Which of the following processes are part of the project integration management area of ??expertise?


Options are :

  • To develop a project plan, define scope, assess the cost
  • None
  • Develop project management plan, Collect Requirements, Create WBS
  • To develop a project plan, direct and manage project implementation, Close Project or Phase
  • Develop a Project Manager to plan, monitor, Scope, develop a schedule

Answer : To develop a project plan, direct and manage project implementation, Close Project or Phase

Which is expected to use technology as a basis for the actual cost of previous similar projects assessment of the cost of the current project?


Options are :

  • parametric
  • corresponding
  • None
  • From down to up
  • From top to bottom

Answer : parametric

Where the companies environmental factors are taken into account in the estimate costs?


Options are :

  • Commercial information and corporate structure
  • Existing human resources and market conditions
  • Company structure and market conditions
  • Market conditions and the published commercial information
  • None

Answer : Market conditions and the published commercial information

Process Group which typically consumes the bulk of the project budget?


Options are :

  • Design
  • Monitoring and control of
  • commencement of
  • None
  • showing

Answer : showing

PMI-SP Scheduling Professional Certification Practice Test Set 8

What is the total float the critical path?


Options are :

  • Can be any
  • None
  • Zero or negative,
  • Depends on the calendar
  • Zero or positive

Answer : Zero or negative,

What tool or technique Quality Plan involves comparing the actual or planned practices of other projects to generate suggestions for improvement and provide the basis on which to measure the results?


Options are :

  • benchmarking
  • None
  • Measuring the performance analysis
  • quality audits
  • histogram

Answer : benchmarking

The organization, which is projectized organizational structure, which manages the project budget?


Options are :

  • None
  • functional Director
  • Project Management Office
  • Project manager
  • Head of Programming

Answer : Project manager

Which type of the assessment can provide greater accuracy, depending on the sophistication and in-built data model?


Options are :

  • corresponding
  • None
  • The three-point
  • parametric
  • From down to up

Answer : parametric

Perform Quality control takes place:


Options are :

  • Applying the Monte Carlo sampling, Pareto analysis and benchmarking techniques in order according to the quality requirements.
  • Ensure that the entire project team is adequately trained in quality control processes.
  • Monitoring and recording the results of carrying out quality activities to assess performance and recommend necessary changes.
  • Identification of quality standards that are relevant to the project and are determined to satisfy them.
  • None

Answer : Monitoring and recording the results of carrying out quality activities to assess performance and recommend necessary changes.

Scope management plan is a subsidiary of a project document?


Options are :

  • The resource management plan
  • The project management plan
  • None
  • Schedule management plan
  • Quality management plan

Answer : The project management plan

PMI-RMP PMI Risk Management Professional Practice Test Set 1

Which tool is designed to develop the technical details within the framework of the project management plan?


Options are :

  • None
  • Project Management Information System (PMI)
  • expert assessment
  • Project Management Method
  • Project selection methods

Answer : expert assessment

Every process uses the probability of occurrence and impact on the project objectives to evaluate the priority of identified risks?


Options are :

  • The risk management plan
  • Perform Qualitative Risk Analysis
  • None
  • quantitative risk analysis
  • identify risks

Answer : Perform Qualitative Risk Analysis

Every method of documenting the business needs of the project and a new product, service, or other result that is intended to satisfy those requirements?


Options are :

  • Collect requirements
  • To develop a project plan
  • Direct and manage project execution
  • Develop Project Management Plan
  • None

Answer : To develop a project plan

What type of analysis is used to plan the quality of the process?


Options are :

  • None
  • Checklist
  • assumption
  • Schedule
  • The cost-benefit

Answer : The cost-benefit

Which of the following consists of a detailed scope of the project and its associatedWBSand WBS dictionary?


Options are :

  • Scope Management Plan
  • The extent of baseline
  • None
  • The definition of product
  • The scope of the plan

Answer : The extent of baseline

Each project management process group Collect Requirements Define Actions Action Sequence, Perform Qualitative Risk Analysis, Quantitative Risk Analysis and Run?


Options are :

  • Closure
  • Design
  • commencement of
  • None
  • Monitoring and control of

Answer : Design

PMPĀ® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 13

Which of the following is an attempt to environmental factor that can affect the project outline to the Charter process?


Options are :

  • historical information
  • Organizational standard processes
  • None
  • Marketplace conditions
  • Templates

Answer : Marketplace conditions

What is the name of a graphic display of project team members and their reporting relationships?


Options are :

  • The project organization chart
  • The role of addictions chart
  • None
  • Reporting flowchart
  • The project team structure diagram

Answer : The project organization chart

Which of the following investigates the likelihood that each specific risk will happen?


Options are :

  • Assessment of risk probability and impact
  • risk register
  • Risk assessment of urgency
  • None
  • audits

Answer : Assessment of risk probability and impact

Which of the following risk strategies related to the allocation of the ownership of a positive risk to a third party?


Options are :

  • Transfer
  • mitigate
  • Avoid
  • None
  • Ice

Answer : Ice

What kind of planning where the work can be carried out in the near future is planned in detail, when the work is planned in the future at a higher level?


Options are :

  • dependency determination
  • Rolling wave planning
  • None
  • Ready-start design
  • Short-term planning

Answer : Rolling wave planning

Which of the following belongs in order to guarantee the right to information for project stakeholders on time?


Options are :

  • plan Communications
  • None
  • share information
  • performance reporting
  • The project status reports

Answer : share information

PMI PGMP Program Management Professional Practice Test Set 1

Which is a tool or technique used to define scope?


Options are :

  • project assumptions
  • None
  • The models, forms, and standards
  • product analysis
  • change requests

Answer : product analysis

When the project is finished?


Options are :

  • Once the project objectives have been achieved
  • After that experience gained is documented in the contract closure
  • None
  • After the verbal approval of the client or sponsor
  • Once the resources have been released

Answer : Once the project objectives have been achieved

project manager for the operation to take to make the project management plan is effective and current?


Options are :

  • Fill out the quality control checklist.
  • To carry out regular project development discussions.
  • Follow the ISO 9000 quality standards.
  • Identify quality requirements of the project.
  • None

Answer : To carry out regular project development discussions.

Feed Create WBS process is:


Options are :

  • None
  • The project plan.
  • traceability matrix.
  • The project scope.
  • Register stakeholders.

Answer : The project scope.

What type of analysis systemically collect and analyze qualitative and quantitative information, which interests must be taken into account throughout the project?


Options are :

  • stakeholders
  • research
  • Product
  • The cost-benefit
  • None

Answer : stakeholders

What is the difference between the critical path and the critical chain?


Options are :

  • quality audits
  • scope changes
  • Risk Analysis
  • resource limitations
  • None

Answer : resource limitations

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 5

What is the number of stakeholders, if a project has 28 potential communication channels?


Options are :

  • 14
  • 7
  • 8
  • None
  • 16

Answer : 8

Which, together with the project manager, is intended to guide the performance of the planned project activities and manage the various technical and organizational interfaces that exist in the project?


Options are :

  • project Management Team
  • Risk owners and stakeholders
  • The customer and operational managers
  • Sponsors and stakeholders
  • None

Answer : project Management Team