PMI-100 Certified Associate Project Management Practice Exam Set 4

The project manager has created a problem of the way to record things served during the project members weekly team meetings. This is the entry:


Options are :

  • None
  • The risk management plan
  • Performance report
  • Manage stakeholder expectations.
  • Monitor and Control Risks

Answer : Manage stakeholder expectations.

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?


Options are :

  • The three-point estimate
  • None
  • Modeling and Simulation
  • The expected monetary value analysis
  • sensitivity analysis

Answer : The expected monetary value analysis

Which of the following is the output Close procurement?


Options are :

  • Managing stakeholder expectations
  • earnings Reports
  • None
  • Organizational process assets updates
  • Accepted deliverables

Answer : Organizational process assets updates

PMI-SP Scheduling Professional Practice Exam Set 2

Probability and impact matrix is ??mainly used for:


Options are :

  • To develop a risk register risk planning
  • In terms of volume of risk issues during quality inspection trends
  • Evaluated during each Riska € ™ s importance and priority Tee Qualitative Risk Analysis
  • Define risk and comparing term effects of quantitative risk analysis
  • None

Answer : Evaluated during each Riska € ™ s importance and priority Tee Qualitative Risk Analysis

The group technique, which improves with brainstorming used in the voting process, investing in the most useful ideas prioritization is called:


Options are :

  • The thought / mind mapping technique
  • None
  • The nominal group technique
  • the majority of power engineering
  • The Delphi technique

Answer : The nominal group technique

The detailed steps of the process development plan for the analysis in order to identify which improve their:


Options are :

  • technical performance
  • Status
  • Quality.
  • Value.
  • None

Answer : Value.

PMI Risk Management Professional Certification Practice Exam Set 9

Which of the following can be used as an input to determine the area?


Options are :

  • The extent of baseline
  • product analysis
  • The project plan
  • The project scope
  • None

Answer : The project plan

During the preparation of the project management plan on a weekly basis, the project manager says Intention to report to the personnel questions by e-mail. Where part of the plan for this kind of information can be included?


Options are :

  • Quality management plan
  • Communications management plan
  • Human resource management plan
  • procurement management plan
  • None

Answer : Communications management plan

At what stage of development do team members begin to work together, adjust working methods, and trust each other?


Options are :

  • forming
  • performing
  • norms
  • storming
  • None

Answer : norms

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 6

Which of the following is a group decision-making technique?


Options are :

  • None
  • the affinity diagram
  • Target groups
  • Brainstorming
  • several

Answer : several

One of the goals is a quality inspection is:


Options are :

  • underline the need for root cause analysis
  • None
  • identify any gaps or defects
  • to provide assistance to non-value added activities
  • to share the documentation process among stakeholders

Answer : identify any gaps or defects

What tool or technique can be used project manager to choose in advance a team member who is critically important task?


Options are :

  • counsel
  • virtual team
  • pre-assignment
  • Acquisition
  • None

Answer : pre-assignment