PMI-001 PMP V5 Planning Certification Practice Exam Set 3

What is the function of the Project Management Office (PMO)?


Options are :

  • None
  • Focus on a specific project goals and manage scope, schedule, cost, and quality of work packages.
  • Manage performance estimates the project manager and project team members and deal with any personnel and payroll administration issues.
  • To coordinate and manage projects related to acquisition of the parent company's goals and manage project plans accordingly.
  • Focus on the coordinated planning, prioritization and implementation of projects and subprojects that are tied to the entire business of the parent organization or client's objectives.

Answer : Focus on the coordinated planning, prioritization and implementation of projects and subprojects that are tied to the entire business of the parent organization or client's objectives.

What information is part of the WBS dictionary?


Options are :

  • Organizational process assets
  • validated deliverables
  • responsibility organization
  • None
  • change requests

Answer : responsibility organization

Changes to formally controlled documentation, plans, etc. to reflect the change in content or ideas or known as:


Options are :

  • preventive measures.
  • corrective measures.
  • bug fixes
  • None
  • updates

Answer : updates

The milestone list is an input, which is the process of planning process group?


Options are :

  • The sequence Action
  • Define Action
  • None
  • Estimate Activity Durations
  • Estimate Activity Resource

Answer : The sequence Action

PMI-100 Certified Associate Project Management Practice Exam Set 4

The work package is to pay $ 1,000 to the end, and it was finished today. As of today, the actual expenditure is $ 1,200, and about half have been completed. What is the cost variance?


Options are :

  • None
  • -200
  • 500
  • 200
  • -700

Answer : -700

What is the total float the critical path?


Options are :

  • None
  • Zero or positive
  • Can be any
  • Zero or negative,
  • Depends on the calendar

Answer : Zero or negative,

Which, together with the project manager, is intended to guide the performance of the planned project activities and manage the various technical and organizational interfaces that exist in the project?


Options are :

  • None
  • project Management Team
  • Sponsors and stakeholders
  • Risk owners and stakeholders
  • The customer and operational managers

Answer : project Management Team

What is a project manager and the functional managers are responsible for?


Options are :

  • Both correspond to the project aims to achieve.
  • The achievement of the objectives of the project providing for the control of the management administrative area
  • None
  • To implement the control of the administrative area; one side of the core business
  • Facet's core business; achievement of the objectives of the project

Answer : The achievement of the objectives of the project providing for the control of the management administrative area

What type of analysis systemically collect and analyze qualitative and quantitative information, which interests must be taken into account throughout the project?


Options are :

  • The cost-benefit
  • None
  • research
  • Product
  • stakeholders

Answer : stakeholders

Which is used to request proposals for prospective sellers?


Options are :

  • resource calendars
  • procurement document
  • independent forecasts
  • Procurement statement of work
  • None

Answer : procurement document

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 7

Which is an example Administer contracts?


Options are :

  • The establishment of evaluation criteria
  • when the agreement
  • Developing the statement of work
  • None
  • The license refurbishment

Answer : The license refurbishment

Which creates a framework for managing a project?


Options are :

  • Work breakdown structure (WBS)
  • Environmental factors
  • Starting the project
  • Project Cycle
  • None

Answer : Project Cycle

Which of the following is an input to control the extent of?


Options are :

  • Organizational process assets updates
  • PROJECT DOCUMENT Updates
  • project schedule
  • None
  • Work performance information

Answer : Work performance information

What tool or technique is used to Manage Stakeholder Expectations?


Options are :

  • Issue log
  • means of communication
  • Stakeholder Management Strategy
  • None
  • change requests

Answer : means of communication

Which of the following are the outputs of the Develop Project Team?


Options are :

  • Team performance assessment and corporate environmental factor update
  • Personnel changes in the plan and project staff assignment updates
  • Resource calendars and project management plan update
  • None
  • Project management plan updates and upgrades of corporate environmental factor

Answer : Team performance assessment and corporate environmental factor update

Gradual detailed project management plan is called:


Options are :

  • rolling wave design.
  • expert assessment.
  • work performance information.
  • breakdown.
  • None

Answer : rolling wave design.

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 1

Which type of diagram is a graphical representation of the process shows the process steps relations between?


Options are :

  • Bar
  • Pareto
  • Flow
  • None
  • control

Answer : Flow

Which can be used to determine whether a process is stable or has predictable performance?


Options are :

  • Matrix diagram
  • histogram
  • None
  • control card
  • flow chart

Answer : control card

Identification of key deliverables, to decide if an adequate cost estimates can be developed, and to identify specific components of both items are all part of, which of the following?


Options are :

  • Organizational Breakdown Structure
  • work breakdown structure
  • Parts List
  • None
  • Resource Breakdown Structure

Answer : work breakdown structure

Quality Tools which are starting the process?


Options are :

  • None
  • Perform Quality Control
  • The quality plan
  • Perform Qualitative Risk Analysis
  • Perform quality assurance

Answer : The quality plan

project manager for the operation to take to make the project management plan is effective and current?


Options are :

  • Follow the ISO 9000 quality standards.
  • Fill out the quality control checklist
  • None
  • Identify quality requirements of the project.
  • To carry out regular project development discussions.

Answer : To carry out regular project development discussions.

Portfolio management control:


Options are :

  • a project by splitting the project into more manageable sub-projects.
  • None
  • all the projects your company
  • project making use of the general portfolio management skills such as planning, organizing, staffing, executing, and monitoring.
  • a collection of projects, are assembled to facilitate the effective management and to meet strategic business objectives.

Answer : a collection of projects, are assembled to facilitate the effective management and to meet strategic business objectives.

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 5

Each project management process group Collect Requirements Define Actions Action Sequence, Perform Qualitative Risk Analysis, Quantitative Risk Analysis and Run?


Options are :

  • Closure
  • commencement of
  • Monitoring and control of
  • Design
  • None

Answer : Design

Pre-assignment When will the project take place in groups?


Options are :

  • When the project is using investments
  • Once the project is the result of specific people are promised as part of a competitive proposal
  • Once the project is ignored due to travel expenses
  • None
  • When the necessary personnel can be acquired from outside sources

Answer : Once the project is the result of specific people are promised as part of a competitive proposal

The organization, which is projectized organizational structure, which manages the project budget?


Options are :

  • None
  • functional Director
  • Project Management Office
  • Head of Programming
  • Project manager

Answer : Project manager

Which tool is designed to develop the technical details within the framework of the project management plan?


Options are :

  • Project Management Method
  • None
  • Project Management Information System (PMI)
  • expert assessment
  • Project selection methods

Answer : expert assessment

Feed Create WBS process is:


Options are :

  • The project scope.
  • Register stakeholders.
  • None
  • The project plan.
  • traceability matrix.

Answer : The project scope.

The tools and techniques used to plan, include communication Communications:


Options are :

  • methods, stakeholder registry, communications technology and communications models.
  • management plan, communication technology, communication patterns and communication requirements analysis.
  • requirements, communication, communication requirements analysis, and communication methods.
  • needs analysis and communication, models of communication and methods of communication.
  • None

Answer : needs analysis and communication, models of communication and methods of communication.

PMI-RMP PMI Risk Management Professional Practice Test Set 6

Output Create WBS process is:


Options are :

  • Traceability matrix.
  • Scope baseline.
  • None
  • The project scope
  • Organizational process assets.

Answer : Scope baseline.

The method comprising the documentation of actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?


Options are :

  • None
  • To monitor and control project work
  • Collect requirements
  • Develop Project Management Plan
  • Direct and manage project execution

Answer : Develop Project Management Plan