PMI-002 Certification Project Management Practices Exam Set 8

When you are developing estimates of the project, you select a mathematical model to predict the estimate. What kind of assessment methods you use?


Options are :

  • Analogous estimating
  • Parameter Estimation
  • Top-down estimates
  • The bottom-up assessment
  • None

Answer : Parameter Estimation

FIG arrow method thereof using the following relationship [the ADM]


Options are :

  • Start - Star
  • Tidy
  • Start - complete
  • Ready to start
  • None

Answer : Ready to start

You are the project manager of the project. The project to install AC hotel room. You do this project with an estimated cost and time estimates are accurate customer, if the room to meet the equivalent (wood coating). This is an example below,?


Options are :

  • Hypothesis
  • budget
  • risk
  • None
  • constraint

Answer : Hypothesis

PMI-100 Certified Associate Project Management Practice Exam Set 1

Which describes how to manage variable costs?


Options are :

  • Chart of Accounts
  • Price
  • Cost management plan
  • None
  • Cost basis

Answer : Cost management plan

Change request can be caused by the following reasons:


Options are :

  • Errors or omissions defined range of products.
  • External events, such as changes in government regulation.
  • all of the above
  • None
  • The project defines the scope of errors or omissions.

Answer : all of the above

You are the project manager and the project is months into the implementation phase. One of the team members consisting of a number of factions. Its management to follow the best results?


Options are :

  • training
  • None
  • stand by-
  • control
  • delegation

Answer : training

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 2

Market conditions are part of ________.


Options are :

  • Organizational process assets
  • None
  • Cost factors
  • Project Management
  • envirnmental factor

Answer : envirnmental factor

If you are the project manager of the project, you need to enter the same number early as possible. The following, which is the best source of information for the project?


Options are :

  • RBS
  • WBS
  • history information
  • None
  • business plan

Answer : history information

How do you determine which amount must be used to perform project activities.


Options are :

  • None
  • Control costs
  • Determine your budget
  • Resource Planning
  • Cost Estimate

Answer : Resource Planning

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 1

Significant default on all network timing method is the duration of the action must be _____.


Options are :

  • Independent statistics
  • Related statistics
  • Divided by the variance
  • None
  • determine

Answer : Independent statistics

________ bound by the buyer and the seller.


Options are :

  • WBS
  • protocol
  • Appraisal
  • responsibility
  • None

Answer : protocol

Insurance is an example of __________.


Options are :

  • emergency plan
  • transfer
  • Ease
  • None
  • Approval

Answer : transfer

PMI-SP Scheduling Professional Practice Exam Set 7

Customer formally accepts the results of each stage of the project. This process is called ________.


Options are :

  • None
  • The scope of the review
  • Quality Insurance
  • Quality measurement
  • Quality control

Answer : The scope of the review

If an item 1.6 of the CPI, what can you tell?


Options are :

  • The project is running ahead of schedule.
  • The project will consume fewer resources than expected
  • None
  • The project will use less resources than expected
  • The project behind.

Answer : The project will consume fewer resources than expected

In an optimal organizational structure, the project manager:


Options are :

  • Weak Matrix
  • practical
  • The project team
  • Piojectized
  • None

Answer : The project team

PMI-002 Certify Associate Project Management Practice Exam Set 4

What is the orientation of the output?


Options are :

  • Hypothesis
  • limit
  • None
  • The project plan and to the PM
  • everything above

Answer : everything above

The project cost management plan has been created as part:


Options are :

  • Develop Project Management Plan process
  • None
  • Determine the budget process
  • Costs and review process
  • Cost Control Process

Answer : Develop Project Management Plan process

Down from the estimate of the second term:


Options are :

  • Analogous estimating
  • Parametric Modeling
  • The bottom-up assessment
  • None
  • Life cycle costs

Answer : Analogous estimating

PMI-SP Scheduling Professional Practice Exam Set 8

__________ involves the use of a mathematical model of the project properties


Options are :

  • Life cycle costs
  • None
  • The bottom-up assessment
  • Parametric Modeling
  • Analogous estimating

Answer : Parametric Modeling

You are the project. You have just completed a project manager and define the scope of the collection. what should I do?


Options are :

  • Creating WBS
  • Degree of control
  • Value Analysis
  • The extent Veirify
  • None

Answer : Creating WBS

A triangular distribution, low and high values ??may € <A € <20,30 and 40, respectively. The average is _____.


Options are :

  • thirty
  • 27.5
  • None
  • $23
  • 25

Answer : thirty

PMI-100 Certified Associate Management Practical Exam Set 1

At what point, the impact of the project stakeholders largest?


Options are :

  • Off Taiwan
  • carried out
  • None
  • Nonene of the above
  • In the beginning of time

Answer : In the beginning of time

Turn off the main output of the project ____________.


Options are :

  • In order to allow customers and sponsors of approval
  • Milestone list
  • None
  • The end of the formal and share all information about the project
  • Learn a lesson

Answer : The end of the formal and share all information about the project

Which of the following is Nonet part of the project cost baseline, but it is included in the project budget?


Options are :

  • Reserve Reserve Board
  • Activities unforeseen expenses reserve
  • None
  • General and administrative expenses
  • Project management planing

Answer : Reserve Reserve Board

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 6

Which of the following is Nonet a planning report examples?


Options are :

  • Fishbone Diagram
  • The network map
  • None
  • Milestone charts
  • Gantt chart

Answer : Fishbone Diagram

Change control committee should _______?


Options are :

  • None
  • flexible
  • all of the above
  • related department
  • Part of the project manager

Answer : all of the above

What is Nonet part of the following earned value calculated?


Options are :

  • project budget
  • UnkNonewn UnkNonewn
  • Characterization UnkNonewn
  • None
  • The amount of work completed

Answer : UnkNonewn UnkNonewn

PMI-RMP PMI Risk Management Professional Practice Test Set 8

Which of the following is the output range verification process?


Options are :

  • Officially approved
  • WBStemplate
  • SOW approval
  • None
  • Heavy Industry

Answer : Officially approved

10 members of the existence of a variety of channels to communicate how the group?


Options are :

  • 10
  • None
  • 20
  • 45
  • thirty

Answer : 45

The organization you are working and have pointed out that stakeholders an open future costs for all involved in the project. Rather, it CAPM is to create a WBS, which does Nonet include all the necessary to get the project completed tasks. What should be done?


Options are :

  • None
  • Immediately faced with other projects
  • Talk about CAPM WBS, see if you can edit the actual cost of the project
  • Mail T0 PMI headquarters
  • igNonere it

Answer : Talk about CAPM WBS, see if you can edit the actual cost of the project