PMI-001 PMP V5 Initiation Certification Practice Exam Set 8

Whose contribution to gather requirements to identify stakeholders who can provide information about the requirements?


Options are :

  • Stakeholder management plan
  • Scope Management Plan
  • The project plan
  • None
  • register of interest groups

Answer : register of interest groups

What are the risks if the probability of occurrence rating is 0.30, and the effect, if it occurs with moderate (0.20)?


Options are :

  • 0.06
  • None
  • 0.5
  • 0.1
  • 0.03

Answer : 0.06

PMI-SP Scheduling Professional Practice Exam Set 1

The danger that the direct result of taking a risk, the answer is called:


Options are :

  • The potential risk of
  • None
  • secondary risk
  • risk of contingent
  • residual risk

Answer : secondary risk

What type of probability distribution is used to represent uncertain events, such as the result of a test or a possible scenario of a decision tree?


Options are :

  • uniform
  • None
  • separate
  • Continuous
  • Linear

Answer : separate

Uncertainty unit is ready to take in anticipation of a reward is known for its risk:


Options are :

  • answer
  • management
  • appetite
  • tolerance
  • None

Answer : appetite

PMI-RMP PMI Risk Management Professional Practice Test Set 4

Every area of ??expertise by studying people, groups or organizations that may influence or affect the project?


Options are :

  • The project stakeholder management
  • The scope of the project management
  • None
  • project Risk Management
  • Project Human Resource Management

Answer : The project stakeholder management

The component is human resource management, including the ways in which team members can get the certificates that support their ability to benefit from the project known as:


Options are :

  • staff acquisition
  • compliance
  • None
  • training needs
  • recognition and awards

Answer : training needs

Every method group and area of ??expertise contain a sequence of operation of the process?


Options are :

  • Executing Process Group and Project Time Management
  • Group planning process and project cost control
  • Group planning process, and Project Time Management
  • Executing Process Group and the project cost management
  • None

Answer : Group planning process, and Project Time Management

PMI Risk Management Professional Certification Practice Exam Set 5

What inputs Manage Stakeholder engagement process will guide you how stakeholders can best be involved in the project?


Options are :

  • stakeholder analysis
  • Feedback analysis
  • communications management plan
  • None
  • Stakeholder management plan

Answer : Stakeholder management plan

Whose contribution to the risk management process plan provides information about a high level of risk?


Options are :

  • Environmental factors
  • Organizational process assets
  • register of interest groups
  • None
  • The project plan

Answer : The project plan

Every process of numerically analyzing the effect of identified risks to the general objectives of the project?


Options are :

  • None
  • The risk management plan
  • Perform Qualitative Risk Analysis
  • quantitative risk analysis
  • Planned Risk Responses

Answer : quantitative risk analysis

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 5

The ad hoc project, which will create a unique product or service is called:


Options are :

  • project
  • portfolio
  • None
  • Program
  • Plan

Answer : project

A stakeholder analysis reflects the need for the project manager is not known. The project manager probably missed a step in which the stakeholders in the management process?


Options are :

  • Identify Stakeholders
  • Manage Stakeholder engagement
  • None
  • Control Stakeholder engagement
  • Planned stakeholder management

Answer : Planned stakeholder management

Project management processes ensure that:


Options are :

  • effective means to achieve the objectives of the project
  • effective flow during the entire project life cycle
  • Harmonization of the organization's strategy
  • the performance of the project team
  • None

Answer : effective flow during the entire project life cycle

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 4

Power, urgency, and legitimacy are the features that interest groups classification model?


Options are :

  • Power / interest
  • The impact / effects
  • Power / effect
  • None
  • salience

Answer : salience

The project stakeholder management will focus on:


Options are :

  • the management of conflicts of interest
  • means of communication
  • None
  • The project tea m acquisition
  • Project Loan staff

Answer : the management of conflicts of interest

The aim is to develop a project scope management plan:


Options are :

  • Manage the timely completion of the project
  • That project includes all the work required.
  • Make sure the project will satisfy for which it has begun.
  • None
  • To reduce the negative events in the project.

Answer : That project includes all the work required.

PMI-SP Scheduling Professional Practice Exam Set 1

Once the project is committed to reducing defects in the product or service, the aim of the project is to create a / an:


Options are :

  • program
  • None
  • portfolio
  • improvement
  • result

Answer : improvement

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions