Legitimate power is ____________.


Options are :

  • Power earned is based on the person's technical knowledge, skill or expertise in a certain area
  • The power bestowed as the personal qualities and abilities of the person
  • None
  • Power comes from the official position of the person in the organization (Correct)
  • The power to share information as one sees fit

Answer : Power comes from the official position of the person in the organization

Which of the following is not a tool or technique that is used in the risk quantification process?


Options are :

  • contingency planning (Correct)
  • The statistical sums
  • The expected monetary value
  • None
  • Decision Trees

Answer : contingency planning

The histogram ordered frequency indicating how many results were obtained in September of each identified called ______________.


Options are :

  • Pareto diagram (Correct)
  • None
  • Jura Histogram
  • The statistical histogram
  • fishbone diagram

Answer : Pareto diagram

PMI-RMP PMI Risk Management Professional Practice Test Set 9

The tools and techniques used in the process are the Quality Plan which of the following:


Options are :

  • control Cards
  • All the above (Correct)
  • The benefit / cost analysis
  • at the expense of quality
  • None

Answer : All the above

Quality Team Project consists of several groups. Which of the following participants in a project plays an important role in the quality of the function?


Options are :

  • customer (Correct)
  • The project team
  • Vendors and suppliers
  • None
  • Project manager

Answer : customer

The tool, which analyzes the inputs to the process to identify the causes of error is called ______________________.


Options are :

  • All the above (Correct)
  • Ishikawa diagram
  • fishbone diagram
  • Cause and effect diagram
  • None

Answer : All the above

PMI-SP Scheduling Professional Certification Practice Test Set 3

Which of the following types of contract the seller's profit is limited?


Options are :

  • The company's fixed price agreement
  • Flatrate-fee contract
  • None
  • Cost plus percentage of cost contract
  • The cost-plus-fixed-fee contract (Correct)

Answer : The cost-plus-fixed-fee contract

at the expense of quality includes ___________.


Options are :

  • Acquired anomalies resulting from the work requirements
  • All the above (Correct)
  • Acquired in the work to build a product or service that meets the requirements
  • Training programs
  • None

Answer : All the above

Project management processes can be organized as follows:


Options are :

  • The initiation, design, contracting, execution and administration
  • None
  • The initiation, planning, execution, control and closure of (Correct)
  • The design, development, testing, and implementing
  • The initiation, planning, design, execution, monitoring and implementation

Answer : The initiation, planning, execution, control and closure of

PMI Certification Mock Questions

Once you identify the risks should be carried out?


Options are :

  • During the development phase
  • None
  • Identify risks should be carried out regularly throughout the project (Correct)
  • During the implementation phase,
  • During the concept phase

Answer : Identify risks should be carried out regularly throughout the project

Once you identify the risks should be carried out?


Options are :

  • During the development phase
  • None
  • During the concept phase
  • On a regular basis throughout the project (Correct)
  • During the implementation phase,

Answer : On a regular basis throughout the project

The control task schedules to use human resource management more efficient resource called _______.


Options are :

  • None
  • Tracking
  • Loading
  • crashes
  • Leveling (Correct)

Answer : Leveling

PMI-SP Scheduling Professional Certification Practical Exam Set 6

Coercion as a means to manage conflicts ______________.


Options are :

  • A loss situation
  • To emphasize areas of agreement while avoiding disagreement
  • Both A and C
  • None
  • Exerts a specific opinion on the potential expense of another party (Correct)

Answer : Exerts a specific opinion on the potential expense of another party

Which of the following are the inputs, which include estimates Activity Resources?


Options are :

  • None
  • All of the above production process are estimates Activity Resources (Correct)
  • resource calendar
  • activity is determined
  • activity list

Answer : All of the above production process are estimates Activity Resources

What are the four parts of the communication model?


Options are :

  • None
  • Communication, understanding the sending, receiving, and
  • Transmission, reception, decoding and understanding
  • Sender, Message, Medium and receiver (Correct)
  • Communicator, Message, the receiver and decoder

Answer : Sender, Message, Medium and receiver

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 6

Which of the following is not a process Project Communications Management?


Options are :

  • administrative closure
  • Conflict resolution (Correct)
  • None
  • Performance report
  • share information

Answer : Conflict resolution

Management reserves are used to deal with which type of risk?


Options are :

  • unknown unknown
  • business risks
  • unknown unknown (Correct)
  • None
  • pure risks

Answer : unknown unknown

Root cause analysis related to ________.


Options are :

  • All the above
  • Process Analysis (Correct)
  • None
  • performance measurements
  • quality audits

Answer : Process Analysis

PMI-100 Certify Associate Project Management Practice Exam Set 4

You are the project manager for the organization. Considering recommending the project, which will cost $ 280,000; Investments are expected during the quarter of $ 10 thousand dollars the first two years and then $ 25,000 per quarter after. What is the payback period?


Options are :

  • 40 months
  • 50 months
  • None
  • 36 months
  • 48 months (Correct)

Answer : 48 months

80% of the problems occur in 20% of the work is the concept of _________.


Options are :

  • Juran
  • Pareto (Correct)
  • None
  • Edward Deming
  • Philip Crosby

Answer : Pareto

Every process monitoring, measuring, and taking corrective action?


Options are :

  • closing processes
  • Controlling processes (Correct)
  • Executing processes
  • planning processes
  • None

Answer : Controlling processes

PMPĀ® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 13

Life cycle costing ________________.


Options are :

  • Including only the development or acquisition cost of the product or service
  • Does not take into account the effect of decisions on the cost of the project by using the resulting product,
  • Both B and C
  • None
  • Including the acquisition, use and disposal costs when assessing the various options (Correct)

Answer : Including the acquisition, use and disposal costs when assessing the various options

A structured tool, usually in industry or in specific activities, to verify that a set of required steps are completed, is called the __________


Options are :

  • checklist (Correct)
  • None
  • Paieto chart
  • quality policy
  • trend Analysis

Answer : checklist

Degradation is ___________.


Options are :

  • Dividing the project into logical divisions of the organization performing the work aligned business units
  • Defines a general description of the product more separate definitions of the individual components
  • None
  • What happens when changes in the scope of the project is to ignore
  • Dividing major project deliverables into smaller, more manageable components (Correct)

Answer : Dividing major project deliverables into smaller, more manageable components

PMI-ACP Agile Certified Practitioner Certified Practice Exam Set 4

Conflict resolution techniques that can be used in the project is ______________.


Options are :

  • Withdrawal, without compromising the control and forcing
  • Control to force the withdrawal of the equalizer
  • None
  • Handicap, encounter, forces, and the withdrawal of (Correct)
  • Towards, compromising, smoothing and directing the

Answer : Handicap, encounter, forces, and the withdrawal of

Deflection or the transfer of risk to the other belongs to which of the following risk response categories?


Options are :

  • Adoption
  • Transfer (Correct)
  • mitigate
  • None
  • Avoidance

Answer : Transfer

Legitimate power is ____________.


Options are :

  • None
  • The power to share information as one sees fit
  • Power comes from the official position of the person in the organization (Correct)
  • Power earned is based on the person's technical knowledge, skill or expertise in a certain area
  • The power bestowed as the personal qualities and abilities of the person

Answer : Power comes from the official position of the person in the organization

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 7

Which of the following is a method for quantifying qualitative data in order to minimize the personal data in the source selection bias?


Options are :

  • None
  • None of the above
  • selection system
  • a weighting system (Correct)
  • screening system

Answer : a weighting system

The control task schedules to use human resource management more efficient resource called _______.


Options are :

  • Tracking
  • None
  • Loading
  • crashes
  • Leveling (Correct)

Answer : Leveling

Projects are typically authorized as a result of any of the following except:


Options are :

  • technological progress
  • None
  • Successful RFP pricing (Correct)
  • regulatory requirement
  • market demand

Answer : Successful RFP pricing