


Options are :

  • motivation
  • management
  • influencing
  • None
  • training

Answer : influencing

Who carry out quality assurance tool or technique is used to identify the problem, find the reasons that lead to it, and develop preventive measures?


Options are :

  • quality audits
  • root cause analysis
  • inspection
  • Design of Experiments
  • None

Answer : root cause analysis

At the beginning of a typical project life cycle costs are:


Options are :

  • high, drop down when work is being done, and the growth of the project nears the end
  • None
  • high, becomes low as the work is done, and drop the project nears the end.
  • low, top, when the work is done, and drop the project nears the end.
  • low, will be steady when the work is done, and the growth of the project nears the end

Answer : low, top, when the work is done, and drop the project nears the end.

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 1

Success is measured benefits for execution:


Options are :

  • program
  • project
  • portfolio
  • strategic plan
  • None

Answer : portfolio

Which is an enterprise environmental factor?


Options are :

  • Project files from previous projects
  • Policies and procedures
  • Lessons learned from previous projects
  • None
  • Marketplace conditions

Answer : Marketplace conditions

The project stakeholder management will focus on:


Options are :

  • None
  • The project tea m acquisition
  • the management of conflicts of interest
  • Project Loan staff
  • means of communication

Answer : the management of conflicts of interest

The project manager should communicate to stakeholders about the project to solve the issues by updating:


Options are :

  • register of interest groups
  • None
  • project records
  • ads stakeholders
  • project reports

Answer : ads stakeholders

Organizational process assets, a database of lessons learned and historical information are all the income to which the process?


Options are :

  • The scope of the plan Management
  • Planned stakeholder management
  • Cost management plan
  • None
  • Planned Schedule Management

Answer : Planned stakeholder management

When painting the bedroom, preparing for the walls can be made when the paint is selected. This is an example:


Options are :

  • to lead
  • mandatory addiction
  • delay
  • None
  • internal dependency

Answer : to lead

PMI-SP Scheduling Professional Certification Practical Exam Set 7

The lowest level is generally described in the work division (VVBS) is called a / an:


Options are :

  • work package
  • performance
  • None
  • activity
  • milestone

Answer : work package

Every project plan is updated Control Stakeholder engagement process?


Options are :

  • None
  • Issue log
  • Work performance information
  • Lessons learned documentation
  • project reports

Answer : Issue log

Every Project Time Management process involves a bottom-up tool to assess or technology?


Options are :

  • Estimate Activity Durations
  • None
  • Develop a schedule
  • Estimate Activity Resource
  • The sequence Action

Answer : Estimate Activity Resource

The disadvantage of virtual teams is that they:


Options are :

  • Create difficulties including those with disabilities.
  • Create a chance of misunderstandings.
  • None
  • Require communication technology, which is not readily available.
  • Often unable to accommodate teams that operate at different hours or shifts.

Answer : Create a chance of misunderstandings.

In a typical project, project managers spend most of their time:


Options are :

  • It is estimated
  • control of
  • Communicating
  • None
  • scheduling

Answer : Communicating

Methodology, which combines scope, schedule and resource measurements to evaluate the success of the project and progress known as:


Options are :

  • None
  • The critical path method.
  • The critical chain method.
  • Divination.
  • Earned value management.

Answer : Earned value management.

PMI-RMP PMI Risk Management Professional Practice Test Set 6

By the schedule method allows the project team to set bumpers path project schedule into account the limited resources and the project's uncertainties?


Options are :

  • The critical chain method
  • None
  • resource leveling
  • Schedule network analysis
  • critical path

Answer : The critical chain method

The advantage of the virtual teams Acquire project is to reduce the process:


Options are :

  • the cost of technology
  • cultural differences of team members
  • None
  • the cost of travel
  • The possibility of communication misunderstandings

Answer : the cost of travel

What are the risks if the probability of occurrence rating is 0.30, and the effect, if it occurs with moderate (0.20)?


Options are :

  • 0.03
  • 0.1
  • 0.06
  • None
  • 0.5

Answer : 0.06

Each process is defined, documentation and management of the stakeholders' needs and meets the requirements of the project objectives?


Options are :

  • define scope
  • Collect requirements
  • None
  • The scope of the plan Management
  • Define Action

Answer : Collect requirements

The scope and extent of the treatment plan at baseline included:


Options are :

  • The project management plan
  • traceability matrix
  • the project plan
  • None
  • organizational process assets

Answer : The project management plan

Every document project management plan can be upgraded to plan procurement management process?


Options are :

  • None
  • budget estimates
  • documentation requirements
  • the procurement documents
  • risk matrix

Answer : documentation requirements

PMI-100 Certified Associate Project Management Practice Exam Set 6

A special bar is used for the sensitivity analysis of the relative importance of the variables are called:


Options are :

  • fishbone diagram
  • None
  • the beta distribution
  • tornado chart
  • a triangular distribution

Answer : tornado chart

Project management processes ensure that:


Options are :

  • effective means to achieve the objectives of the project
  • the performance of the project team
  • None
  • effective flow during the entire project life cycle
  • Harmonization of the organization's strategy

Answer : effective flow during the entire project life cycle

M & A projects purpose or justification, measurable project objectives and related success criteria, a summary of a milestone schedule, summary and budget are factors that document?


Options are :

  • work breakdown structure
  • The project management plan
  • None
  • requirements document
  • The project plan

Answer : The project plan

In order for stakeholders with low interest and high power output, the project will:


Options are :

  • Keep track of stakeholders.
  • accurately manage stakeholders.
  • Keep your stakeholders happy.
  • Keep stakeholders informed.
  • None

Answer : Keep your stakeholders happy.

Project Human Resource Management process, for which the availability and the strengthening of human resources to get the team necessary to complete the project activities is:


Options are :

  • manage Project Team
  • Plan for Human Resource Management.
  • Acquire project team.
  • To develop the project team.
  • None

Answer : Acquire project team.

The risk of operational strategy in which the project is to reduce the likelihood or effect of danger are known:


Options are :

  • mitigate
  • avoid
  • Ice
  • None
  • exploit

Answer : mitigate

PMI-001 PMP V5 Planning Certification Practice Exam Set 4

That define the Action tool or technique is used to share and dividing by the scale of the project and the project deliverables into smaller, more manageable parts?


Options are :

  • inspection
  • decomposition
  • document analysis
  • None
  • project Analysis

Answer : decomposition

Which objects are part of the project management plan?


Options are :

  • Change management plan, process improvement plan, and the extent of the treatment plan
  • Contracts, procurement management plan and work performance information
  • None
  • The schedule management plan, project schedule and resource calendars
  • Scope baseline, the project statement of work and the traceability matrix

Answer : Change management plan, process improvement plan, and the extent of the treatment plan