PMI-100 Certified Associate Project Management Practice Exam Set 8

Another name for the Ishikawa diagram is:


Options are :

  • cause and effect diagram.
  • flow chart.
  • the control scheme.
  • the histogram.
  • None

Answer : cause and effect diagram.

What is the most accurate rough order of magnitude (ROM)?


Options are :

  • The planning stage, the estimate is between +/- 50%.
  • None
  • Monitoring and control stage, the estimate of +/- 15%.
  • In the Closure stage, the estimate is +/- 15%.
  • In the initiation stage, the estimate is between +/- 50%.

Answer : In the initiation stage, the estimate is between +/- 50%.

Which of the following is the output Perform Integrated Change Control Management process?


Options are :

  • Organizational process assets updates
  • change requests
  • None
  • PROJECT DOCUMENT Updates
  • Outputs

Answer : PROJECT DOCUMENT Updates

Control charts, flow charts, histograms, Pareto charts, and scatter diagrams are tools and techniques that process?


Options are :

  • The quality plan
  • Perform quality assurance
  • None
  • Performance report
  • Perform Quality Control

Answer : The quality plan

PMPĀ® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 13

Which of the following events would lead to a basic level of upgrade?


Options are :

  • The customer has accepted the change request to extend the scope of the project and a budget increase.
  • None
  • One of the risks identified in the risk management plan is done, what the schedule delay.
  • One of the main resources of the project team has left the team and no replacement is available.
  • The project has been delayed and the project manager wants the baseline to meet the estimated real end.

Answer : The customer has accepted the change request to extend the scope of the project and a budget increase.

Which has the following outputs Control Schedule process aids communication schedule variance (SV), schedule performance index (SPI), or any of the performance of the stakeholders?


Options are :

  • the performance of organizations
  • change requests
  • Work performance measurements
  • schedule baselines
  • None

Answer : Work performance measurements

Which of the following is the output of direct and manage project execution?


Options are :

  • The project management plan
  • Organizational process assets updates
  • Change request status updates
  • None
  • Work performance information

Answer : Work performance information

What is a tool to improve the team's performance?


Options are :

  • earnings Reports
  • Co-location
  • external feedback
  • None
  • staffing plan

Answer : Co-location

What cost technology includes contingencies account the uncertainty of costs?


Options are :

  • The three-point reviews
  • Editor's offer analysis
  • booking analysis
  • None
  • parametric estimation

Answer : booking analysis

Which provides inputs to the original estimates the duration missions to the project plan?


Options are :

  • None
  • Project manager
  • The person who best knows the task
  • The person responsible for project scheduling
  • The project sponsor

Answer : The person who best knows the task

PMI Risk Management Professional Certification Practice Exam Set 4

A written document to help monitor who is responsible to solve specific problems and concerns of the target value far?


Options are :

  • None
  • The project plan
  • Issue Log
  • Responsibility Matrix
  • Scope of Document

Answer : Issue Log

What is the standard interconnection with other project management disciplines such as management and portfolio management programs?


Options are :

  • Organizational Project Management Maturity Model (OPM3 $)
  • Program Management Body of Knowledge Guide
  • Standard Program Management
  • Guide to the Project Management Body of Knowledge (PMBOKĀ®)
  • None

Answer : Guide to the Project Management Body of Knowledge (PMBOKĀ®)

PV is the $ 1,000 EV is $ 2,000 and $ AC is 1500. What is the CPI?


Options are :

  • 2
  • None
  • 0.75
  • 1.33
  • 0.5

Answer : 1.33

Which of the following is an input to Run a Qualitative during the risk analysis?


Options are :

  • risk register
  • None
  • risk of urgency
  • Risk assessment of the quality of information
  • risk rating

Answer : risk register

Types of internal failure costs are:


Options are :

  • editing and scrapping.
  • lost business.
  • inspections
  • None
  • equipment and training.

Answer : editing and scrapping.

Which is an input to check the extent of the process?


Options are :

  • performance report to the
  • requested changes
  • The project management plan
  • None
  • Work breakdown structure (WBS)

Answer : The project management plan

PMI-100 Certified Associate Project Management Practice Exam Set 11

Which of the following types of dependency assay is used to determine the sequence of activities?


Options are :

  • discretionary
  • Resource
  • internal
  • None
  • legal

Answer : discretionary

Managing relationships with procurement and monitoring of the performance of the agreement which are part of the process?


Options are :

  • procurement plan
  • close procurement
  • manage procurement
  • behavior procurement
  • None

Answer : manage procurement

Which of the following is an input to control the extent of?


Options are :

  • project schedule
  • PROJECT DOCUMENT Updates
  • Work performance information
  • None
  • Organizational process assets updates

Answer : Work performance information

Which of the following correctly explain the term "progressive elaboration?


Options are :

  • Changing the project specifications constantly
  • Establish a change control system monitoring the project specifications
  • None
  • Establish monitoring progress of the project
  • The project Provisions increasingly clear and detailed as the project progresses

Answer : The project Provisions increasingly clear and detailed as the project progresses

Which of the following is the primary output process to identify risks?


Options are :

  • None
  • change requests
  • risk register
  • Risk Management plan
  • The risk response plan

Answer : risk register

Which has an outlet to share information?


Options are :

  • Earned value analysis
  • trend Analysis
  • performance Reviews
  • None
  • project records

Answer : project records

PMPĀ® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 13

Co-location is a tool and technique:


Options are :

  • Develop Human Resource Plan.
  • Acquire project team.
  • To develop the project team.
  • manage Project Team
  • None

Answer : To develop the project team.

The project manager needs to review designs in use. The models are part of:


Options are :

  • Corporate knowledge base.
  • Organizational process assets.
  • None
  • Historical information,
  • Enterprise environmental factors.

Answer : Organizational process assets.

Which of the following strategies are used to deal with risks that may have a negative impact on the objectives of the project?


Options are :

  • Exploit
  • Improve
  • Ice
  • Transfer
  • None

Answer : Transfer

What type of organizational structure are grouped by specialty staff?


Options are :

  • None
  • functional
  • Matrix
  • balanced
  • Projectized

Answer : functional

What tool or technique is used to Close procurement?


Options are :

  • procurement plan
  • None
  • contract plan
  • procurement audits
  • the closure of

Answer : procurement audits

The process to identify the information needs of the stakeholders will be completed during the period:


Options are :

  • plan Communications
  • Manage stakeholder expectations.
  • Identify Stakeholders
  • None
  • Stakeholder analysis.

Answer : plan Communications

PMI-100 Certify Associate Project Management Practice Exam Set 8

In dealing with the roles and responsibilities that point to ensure that staff have the knowledge to meet the project activities?


Options are :

  • responsibility
  • authority
  • Role
  • qualification
  • None

Answer : qualification

The construction schedule, which is a logical relationship between the concrete delivery and pouring of concrete?


Options are :

  • Start finish (SF)
  • None
  • Rnish finish (FF)
  • Start-start (SS)
  • Ready-start (FS)

Answer : Ready-start (FS)