Unique identifiers for each item in the WBS is often commonly known as:


Options are :

  • code of accounts
  • The element accounts
  • project tags
  • Work package code list
  • None

Answer : code of accounts

Which is not a technique Sequence operation?


Options are :

  • Rolling Wave Planning
  • The arrow diagram of a method of [ADM
  • None
  • mandatory dependencies
  • Preference diagram of a method [PDM]

Answer : Rolling Wave Planning

What is the lowest level of work breakdown structure?


Options are :

  • project task
  • sow
  • work package
  • None
  • nothing

Answer : work package

PMI-RMP PMI Risk Management Professional Practice Test Set 2

You are the project managers the company ABC. The project team members are finance and accounts. Team members report to the finance and account representatives, respectively, and you have limited control over them. What type of organization hierarchy does not follow the company ABC?


Options are :

  • Projectized organization
  • Nothing
  • functional organization
  • None
  • matrix

Answer : functional organization

Name the ethical you need to follow than the CAPM.


Options are :

  • Project Management Professional Standards
  • Project Management Professional Code of Professional Conduct
  • Project Management Policy Ethics
  • Project Management Code of professional ethics and standards
  • None

Answer : Project Management Professional Code of Professional Conduct

Which of the following statements are true concerning the scope?


Options are :

  • Once written, the scope should never be a check
  • None
  • H provides a documented basis for making decisions on future projects and to develop a common understanding of project scope among the stakeholders.
  • Scope and statement of work are synonymous.
  • The project justification and objectives of the project are not included or referenced application.

Answer : H provides a documented basis for making decisions on future projects and to develop a common understanding of project scope among the stakeholders.

Collect the requirements for the process is


Options are :

  • Design project milestones
  • Institutionalized approach the acceptance of the project scope
  • The development plan with key stakeholders
  • To develop the basis for a written scope of its future decisions projects
  • None

Answer : To develop the basis for a written scope of its future decisions projects

Staffing requirements do not define:


Options are :

  • None
  • What types of skills are required
  • What kind of resource planning is needed
  • What kind of individuals or groups
  • What time frames

Answer : What kind of resource planning is needed

Project managers have the greatest authority on the type of organization?


Options are :

  • None
  • strong Matrix
  • Nothing
  • Balanced matrix organization
  • weak matrix organization

Answer : strong Matrix

PMI-SP Scheduling Professional Certification Practical Exam Set 8

The risk event is a description of what can happen, that _____ the project.


Options are :

  • damage
  • budget
  • None
  • manager
  • schedul

Answer : damage

Which of the following would be the appropriate WBS work package code to the fourth level is where the top level of the WBS code is 1.0?


Options are :

  • 1.2.3.4
  • b and c
  • None
  • 1.4
  • 1.1.1.1

Answer : b and c

Which of the following work items associated with the individual cost of:


Options are :

  • computerized
  • None
  • Square Foot
  • The bottom-up assessment of the
  • analog estimation

Answer : The bottom-up assessment of the

Three-point include_________ Reviews.


Options are :

  • Most likely,
  • None
  • Optimistic
  • Pessimistic
  • All

Answer : All

What is not included tools and techniques, which Organizational Planning?


Options are :

  • Staffing management plan
  • Templates
  • Human resource management practices
  • organizational
  • None

Answer : Staffing management plan

The work that must be done to obtain a product of defined characteristics and functions:


Options are :

  • project management
  • None
  • project verification
  • The scope of the project
  • The definition of product

Answer : The scope of the project

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 3

Technical associations and consultants of the project are two examples of __________?


Options are :

  • external Resources
  • None
  • expensive additions
  • expert assessment
  • scope of leaders

Answer : expert assessment

The fastest estimate the cost of the technology is:


Options are :

  • Square foot estimation
  • The computerized estimation
  • template estimation
  • None
  • analog estimation

Answer : The computerized estimation

Which method is not included in the Project Time Management Process?


Options are :

  • The sequence Action
  • None
  • Develop a timetable and schedule control
  • Work breakdown structure (WBS)
  • Define Action

Answer : Work breakdown structure (WBS)

__________ task is defined as the ratio of the duration of activities:


Options are :

  • Start a bootable
  • None of the above
  • Start finish
  • None
  • the end of the finalization of the

Answer : None of the above

Importance sequence diagram of a method (PDM) uses the following dependencies


Options are :

  • Start finish
  • end-start
  • the end of the finalization of the
  • None
  • Start a bootable

Answer : end-start

Which is not included in the General Management:


Options are :

  • Strategic planning
  • Develop a new product or service
  • Finance and Accounting
  • None
  • sales and marketing

Answer : Develop a new product or service

PMI-SP Scheduling Professional Certification Practice Test Set 1

Project Procurement Management includes:


Options are :

  • All the above
  • None
  • call
  • acquisition planning
  • an invitation design

Answer : All the above

Make a reservation method of analysis has not been spent __________.


Options are :

  • estimate of costs
  • determine your budget
  • control costs
  • None
  • Assess the duration of the action

Answer : control costs

Personnel management plan ___________, is formal or informal.


Options are :

  • Depending on the project
  • None
  • Depending on the size only
  • Depending management
  • Depending on the size and complexity of the project

Answer : Depending on the size and complexity of the project

If you are a project manager, and the change request has been denied, you should:


Options are :

  • Forget about
  • Record and save it.
  • None
  • Nothing
  • Pass on to the project team.

Answer : Record and save it.

Which of the following is not true about Analog to estimate costs?


Options are :

  • None
  • Useful in the early stages of the project
  • Used to reference objects are similar
  • Does not require much expertise as part of the estimator estimates are based on previous projects
  • Use the expert assessment

Answer : Does not require much expertise as part of the estimator estimates are based on previous projects

To ensure that project objectives are met by monitoring and measuring progress and taking corrective action if necessary.


Options are :

  • controlling the process
  • project charts
  • control logs
  • None
  • project control

Answer : controlling the process

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 8

Resource transfers is not critical to critical activities is an example of which of the following Project Scheduling:


Options are :

  • critical path
  • What if analysis
  • schedule Package
  • None
  • resource leveling

Answer : resource leveling

Product Description The project allows to create the details of acquisitions. Which of the following best describes the product description?


Options are :

  • Product description defines the requirements for contract work
  • Product description defines the contracted work
  • Product description defines the contracted work on the basis of the requirements of the customer's project
  • All the above
  • None

Answer : Product description defines the contracted work on the basis of the requirements of the customer's project

Which gives approval of the project?


Options are :

  • customer
  • None
  • Project manager
  • Team Lead
  • Sponsor

Answer : customer