The tool that combines the roles and responsibilities of the project to determine the project area is called ____________.


Options are :

  • Roles Assignment Matrix
  • None
  • Raci
  • Define scope Matrix
  • The scope and roles of Project Matrix

Answer : Raci

Which of the following is true about risk insurance?


Options are :

  • Pure risks associated with the potential for both profit and loss.
  • No opportunities associated with risk insurance only losses.
  • The risk may bend or transferred to another party with or insurance.
  • Botn A and c are correct.
  • None

Answer : Botn A and c are correct.

The concept that is easier and cheaper to do the job right the first time is called _______________.


Options are :

  • Continuous improvement
  • DTRTRTFT
  • The customer is the next person in the process
  • zero error
  • None

Answer : DTRTRTFT

PMI-RMP PMI Risk Management Professional Practice Test Set 9

Which of the following statements applies to compromise efforts to resolve conflicts is wrong?


Options are :

  • Neither party wins, but both sides will get some degree of satisfaction.
  • Important aspects of the project can be blocked in order to achieve personal goals.
  • A compromise is generally regarded as a loss situation.
  • None
  • The final resolution is seldom achieved.

Answer : The final resolution is seldom achieved.

The receiver filters messages based on all but the following:


Options are :

  • Distance
  • Semantics
  • None
  • Culture
  • Language

Answer : Distance

Which has the following inputs Source selection procedure?


Options are :

  • Both A and B
  • assessment criterion
  • organizational policy
  • the procurement documents
  • None

Answer : Both A and B

PMP Certification

Human resource adininistration has the primary responsibility for the_____________


Options are :

  • None
  • Executive Director
  • Project manager
  • Project Management Team
  • Human Resources Department

Answer : Human Resources Department

________ must be measured on a regular basis to identify the variance of the plan.


Options are :

  • None
  • Costs and Schedule
  • Project performance
  • the needs of stakeholders
  • schedule progress

Answer : Project performance

Mathematical models using linear, dynamic, integer, or algorithm models are considered _____________.


Options are :

  • Form an expert assessment
  • selection criteria for projects
  • None
  • Form of historical knowledge
  • Project selection methods

Answer : Project selection methods

PMI-SP Scheduling Professional Certification Practice Test Set 7

When the risk should be avoided?


Options are :

  • The risk of an event can never be avoided.
  • None
  • The risk event is a low probability and low impact.
  • The risk event is a low probability and low impact.
  • It can be transferred by purchasing insurance.

Answer : The risk event is a low probability and low impact.

CIP is ___________.


Options are :

  • The continuous, gradual change
  • None
  • Includes the stability of the quality of purpose and commitment as part of focu
  • continuous improvement
  • All the above

Answer : All the above

Which of the following technologies accounted for on the road to convergence, and in general, estimated duration of the project in more detail?


Options are :

  • PERT
  • The convergence path
  • schedule simulation
  • None
  • CPM

Answer : < the project is a large, complex project?


Options are :

  • None
  • A strong matrix organization
  • The project Co-ordinator
  • The project is an early
  • Direct participation in the Executive

Answer : A strong matrix organization

Which of the following is true about the project plan?


Options are :

  • The project plan should be published under the name of the project manager.
  • The project plan should be published under the title director of external project.
  • The project plan should be published under the name of the project manager.
  • None
  • The project plan should be published on the project sponsor's name

Answer : The project plan should be published under the title director of external project.

PMI-002 Certified Associate Project Management Practice Exam Set 1

Deflection or the transfer of risk to the other belongs to which of the following risk response categories?


Options are :

  • Avoidance
  • Adoption
  • mitigation
  • None
  • analysis

Answer : mitigation

You are the project manager of software development projects. You create a project schedule network diagram code development part of the project. This is an example of _________.


Options are :

  • Preference diagram of a method [PDM]
  • The arrow diagram of a method of [ADM]
  • fragment Network
  • The activity is the node [ALN]
  • None

Answer : fragment Network

What if scenario analysis is conducted as part of the process of __________.


Options are :

  • None
  • the control schedule
  • Develop a schedule
  • Define Action
  • The sequence Action

Answer : Develop a schedule

PMI-RMP PMI Risk Management Professional Practice Test Set 7

What process requires formal approval, and at the end of the project?


Options are :

  • by controlling the processes
  • planning processes
  • closing processes
  • Executing processes
  • None

Answer : closing processes

From the buyer's point of view, which of the following is true?


Options are :

  • Subcontractors are first examined in a solicitation process.
  • Acquisition planning, consideration should be given possibilities of subcontracting work.
  • None
  • The acquisition is not included in the design of the possibilities of subcontracting work because this is a responsibility to the contractor.
  • None of the above

Answer : Acquisition planning, consideration should be given possibilities of subcontracting work.

Under what circumstances it is better that the contractor subcontracts?


Options are :

  • Subcontractor to perform the work more cheaply than the contractor.
  • Both A and C
  • None
  • Subcontractor has special features technical and engineering skills that the contractor is not.
  • Work subcontracting represents almost all of the entire work effort.

Answer : Both A and C

PMI-RMP PMI Risk Management Professional Practice Test Set 9

Send or transmit information from one place to another is a process _______________.


Options are :

  • promotion
  • transmitting
  • concealment
  • networking
  • None

Answer : transmitting

Group brainstorming encourages all of the following except _________.


Options are :

  • team building
  • Convergent thinking
  • Q uninhibited language
  • None
  • analysis of alternatives

Answer : Convergent thinking

Which of the following is not entered in the organizational design?


Options are :

  • staffing needs
  • None
  • recruitment practices
  • project interfaces
  • constraints

Answer : recruitment practices

PMI-SP Scheduling Professional Certification Practical Exam Set 8

One document, which should always be used to help identify the risk is _____________________.


Options are :

  • Risk Analysis
  • risk quantification
  • Respond to risks Development
  • None
  • identify risks

Answer : identify risks

The extent of the end product measured on which of the following:


Options are :

  • product Specifications
  • WBS and WBS Dictionary
  • None
  • The project management plan
  • product management plan

Answer : WBS and WBS Dictionary

The independence of two events where the occurrence of one does not involve the presence of the other is called ________________.


Options are :

  • event phenomenon
  • None
  • statistical probability
  • independent of the probability of
  • The independence

Answer : The independence

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 1

A technique for solving a problem, in which the parties agree that a neutral third party to resolve the matter and make a decision called ____________.


Options are :

  • forcing the
  • counsel
  • handicap
  • None
  • arbitration

Answer : arbitration

A series of consecutive points of the same side of the mean called __________.


Options are :

  • Run
  • cycle
  • outliers
  • None
  • Trend

Answer : Run

What can be used to determine what work is included in each work package for each of the team members of the following?


Options are :

  • None
  • WBS dictionary
  • None of the choices are correct
  • The project scope
  • RBS

Answer : WBS dictionary