PMI-100 Certified Associate Project Management Practice Exam Set 3

Which of the following is a tool or technique used in Determine Budget procedure?


Options are :

  • The three-point estimation
  • The bottom-up assessment of the
  • Analysis of variance
  • None
  • historical relations

Answer : historical relations

The project life cycle is defined as follows:


Options are :

  • recognized standard for the project management profession.
  • a process is needed to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
  • None
  • the application of knowledge, skills, tools and techniques to project activities to meet project requirements.
  • a collection of generally sequential and sometimes overlapping project phases.

Answer : a collection of generally sequential and sometimes overlapping project phases.

Which process is responsible for monitoring the status of the project and the scope of the product and the extent of managing changes to the baseline?


Options are :

  • to review the scope of the
  • Analysis of variance
  • define scope
  • The extent of control
  • None

Answer : The extent of control

Tool and the Define Extent used during the process is:


Options are :

  • surveys and studies
  • group creativity techniques
  • facilitated workshops.
  • findings
  • None

Answer : facilitated workshops.

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 11

Which of the following strategies for action agreed to negative risks or threats?


Options are :

  • Exploit, enhance, share or accept
  • To avoid, mitigate, transfer or accept
  • Mitigate, Share, avoid or accept
  • None
  • Share, accept, transfer, or mitigate

Answer : To avoid, mitigate, transfer or accept

Every process is a collection of processes performed in a pre-defined project management plan to satisfy the specifications of the project?


Options are :

  • Closure
  • commencement of
  • Design
  • showing
  • None

Answer : showing

The risk is divided buyer and seller is determined


Options are :

  • None
  • risk register.
  • The default log.
  • quality checklist
  • Type of contract

Answer : Type of contract

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 4

Total planned (PV), also known as


Options are :

  • earned value baseline
  • schedule target
  • None
  • performance measurement baseline (PMB).
  • work breakdown structure (WBS).

Answer : performance measurement baseline (PMB).

After allowing the agency will take longer than planned to issue a permit, this risk can be described as:


Options are :

  • answer,
  • effect.
  • None
  • event.
  • understanding.

Answer : event.

The process to ensure that appropriate quality standards and operational definitions are used:


Options are :

  • None
  • Perform Quality Control
  • Perform quality assurance
  • Plan Quality.
  • Full quality control

Answer : Perform quality assurance

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 2

Project management processes are generally shown as separate interfaces of the processes defined, although in practice they


Options are :

  • None
  • overlapping and interacting
  • are independent of
  • move sequence
  • move together in batches

Answer : overlapping and interacting

Plan-do-check-act also known as


Options are :

  • continuous improvement
  • statistical sampling
  • management responsibility
  • Prevention over inspection
  • None

Answer : continuous improvement

carrying out the process of variance may vary, depending on:


Options are :

  • the work will be completed next
  • of application used for the standard and the industry
  • working relationship with the various stakeholders and team members
  • scenario development, technology forecasting, and forecasting by analogy.
  • None

Answer : of application used for the standard and the industry

PMI-SP Scheduling Professional Certification Practice Test Set 7

The processes required to set up the scope of the project, refine the objectives and define the course of action needed to achieve the objectives that the project is committed to achieving the grouping who process the Group?


Options are :

  • Monitoring and control of
  • Design
  • commencement of
  • None
  • showing

Answer : Design

The Project Manager publishing company decides to initiate the editing phase of the project as soon as each chapter is written. What type of sequence Operating tool and technique is involved, considering that was the beginning of a bootable relationship with 15-day delay?


Options are :

  • Float
  • None
  • To lead
  • loose
  • delay

Answer : delay

Every entry will be used in the task is to develop the human resource management plan?


Options are :

  • Project staff assignments
  • resource calendar
  • None
  • The project management plan
  • Activity resource requirements

Answer : Activity resource requirements

PMP Certification

Which of the following are company environmental factor that can affect the risk identification process?


Options are :

  • academic studies
  • assumptions logs
  • None
  • Work performance reports
  • network diagrams

Answer : academic studies

Manage Procurement is part of that process group?


Options are :

  • None
  • showing
  • Design
  • Monitoring and control of
  • Closure

Answer : Monitoring and control of

The end of the project scope is measured against:


Options are :

  • The project scope.
  • documentation requirements
  • The project management plan
  • None
  • work performance measurements.

Answer : The project management plan

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 6

The scope of the control which input is compared to the actual results to verify whether corrective action is needed of the project?


Options are :

  • The extent of baseline
  • change management
  • None
  • cost baseline
  • Scope Management Plan

Answer : The extent of baseline

What type of addiction is the nature of the contract or the nature of work?


Options are :

  • external
  • None
  • Obligatory
  • To lead
  • discretionary

Answer : Obligatory

PMI-002 Certified Associate Project Management Practice Exam Set 14

With the cost variance is negative and schedule variance is positive, the project is:


Options are :

  • complete; all the planned values have been earned
  • budget support and behind schedule.
  • on schedule
  • over budget and ahead of schedule
  • None

Answer : over budget and ahead of schedule

Which of the following is the assessment of the technology, which uses a previous similar projects to evaluate the parameters of the same parameter or measure of a current project?


Options are :

  • parametric estimation
  • analog estimation
  • None
  • booking analysis
  • The three-point estimation

Answer : analog estimation

Each index is calculated projection of cost performance that can be achieved in the remaining work to meet a specified management objective?


Options are :

  • Score at the end of the
  • None
  • schedule performance
  • to-complete performance
  • cost-effectiveness

Answer : to-complete performance

PMI-100 Certified Associate Management Practical Exam Set 3

The tool used to collect and during the process requirements to:


Options are :

  • expert assessment
  • Identifying alternatives
  • analysis of the product
  • prototypes
  • None

Answer : prototypes

Development of a prototype can be used as a tool, which of the following risk strategies?


Options are :

  • Avoid
  • Exploit
  • None
  • Accept
  • mitigate

Answer : mitigate

Which of the following is how the requirements of the activities planned, monitored and reported?


Options are :

  • Schedule Baseline
  • requirements management plan
  • None
  • Configuration management plan
  • The extent of baseline

Answer : requirements management plan

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 1

Which one correctly describes the value of the business case?


Options are :

  • It provides in the event of alternative dispute resolution mechanisms by default agreement
  • It provides necessary information about whether the project is worth the investment needed
  • It is used to assist the project manager to understand the extent of the commercial interests of
  • It offers one of a number of alternative scenarios that help to carry out a qualitative risk analysis
  • None

Answer : It provides necessary information about whether the project is worth the investment needed

Which of the following is a tool and technique used to track risks?


Options are :

  • benchmarking
  • at the expense of quality
  • Cost-effectiveness Baseline
  • Technical performance measurement
  • None

Answer : Technical performance measurement

The agreement, which the seller shall be replaced by the performance of all eligible costs, contract work and then pay a bonus based on the achievement of certain financial targets are called:


Options are :

  • None
  • Cost Plus Fee Contract (CPIF).
  • Fixed price Contract fee (FPIF).
  • Contract and material (T & M).
  • Cost plus fixed fee contract (CPFF).

Answer : Cost Plus Fee Contract (CPIF).

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 12

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions