PMI-002 Certified Associate Project Management Practice Exam Set 8

Every feature to distinguish the network diagram Gant chart?


Options are :

  • The main objectives of
  • critical dates
  • few resources
  • critical dependencies
  • None

Answer : critical dependencies

The project schedule may be represented in many different forms. All of the following are valid formats for the project schedule EXCEPT:


Options are :

  • Activity-on-node diagram
  • flow charts
  • The time-scaled schedule network diagram
  • The logic bar chart
  • None

Answer : flow charts

Which of the following methods is the technique used to predict project duration by analyzing which sequence of activities have the least scheduling flexibility?


Options are :

  • critical path
  • Grant Scheme
  • None
  • dependency diagram
  • PERT

Answer : critical path

PMI-ACP Agile Certified Practitioner Certified Practice Exam Set 5

To determine the impact of the change occurred, which of the following should be done?


Options are :

  • Check the earned value
  • Evaluate communication policy.
  • Re-evaluate the work breakdown structure.
  • None
  • performance measurement

Answer : performance measurement

What are the five project management process groups. Choose OK?


Options are :

  • The initiation, execution planning, monitoring and controlling, and closing
  • The initiation, planning, monitoring and controlling, executing and closing
  • The initiation, planning, monitoring and controlling, executing and closing
  • The initiation, monitoring and control, planning, executing, and closing
  • None

Answer : The initiation, planning, monitoring and controlling, executing and closing

Project management is an affordable approach to management, except for the following:


Options are :

  • Time limited performances.
  • Unique activities.
  • Cross-cutting tasks.
  • The product in a production environment.
  • None

Answer : The product in a production environment.

Reply risk of an event that has not been determined in advance is referred to as the occurrence of:


Options are :

  • Workaround to answer.
  • The emergency plan response.
  • Risk mitigation measures the response.
  • None
  • Corrective action response.

Answer : Workaround to answer.

The development of alternative activity of the sequences is an example:


Options are :

  • risk aversion.
  • rework
  • Contingency planning.
  • None
  • Wave of the polling stations.

Answer : Contingency planning.

Customer Service VP is concerned about the project in which you are involved. His special concern is that if the project is implemented as planned, he will have to buy more equipment for his staff in customer service. The cost is significant and is not taken into account in the project budget. The project sponsor emphasizes that the project must go forward as originally planned, or the customer suffers. Which of the following is true?


Options are :

  • The conflict should be resolved in favor of the customer.
  • None
  • The conflict should be resolved in favor of VP of customer service.
  • Nothing
  • The conflict should be resolved in favor of the project sponsor.

Answer : The conflict should be resolved in favor of the customer.

PMI-RMP PMI Risk Management Professional Practice Test Set 1

What is the key difference between the closing of the agreement and the administrative closing?


Options are :

  • Administrative closure includes procurement audits.
  • None
  • The agreement to formalize the closing end of the project.
  • The agreement includes a close inspection of the product.
  • The agreement includes a close update records in the final results.

Answer : The agreement includes a close inspection of the product.

As project manager, you know that the most important action to ensure the satisfaction of customers and stakeholders is which of the following?


Options are :

  • Documentation and meet performance measurements
  • None
  • Documentation and which fulfill the
  • Reporting project status regularly and on time
  • Changes in financial reporting and updating the project plan and other project documents if necessary

Answer : Documentation and which fulfill the

What is one of the advantages of the operating organization?


Options are :

  • The organization focuses on projects.
  • All employees report to two or more managers
  • All employees report to one manager and has a clear chain of command.
  • None
  • The teams are co-located.

Answer : All employees report to one manager and has a clear chain of command.

Ishikawa diagrams are used with the following processes?


Options are :

  • Create WBS
  • None
  • The risk management plan
  • Develop a schedule
  • Perform quality control

Answer : Perform quality control

What is required scope of supervision of the following?


Options are :

  • None
  • Risk mitigation measures
  • The cost-benefit analysis
  • to review the scope of the
  • charter update

Answer : to review the scope of the

Which creates a document in the application of experience?


Options are :

  • stakeholders
  • Customers
  • None
  • The project sponsor
  • The project team

Answer : The project team

PMI-002 Certified Associate Project Management Practice Exam Set 4

Which of the following are not essential for the project excluded?


Options are :

  • Nothing
  • None
  • Documenting the extent of the thesis
  • documenting lessons
  • Documenting the formal approval of the product.

Answer : Documenting the extent of the thesis

Which of the following is required to develop a detailed cost estimate of the project?


Options are :

  • cost plan
  • None
  • project sign
  • treatment plan
  • resource requirements

Answer : resource requirements

Sales VP visitor approaches you can change the logon user name included in the company's website at least eight characters. this is considered


Options are :

  • project
  • In the running operations
  • Starting the project
  • implementation of the project
  • None

Answer : In the running operations

Machine Catalog


Options are :

  • Machine Catalog
  • Machine Catalog
  • Machine Catalog
  • Machine Catalog
  • Machine Catalog

Answer : Machine Catalog

Your selection Committee will discuss two projects. A project has a payback period 20 months. Project B is for $ 150,000 with the expected cash flows of $ 50,000 after the first year and $ 25,000 per quarter. Which project should you recommend?


Options are :

  • Either the Project A or Project B, because the payback periods are equal
  • None
  • The project A, project B as a payback period of 24 months
  • The project A, project B as the repayment period is 20 months
  • The project A, project B as the repayment period is 21 months

Answer : The project A, project B as a payback period of 24 months

The primary function of the change of the control board has:


Options are :

  • None
  • Nothing
  • At the request of the impact of change.
  • Question change requests.
  • Identify new areas of project work.

Answer : At the request of the impact of change.

PMI PGMP Program Management Professional Practice Test Set 6

The process to change the clause in the agreement is the _______ of the project change control system.


Options are :

  • integrated
  • are not related
  • Input
  • None
  • Same as

Answer : integrated

Random variation of the process, in terms of standard deviation can be directly reduced to:


Options are :

  • increasing the number of quality inspectors.
  • By studying the scattering patterns.
  • Identification of variance models.
  • None
  • Improves overall production system.

Answer : Improves overall production system.

Mathematical models using linear, dynamic, integer, or algorithm models are considered


Options are :

  • Form an expert assessment
  • Project selection methods
  • Form of historical knowledge
  • None
  • selection criteria for projects

Answer : Project selection methods

Resource leveling is usually:


Options are :

  • Increase the total cost of the project.
  • None
  • Hurl the end date of the project.
  • We need fewer resources
  • Require more resources.

Answer : Hurl the end date of the project.

You are the project manager has many years of experience in project management. You have just approved the first project in a foreign country. You've been in the country for a week or two, and experiencing some disorientation. This is known which of the following?


Options are :

  • diversity shock
  • collocation
  • None
  • culture shock
  • Same as

Answer : culture shock

Fast tracking requires:


Options are :

  • By developing workarounds for the above problems.
  • The increase project risk.
  • None
  • Getting people to work longer overtime.
  • The meeting schedule targets by increasing resources.

Answer : The increase project risk.

PMI-100 Certified Associate in Project Management Test Set 2

Which of the following schedule incorporates a form of risk assessment techniques?


Options are :

  • Pert (PERT)
  • The critical path (CPM)
  • Arrow diagram of a method (ADM)
  • Preference diagram of a method (PDM)
  • None

Answer : Pert (PERT)

Work division:


Options are :

  • None of the above
  • Required as part of the project plan
  • None
  • Is set and does not change throughout the project
  • Is used to break down the project size chunks

Answer : Is used to break down the project size chunks

Change requests should be ______?


Options are :

  • Nothing
  • Interestingly
  • Formal
  • None
  • Short

Answer : Formal

Comment / Suggestion Section