Which is an enterprise environmental factor?


Options are :

  • Marketplace conditions
  • Project files from previous projects
  • Policies and procedures
  • Lessons learned from previous projects
  • None

Answer : Marketplace conditions

What object is an example of the staff evaluation?


Options are :

  • tight matrix
  • resource calendar
  • Target group
  • None
  • team-building activities

Answer : Target group

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 7

Business needs, assumptions and limitations and understanding the needs of customers and the high-level requirements are documented:


Options are :

  • None
  • Stakeholder Register.
  • The project management plan.
  • Work breakdown structure.
  • The project plan.

Answer : The project plan.

Every document describes the necessary information whether the project is worth the investment needed?


Options are :

  • Case Study
  • a letter of intent
  • None
  • cost baseline
  • service level agreement

Answer : Case Study

Plan stakeholder management process, the expert estimates are used:


Options are :

  • To ensure comprehensive identification and listing of new stakeholders.
  • None
  • Which is needed to design appropriate ways to engage project stakeholders.
  • Decide on the degree of commitment of stakeholders at each stage required.
  • By analyzing the information needed to develop the project scope.

Answer : Decide on the degree of commitment of stakeholders at each stage required.

PMI Certification Practice Questions

Identify Stakeholders process is found, the process in which the Group?


Options are :

  • Monitoring and control of
  • Design
  • commencement of
  • None
  • showing

Answer : commencement of

Communications Management plan to develop an approach and plan for project communication is based on the needs and requirements of stakeholders and:


Options are :

  • Environmental factors
  • Available organizational resources
  • interpersonal skills
  • Project staff assignments
  • None

Answer : Available organizational resources

Interest groups can be identified in the later stages of the project, as stakeholders identification process should be:


Options are :

  • None
  • Continuous
  • separate
  • regulated
  • arbitrary

Answer : Continuous

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 7

Element project scope statement is:


Options are :

  • High-level risks.
  • Accreditation criteria.
  • None
  • Summary of the budget,
  • A stakeholder analysis list.

Answer : Accreditation criteria.

The organization's perceived balance between risk-taking and risk avoidance appears on risk:


Options are :

  • None
  • stance
  • Replies
  • Tolerance
  • Appetite

Answer : Replies

Each process is defined, documentation and management of the stakeholders' needs and meets the requirements of the project objectives?


Options are :

  • Collect requirements
  • None
  • Define Action
  • define scope
  • The scope of the plan Management

Answer : Collect requirements

PMI-100 Certified Associate in Project Management Test Set 1

Input Develop a project plan is a / an:


Options are :

  • The cost estimates.
  • Case Study.
  • The project management plan.
  • Action in the list.
  • None

Answer : Case Study.

Capacities of project management, such as motivational to encourage; listens actively; to persuade the team to perform an operation; and a summary, by coating, and identifying steps are known as:


Options are :

  • None
  • communication skills
  • hard skills
  • organizational skills
  • technical skills

Answer : communication skills

Every stakeholder accepts the project result?


Options are :

  • customer
  • None
  • Sponsor
  • Seller
  • functional Director

Answer : customer

PMP Certification Question and Answers

The ability to influence cost is greatest during which phases of the project?


Options are :

  • Graduation
  • early
  • middle
  • Late
  • None

Answer : early

In which area of ??expertise is project plan developed?


Options are :

  • Project Integration Management
  • None
  • The scope of the project management
  • Project Cost Management
  • Project Time Management

Answer : Project Integration Management

through which project managers do not take the job?


Options are :

  • Of consultants and stakeholders
  • Members and consultants of the project
  • members and stakeholders of the project
  • None
  • Stakeholders and functional leaders

Answer : members and stakeholders of the project

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 4

Every process is carried out from the beginning of the project when filling and is ultimately the responsibility of the project manager?


Options are :

  • Perform Integrated Change Control
  • None
  • Quality control
  • The extent of control
  • To monitor and control project work

Answer : Perform Integrated Change Control

Perfect for concepts, terms and functions that make up the area known as the specialization of:


Options are :

  • process Group
  • knowledge area
  • management of programs
  • portfolio management
  • None

Answer : knowledge area

Project management, temporary project can be:


Options are :

  • The process of producing goods
  • Completed without planning
  • Long lasting
  • None
  • The routine business processes

Answer : Long lasting

PMI Risk Management Professional Certification Practice Exam Set 8

Every document project management plan can be upgraded to plan procurement management process?


Options are :

  • risk matrix
  • budget estimates
  • documentation requirements
  • None
  • the procurement documents

Answer : documentation requirements

Stakeholders should be managed as a key project:


Options are :

  • benefit
  • Target
  • None
  • Process
  • initiative

Answer : Target

Zero duration of the milestones in the project planning occurs because the milestones:


Options are :

  • Occur at random times in the project plans.
  • Represent both significant and insignificant steps in the project and are difficult to predict.
  • None
  • Represent the time, as a major project point or event.
  • Are unpredictable and challenge the Plan Schedule Management process.

Answer : Represent the time, as a major project point or event.

PMI-SP Scheduling Professional Practice Exam Set 3

Identify risks is part of that process group?


Options are :

  • Closure
  • None
  • Design
  • showing
  • commencement of

Answer : Design

What the process involves developing an approximation of the monetary resources needed to complete project activities?


Options are :

  • Cost management plan
  • None
  • estimate of costs
  • determine your budget
  • control costs

Answer : estimate of costs

What tool or technique is used in developing the Project Management Plan process?


Options are :

  • Pareto chart
  • expert assessment
  • performance reporting
  • SWOT
  • None

Answer : expert assessment

PMI-SP Scheduling Professional Practice Exam Set 7

By the input of stakeholders on the process data is internal or external parties related to the project?


Options are :

  • The project plan
  • the procurement documents
  • None
  • register of interest groups
  • a communication plan

Answer : The project plan

The risk of operational strategy in which the project is to reduce the likelihood or effect of danger are known:


Options are :

  • None
  • Ice
  • to take advantage of
  • avoid
  • mitigate

Answer : mitigate

Output management Stakeholder engagement process is:


Options are :

  • change log
  • Enterprise environmental factors
  • Stakeholder management plan
  • None
  • change requests

Answer : change requests

PMI-SP Scheduling Professional Practice Exam Set 2

The process of prioritizing risks for further analysis or operation are known:


Options are :

  • Quantitative risk analysis.
  • Perform Qualitative Risk Analysis.
  • Risk Replies plan.
  • None
  • Risk Management Plan.

Answer : Perform Qualitative Risk Analysis.