PMI-002 Certified Associate Project Management Practice Exam Set 15

You are the project manager Tech Days seminar Homes. The new project is to head home the opening Seminar Days Mountainview, CA. Estimated duration of the project plan activities, to plan the project schedule, and monitoring and control of deviations from the schedule. Every project management expertise you are working on?


Options are :

  • Project Integration Management
  • Project quality management
  • None
  • The scope of the project management
  • Project Time Management (Correct)

Answer : Project Time Management

According to the PMBOK Guide, the project report work (SOW) should include or reference all of the following except the part?


Options are :

  • None
  • The strategic plan, the definition of the product description, influenced by interest groups, and companies needed
  • The purpose of the project, the business model, stakeholder influences, the definition of the product description
  • Requirements, business needs, the expectations of stakeholders
  • Business needs, the strategic plan, the definition of the product description (Correct)

Answer : Business needs, the strategic plan, the definition of the product description

PMI-RMP PMI Risk Management Professional Practice Test Set 4

The project scope management plan should document the extent of the Control System


Options are :

  • the end of the project phase. (Correct)
  • Upon delivery.
  • None
  • Performance graduation.
  • Product ready.

Answer : the end of the project phase.

Developing an integrated project takes place:


Options are :

  • Throughout the project. (Correct)
  • Nothing
  • Design.
  • during initiation.
  • None

Answer : Throughout the project.

Control costs are included in all of the following EXCEPT:


Options are :

  • Follow-up money.
  • None
  • Recording the appropriate modifications to the basic level of expenses.
  • To inform stakeholders of changes.
  • Preparing cost estimates. (Correct)

Answer : Preparing cost estimates.

The project scope statements during the evolving scope:


Options are :

  • confirmation
  • commencement of
  • Definition
  • Design (Correct)
  • None

Answer : Design

The communication between the project manager and project team members should take place:


Options are :

  • Through the formal chain of comman
  • Approved documented forms.
  • None
  • Via a daily situation report.
  • By written and oral communication. (Correct)

Answer : By written and oral communication.

How many channels of communication needed for the project, there are five individual participants?


Options are :

  • 10 (Correct)
  • 5
  • None
  • 12
  • 4

Answer : 10

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 5

You are the project manager and is working to gather requirements and evaluate the project. Which process group are you?


Options are :

  • Monitoring and control of
  • Design (Correct)
  • showing
  • commencement of
  • None

Answer : Design

After the production, the probability of results in the project cost estimate, which is a 20% probability to be exceeded is about one standard deviation:


Options are :

  • Below average.
  • below the median.
  • Just above the median.
  • None
  • above the average. (Correct)

Answer : above the average.

Activity duration estimates include all of the following except:


Options are :

  • Details previous experience.
  • The project team information.
  • Time studies. (Correct)
  • None
  • The duration of the commercial databases.

Answer : Time studies.

You are the project manager for the project. After the scope of the change requested by the customer acceptance of the design is the potential impact on several parts of the project. What are you doing?


Options are :

  • To convince the customer to postpone the change.
  • To make the change, if it is critical, regardless of its costs and effects, as well as the form of management changes in hog
  • Nothing
  • None
  • Assess their effects on cost and schedule and approval before proceeding. (Correct)

Answer : Assess their effects on cost and schedule and approval before proceeding.

Once the project is completed in accordance with the agreement, which provides sowed


Options are :

  • Contractor
  • Project manager
  • Buyer (Correct)
  • None
  • the project sponsor

Answer : Buyer

Which of the following most accurately estimates correspond to the actual cost of the project?


Options are :

  • budget
  • None
  • From top to bottom
  • From down to up (Correct)
  • appropriations

Answer : From down to up

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 8

Estimate At Completion (EAC) is a regular assessment of:


Options are :

  • None
  • Resources project is projected to complain
  • The cost of work in progress.
  • The projected cost of the project. (Correct)
  • performed by the value of the work.

Answer : The projected cost of the project.

As project manager, you know that the most important action to ensure the satisfaction of customers and stakeholders is which of the following?


Options are :

  • Reporting project status regularly and on time
  • Documentation and which fulfill the (Correct)
  • Documentation and meet performance measurements
  • None
  • Changes in financial reporting and updating the project plan and other project documents if necessary

Answer : Documentation and which fulfill the

You are currently numerically analyze the impact of identified risks. Which of the following is the tools or techniques you can use in this process?


Options are :

  • None
  • sensitivity analysis
  • Modeling and Simulation
  • booking analysis (Correct)
  • The expected monetary value analysis

Answer : booking analysis

As CAPM, you need to follow the CAPM Code of Professional Conduct. This code refers to all of the following except which one?


Options are :

  • None
  • conflicts of interest disclosure
  • Adhering to the needs of stakeholders (Correct)
  • Comply with rules and standards in foreign countries
  • Reporting experience and CAPM status truthfully

Answer : Adhering to the needs of stakeholders

You are a project manager for the manufacturing company. You will notice a design error during the test production to install itself on the latest project. Which of the following is the most likely answer to this problem?


Options are :

  • Proceed to production, and leave the error.
  • Develop alternative solutions for the error. (Correct)
  • Proceed to production, but inform the customer of the problem.
  • None
  • Reduce the technical requirements so that the error is no longer valid.

Answer : Develop alternative solutions for the error.

The integrity of the project management field manages all of the following except:


Options are :

  • The following CAPM Code of Professional Conduct
  • Applying established project management processes
  • Adhering to ethical
  • None
  • Training to learn to manage relationships with different cultures (Correct)

Answer : Training to learn to manage relationships with different cultures

PMI-002 Certified Associate Project Management Practice Exam Set 13

You are a project manager for the organization. Management has asked you to help them choose which projects should be implemented. The project selection model, which of the following is the most important factor?


Options are :

  • None
  • Schedule
  • Type constraints
  • business needs (Correct)
  • budget

Answer : business needs

Every process monitoring, measuring, and taking corrective action?


Options are :

  • closing processes
  • None
  • Executing processes
  • Controlling processes (Correct)
  • planning processes

Answer : Controlling processes

You have been chosen project, where the goal is to create a new building. You are responsible for the demolition phase of this project, and advise the project manager responsible for this project. You have been hired contract and it will be published the end of the discharge phase. What kind of organizational structure you're working on?


Options are :

  • None
  • Projectized organization (Correct)
  • functional organization
  • Balanced matrix organization
  • Weak matrix organization

Answer : Projectized organization

The project is considered successful when


Options are :

  • None
  • Project meets or exceeds the expectations of stakeholders (Correct)
  • Nothing
  • the project sponsor announces the completion of the project
  • the product of the project is made

Answer : Project meets or exceeds the expectations of stakeholders

If the level of concordance more directly as a result of new processes, costs of the required follow-up is likely to be:


Options are :

  • Increase
  • To stay the same.
  • None
  • To be more predictable.
  • reduction (Correct)

Answer : reduction

Which of the following is true regarding IRR?


Options are :

  • None
  • IRR is a constrained optimization method.
  • IRR is the discount rate when the NPV is greater than zero.
  • IRR is the discount rate when NPV is zero. (Correct)
  • IRR assumes reinvestment at the cost of capital.

Answer : IRR is the discount rate when NPV is zero.

PMI-RMP PMI Risk Management Professional Practice Test Set 4

Which of the following describes a group of elated to schedule activities together in one summary level, displayed as a single activity reported to the summary level?


Options are :

  • None
  • work experience
  • control account
  • a hammock activity (Correct)
  • design package

Answer : a hammock activity

Maslow's vertex is called:


Options are :

  • Self-actualization. (Correct)
  • survival
  • safety
  • The physiological satisfaction.
  • None

Answer : Self-actualization.