PMI-002 Certify Associate Project Management Practice Exam Set 6

Risk response, which involves removing the threat is called


Options are :

  • Avoidance
  • None
  • Transfer
  • deviation
  • mitigation

Answer : Avoidance

When the risk should be avoided?


Options are :

  • The risk event is unacceptable - usually one of the very high probability and high impact.
  • The risk can be transferred by purchasing insurance.
  • The risk of an event can never be avoided.
  • The risk event is a low probability and low impact.
  • None

Answer : The risk event is unacceptable - usually one of the very high probability and high impact.

Analog estimation ___________.


Options are :

  • Uses the actual cost of previous, similar project
  • None
  • A bottom-up assessment of the techniques.
  • It is synonymous with top-down assessment of the
  • Both B and C

Answer : Both B and C

PMI-SP Scheduling Professional Certification Practical Exam Set 6

The core planning processes are:


Options are :

  • Plan Quality Plan Communications and Risk Response Development
  • Collect Requirements, Sequence Actions and Communications Plan
  • Define scope, duration and Review Activity Set your budget
  • None
  • Collect Requirements Define Actions to estimate the cost, Quality Plan and Plan Risk Responses

Answer : Define scope, duration and Review Activity Set your budget

Parametric estimate the cost of the case:


Options are :

  • None
  • Using the rates and factors are based on historical experience to estimate the cost
  • Both A and B
  • Individual cost estimates for each work package
  • Using the actual cost of a similar project to estimate the total project cost

Answer : Using the rates and factors are based on historical experience to estimate the cost

Techniques for conducting the analysis of the product include:


Options are :

  • value engineering
  • Technical benefit analysis
  • None
  • Identifying alternatives
  • expert assessment

Answer : value engineering

PMI PGMP Program Management Professional Practice Test Set 3

All of the following are the outputs Performance Report EXCEPT _________.


Options are :

  • "S" curves, histograms, bar charts and tables
  • None
  • trend Analysis
  • change requests
  • earnings Reports

Answer : trend Analysis

Ideally, resource leveling should be limited to activities ________.


Options are :

  • None
  • A positive float
  • Witn zero float
  • On tne critical path
  • negative float

Answer : A positive float

Technical staff tend to be especially responsive to __________.


Options are :

  • referent power
  • functional effect
  • formal power
  • expert power
  • None

Answer : formal power

PMI Certification Practice Questions

The independence of two events where the occurrence of one does not involve the presence of the other is called _______.


Options are :

  • event phenomenon
  • statistical probability
  • None
  • The independence
  • independent of the probability of

Answer : The independence

Which of the following statements applies to compromise efforts to resolve conflicts is wrong?


Options are :

  • None
  • Neither party wins, but both sides will get some degree of satisfaction
  • A compromise is generally regarded as a loss situation
  • The final resolution is rarely achieved
  • Important aspects of the project can be blocked in order to achieve personal goals

Answer : The final resolution is rarely achieved

You are the project manger of the current project. You had your own business for several years, but not in the area where this project takes place. Project Management Plan is in place. The project has not exceeded the number of basic-level change thresholds. The customer is not satisfied with the status of the project. Which of the following is the best original action?


Options are :

  • Checks the customer's needs and expectations
  • Nothing
  • None
  • Prepare a corrective action plan
  • Performs the creation of a team spirit with all stakeholders

Answer : Checks the customer's needs and expectations

PMI-SP Scheduling Professional Certification Practice Test Set 6

The document or tool, which describes when and how staff resources are imported and exported out of the project called _______.


Options are :

  • Organizational Breakdown Structure (OBS)
  • Staffing management plan
  • Raci (RAM)
  • resource assignment Chart
  • None

Answer : Staffing management plan

The work that must be done to obtain a product of defined characteristics and functionality is called __________.


Options are :

  • The scope of Human Resources
  • None
  • The definition of product
  • The scope of the project
  • Project

Answer : The scope of the project

A contingency plan is ________.


Options are :

  • The reserve fund is used to allow for future situations that may be designed to only partially
  • None
  • All the above
  • Designed for the answer, which defines the measures to be taken if the identified risk event should occur
  • you can skip

Answer : Designed for the answer, which defines the measures to be taken if the identified risk event should occur

PMI-SP Scheduling Professional Certification Practical Exam Set 3

Which of the following are examples of indirect costs?


Options are :

  • Salaries of full-time project staff
  • Both a and c
  • overhead costs
  • None
  • Salaries of corporate executives

Answer : Both a and c

80% of the problems occur in 20% of the work is the concept of ___________.


Options are :

  • Philip Crosby
  • Juran
  • None
  • Pareto
  • Edward Deming

Answer : Pareto

One example is to reduce the risks:


Options are :

  • The reason is removed from the danger
  • Purchasing insurance
  • Early action to reduce the risks probably more to repair the damage after the risk has occurred.
  • None
  • You will develop a contingency plan to implement in the event that the risk of an event.

Answer : Early action to reduce the risks probably more to repair the damage after the risk has occurred.

PMI-SP Scheduling Professional Certification Practical Exam Set 1

Project Procurement Management includes all of the following EXCEPT:


Options are :

  • administration
  • call
  • stakeholder analysis
  • None
  • Design

Answer : stakeholder analysis

A cost management plan ______________.


Options are :

  • None
  • The subsidiary part of the project plan
  • Feed Cost Estimate process
  • Both the A and C
  • The plan describes how the cost variations are managed

Answer : The plan describes how the cost variations are managed

Which of the following functions does the project start-up appointment?


Options are :

  • Obtaining commitment
  • None
  • Introducing the stakeholders
  • Presenting the project cost
  • Identification of project goals

Answer : Presenting the project cost

PMP Certification Practice

Collect requirements include identification of options that can be carried out to the common technique


Options are :

  • Cost / benefit analysis
  • lateral thinking
  • None
  • constraints analysis
  • value engineering

Answer : lateral thinking

A is the correct answer. Trend analysis is a tool and technique used to monitor and manage these risks.


Options are :

  • technical inspection
  • None
  • The project plan
  • project reports
  • accounting

Answer : accounting

Which of the following statement is true about quality control?


Options are :

  • Taking steps to increase the efficiency and effectiveness of the project
  • Assessing the overall project performance on a regular basis
  • By identifying the quality standards are relevant to the project
  • Follow-up results of a particular project to determine if they meet the relevant quality standards
  • None

Answer : Follow-up results of a particular project to determine if they meet the relevant quality standards

PMP Certification

The project, the quality should generally be ________.


Options are :

  • Equal privilege of costs, but higher priority than schedule
  • A higher priority than cost and schedule
  • Equal privilege of cost and schedule
  • None
  • Equal privilege of schedule, but a higher priority than cost

Answer : Equal privilege of cost and schedule

Group brainstorming encourages all of the following, except ___________.


Options are :

  • None
  • uninhibited language
  • analysis of alternatives
  • Convergent thinking
  • team building

Answer : Convergent thinking

The ability product can be used for different purposes and in different capacities under various conditions to determine its __________.


Options are :

  • functionality
  • Flexibility
  • None
  • Availability
  • usability

Answer : Flexibility

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 8

What is not considered negative risks to the strategy of the following?


Options are :

  • None
  • Accept
  • Transfer
  • Avoid
  • ExPlot

Answer : ExPlot

Legitimate power is __________.


Options are :

  • Power is derived from the person's official status in the organization.
  • Power earned is based on the person's technical knowledge, skill or expertise in a particular area.
  • None
  • The power bestowed as the personal qualities and abilities of the person.
  • The power to share information as one can see.

Answer : Power is derived from the person's official status in the organization.

at the expense of quality includes ___________.


Options are :

  • None
  • Training programs
  • All the above
  • Acquired anomalies resulting from the work requirements
  • Acquired in the work to build a product or service that meets the requirements

Answer : All the above