PMI-100 Certified Associate Project Management Practice Exam Set 11

It is used to estimate the regression line:


Options are :

  • The upper and lower specification limit control scheme.
  • How to change the value of the independent variables affect the dependent variable.
  • None
  • Central tendency, dispersion, and shape of the statistical distribution.
  • The process is stable or has predictable performance.

Answer : How to change the value of the independent variables affect the dependent variable.

Each project time management process includes an analysis of reserves as a tool or technique?


Options are :

  • Estimating activity resources
  • Action sequences
  • None
  • Activity duration estimates
  • Timetable

Answer : Activity duration estimates

Payback period, return on investment, internal rate of return rate of return and the present value of cash flows are all examples:


Options are :

  • The method of analysis.
  • None
  • Group Decision TechNonelogy.
  • expert review.
  • Earned Value Management.

Answer : The method of analysis.

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 1

Ā€ <A Ā€ <such as the range, cost, budgets, and the duration or size of the measure values, for example on the basis of the complexity of the size, weight, and position of the same parameters for the assessment or measurement of the current project is similar to previous item type description assessments?


Options are :

  • Three points
  • parameter
  • corresponding
  • From bottom to top
  • None

Answer : corresponding

What tools or techniques can make a lot of thought into groups for review and analysis?


Options are :

  • Brainstorming
  • Thoughts / mind map
  • None
  • Noneminal group technique
  • The affinity and

Answer : The affinity and

Process output management stakeholder participation are:


Options are :

  • Enterprise environmental factors
  • None
  • Change Request
  • Change Log
  • Stakeholder Management Plan

Answer : Change Request

PMI-100 Certified Associate Project Management Practice Exam Set 11

What tools or techniques to manage change requests and decisions arising?


Options are :

  • Change Log
  • expert review
  • Delphi
  • Change control tool
  • None

Answer : Change control tool

Risk response strategy, which together with the impact of the project team to move ownership of the threat of an answer, a third party is called:


Options are :

  • Ease
  • None
  • transfer
  • accept
  • avoid

Answer : transfer

Outside the organization to detect whether the project requires the acquisition of most products, services, or results to be met?


Options are :

  • Gain control
  • Gathering requirements
  • Purchasing Management Program
  • Cost management plan
  • None

Answer : Purchasing Management Program

PMI-RMP PMI Risk Management Professional Practice Test Set 6

If the bonus is only valid:


Options are :

  • None
  • It is given as long as the project is completed.
  • Something that is tangible.
  • In order to meet the needs of personal attention.
  • From the formal point of view, it is given in the discussion of project development.

Answer : In order to meet the needs of personal attention.

The condition, which is Nonet a project team, under the control or limit the direct impact of the project, to be kNonewn as:


Options are :

  • Background
  • None
  • Performance Reports
  • Organizational process assets
  • envirnmental factor

Answer : envirnmental factor

Examples of techNonelogy is that the group Ma King:


Options are :

  • most
  • Affinity to FIG.
  • Noneminal group technique
  • None
  • Multi-criteria decision analysis

Answer : most

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 5

Area where A Ā€ <A Ā€ <expertise in project development?


Options are :

  • Range of project management
  • Project Integration Management
  • None
  • Project Cost Management
  • Project Time Management

Answer : Project Integration Management

Perception tissue between adventure and risk aversion risk balance appears:


Options are :

  • appetite
  • attitude
  • None
  • Reply
  • tolerance

Answer : Reply

Who contribution collection needs to identify stakeholders who can provide the required information?


Options are :

  • Stakeholder Management Plan
  • None
  • Registration of interest groups
  • The project
  • Range management plan

Answer : Registration of interest groups

PMI PGMP Program Management Professional Practice Test Set 9

Reservations analysis is a tool, the use of techNonelogy?


Options are :

  • None
  • Identify risks
  • Risk Management
  • Risk Management Plan
  • Risk response plan

Answer : Risk Management

The ways in which roles and responsibilities, reporting relationships and personnel management are discussed and structured project description:


Options are :

  • By evaluators,
  • Human resource management plan.
  • Multi-criteria decision analysis.
  • Activity resource requirements.
  • None

Answer : Human resource management plan.

What tool or method allows a large number of ideas, which can be divided into groups for review and analysis?


Options are :

  • The nominal group technique
  • affinity diagram
  • Idea / mind mapping
  • None
  • brain attack

Answer : affinity diagram

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 5

Yield control plan process quality:


Options are :

  • None
  • Plan for the improvement of processes,
  • quality control measures.
  • Project Management Plan.
  • Work performance information,

Answer : Plan for the improvement of processes,

Which area of ??expertise involves the identification of individuals, groups or organizations that may be affected by or affect the project?


Options are :

  • Project Scope Management
  • Project Human Resource Management
  • None
  • Project Management with stakeholders
  • Project Risk Management

Answer : Project Management with stakeholders

Analysis Reserve is a tool and technique used in each process?


Options are :

  • risk control
  • Risk Management Plan
  • None
  • Replies Risk Plan
  • Risk Identification

Answer : risk control

PMI-RMP PMI Risk Management Professional Practice Test Set 2

Contribution to the procurement management plan process is to:


Options are :

  • Market research.
  • Criteria for selecting a source.
  • Records management.
  • Sign stakeholders.
  • None

Answer : Sign stakeholders.

The way will be considered and structured roles and responsibilities, reporting relationships, as well as the management of human resources within the project is described in:


Options are :

  • Multi-criteria decision analysis.
  • None
  • human resources management plan.
  • personnel assessment tools,
  • resource requirements.

Answer : human resources management plan.

Ability to influence the maximum, during which stage of the project?


Options are :

  • average
  • None
  • soon
  • completion
  • late

Answer : soon

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 12

The classes are created and the project resources are released in the course of which band?


Options are :

  • conduct
  • planning
  • initiation
  • None
  • closing

Answer : closing

What tool or method used to manage change requests, and as a result of the decision?


Options are :

  • Change Management Tools
  • change history
  • None
  • Expert review
  • Delphi technique

Answer : Change Management Tools

Strengths and Weaknesses, Opportunities and Threats (SWOT) is a tool or method used in other processes?


Options are :

  • To make a qualitative risk assessment
  • Risk Identification
  • None
  • Perform Quantitative Risk Analysis
  • risk control

Answer : Risk Identification

PMI-RMP PMI Risk Management Professional Practice Test Set 8

planned work contained in the starting components work structure (WBS), also known as:


Options are :

  • None
  • The results are adopted.
  • Work packages.
  • The volume of the baseline.
  • WBS dictionary.

Answer : Work packages.

recovery period, the return on investment, internal rate of return, discounted cash flow, net present value are examples:


Options are :

  • Group decision-making methods.
  • Earned Value Management.
  • expert.
  • None
  • Analytical methods.

Answer : Analytical methods.

What areas are developed skills of the Project Charter?


Options are :

  • Project Time Management
  • Project Scope Management
  • Project Cost Management
  • Project Management Integration
  • None

Answer : Project Management Integration

PMI-100 Certified Associate Project Management Practice Exam Set 11

perceived balance between risk organization and risk aversion are reflected in danger:


Options are :

  • Tolerance
  • answers
  • Appetite
  • attitude
  • None

Answer : answers

Which element is a formal proposal to amend any document, the final result or the base?


Options are :

  • baseline shift
  • Risk assessment of urgency
  • documentation requirements
  • Modify request
  • None

Answer : Modify request

What is the process if the project identifies the needs can be met through the purchase of products, services, or results outside the organization?


Options are :

  • test purchases
  • Procurement Management Plan
  • requirements gathering
  • Cost Management Plan
  • None

Answer : Procurement Management Plan

PMI-RMP PMI Risk Management Professional Practice Test Set 3

Updates Organizational process assets, such as the purchase of acceptances delivered files, and lessons learned documents are typical outputs that process?


Options are :

  • Close purchases
  • None
  • supply
  • Closing a project or phase
  • test purchases

Answer : Close purchases

What process includes funds for the development of approximation needed to complete the project activities?


Options are :

  • cost control
  • estimated costs
  • The determination of budget
  • None
  • Cost Management Plan

Answer : estimated costs

What is the process of numerical analysis of the risks identified effects on the general objectives of the project?


Options are :

  • None
  • Replies Risk Plan
  • Perform Quantitative Risk Analysis
  • To make a qualitative risk assessment
  • Risk Management Plan

Answer : Perform Quantitative Risk Analysis

PMI Risk Management Professional Certification Practice Exam Set 9

Inputs to the management plan planning process include:


Options are :

  • The enterprise environmental factors and graphics tools.
  • Attributes of the activities and resource calendars.
  • Organizational Process Assets and the project charter,
  • Temporary tables and Pareto charts.
  • None

Answer : Organizational Process Assets and the project charter,

What are the main instrument quality is most useful when collecting data attributes during defect inspection?


Options are :

  • None
  • chart Ishikavva
  • checklists
  • verification sheets
  • Pareto diagram

Answer : verification sheets

That metric earned value management (EVM) is a measure of the efficiency of budgetary resources costs expressed as a ratio between the obtained value (EV) to actual cost (AC) and is considered a critical metric EVM?


Options are :

  • The difference at the completion (VAC)
  • Budget for completion (BAC)
  • None
  • cost performance index (CPI)
  • The cost difference (CV)

Answer : cost performance index (CPI)

PMI-SP Scheduling Professional Certification Practice Test Set 6

The regression line is used to evaluate:


Options are :

  • None
  • The upper and lower specification limits on the control card.
  • central tendency, dispersion and shape of the statistical distribution.
  • How to change the independent variable affect the value of the dependent variable.
  • If the process is stable or has predictable performance.

Answer : How to change the independent variable affect the value of the dependent variable.

Example Group Technology Solutions-ma king:


Options are :

  • affinity graph.
  • most
  • The nominal group technique
  • None
  • Multi-criteria decision analysis

Answer : most

The project manager should document the escalation path for project risks Unauthorized:


Options are :

  • risk magazine
  • Sign stakeholders
  • Plan communications management
  • Transmission rates management plan
  • None

Answer : Plan communications management

PMI-100 Certify Associate Project Management Practice Exam Set 5

Which process includes identifying, preparing and coordinating all subsidiary plans and integrate them into a comprehensive plan?


Options are :

  • Management and control of the Work project
  • Monitor and Control Project Work
  • None
  • Plan Quality Management
  • Develop Project Management Plan

Answer : Develop Project Management Plan

The main advantage of the communication control process is that it allows you to:


Options are :

  • The project cost will be reduced.
  • efficient and effective flow of communication.
  • Better use of communication methods.
  • Better use of communication technologies.
  • None

Answer : efficient and effective flow of communication.

Prizes can only be effective if:


Options are :

  • Something that is tangible.
  • None
  • Meeting the needs of individual value.
  • Formally, this during the evaluation of the project results.
  • Since immediately after the completion of the project.

Answer : Meeting the needs of individual value.

PMI-SP Scheduling Professional Certification Practical Exam Set 10

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions