PMI-001 PMP V5 Initiation Certification Practice Exam Set 3

Which of them is true about the project management body of knowledge?


Options are :

  • The sum of information that should be applied to every project
  • constantly evolving
  • Recognized as each project manager
  • The sum of all the information related to project management
  • None

Answer : constantly evolving

Those properties are not effective project managers possess?


Options are :

  • Preparedness, project management, knowledge and personality characteristics
  • Project management knowledge, presentation skills and personal effectiveness
  • General management, preparedness and project management knowledge
  • Self-assurance, collaboration and presentation skills
  • None

Answer : Project management knowledge, presentation skills and personal effectiveness

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 11

There is a danger, a moment that the project is:


Options are :

  • were executed
  • None
  • hired
  • conceived
  • designed by

Answer : conceived

Which of the following is the outline of the project as an input to the Charter process?


Options are :

  • Work performance information
  • None
  • change requests
  • The project management plan
  • Case Study

Answer : Case Study

Which of the following methods is the selection of projects for technology?


Options are :

  • Flowcharts
  • None
  • Earned value
  • Pareto analysis
  • The cost-benefit analysis

Answer : The cost-benefit analysis

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 5

Which of the following is a limitation of the project?


Options are :

  • Project management can become volatile political environment.
  • None
  • Twenty-five per cent of staff turnover is expected.
  • 250 days required for the product.
  • The technology can be used, is the top level.

Answer : 250 days required for the product.

The initial development of the Project Scope Management Plan to use what technology?


Options are :

  • product analysis
  • Identifying alternatives
  • expert assessment
  • The scope of disintegration
  • None

Answer : expert assessment

The scope of the control which input is compared to the actual results to verify whether corrective action is needed of the project?


Options are :

  • cost baseline
  • The extent of baseline
  • None
  • change management
  • Scope Management Plan

Answer : The extent of baseline

PMI Question Answers

The application of knowledge, skills, tools and techniques to project activities to meet project requirements image management, which of the following


Options are :

  • project
  • scope
  • None
  • Program
  • agreement

Answer : project

The scope of the inspection mainly concerns which of the following?


Options are :

  • Approval of work performances.
  • None
  • Precision work performances.
  • Precision work breakdown structure.
  • Approval of the scope of the

Answer : Approval of work performances.

Collect the input requirements for the process is:


Options are :

  • None
  • Register stakeholders.
  • requirements management plan.
  • The project scope.
  • project management plan.

Answer : Register stakeholders.

PMI-RMP PMI Risk Management Professional Practice Test Set 9

Check-in requires the development of a preliminary project scope statement is:


Options are :

  • Organizational Breakdown Structure
  • organizational Matrix
  • A similar process Organizational
  • organizational structure
  • None

Answer : A similar process Organizational

Risk responses reflect the perceived balance of the organization:


Options are :

  • known risks and unknown risks.
  • the avoidance of risk taking and risk.
  • None
  • identified risk and analyzed the risk
  • varying degrees of risk.

Answer : the avoidance of risk taking and risk.

Every activity is an input to the process to select vendors?


Options are :

  • availability of resources
  • the management of change process
  • Team performance evaluation
  • Organizational process assets
  • None

Answer : Organizational process assets

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 2

Projects are separated phases or sub-projects; These steps are:


Options are :

  • feasibility study, concept development, design and prototype.
  • to initiate, plan, execute and monitor.
  • Identify stakeholders, to develop the concept, build, and test.
  • None
  • Develop Charter, Define Activities, Manage Stakeholder Expectations and Performance Report.

Answer : feasibility study, concept development, design and prototype.

What type of contract is a hybrid of both cost-reimbursable and fixed-price contract?


Options are :

  • Cost Plus Fee Contract (CPIF)
  • Contract and material (T & M)
  • Firm Orientation-Fixed -Price Contract (FFP)
  • Cost Plus Award Fee Contract (CPAF)
  • None

Answer : Contract and material (T & M)

Which of the following processes of prioritizing risks include the subsequent further analysis or action by assessing and combining the likelihood and impact of their occurrence?


Options are :

  • Risk Management Plan
  • None
  • Qualitative risk analysis
  • Quantitative risk analysis
  • Risk response planning

Answer : Qualitative risk analysis

PMI-100 Certified Associate Project Management Practice Exam Set 8

What are the components ā € œtriple constraintā €?


Options are :

  • Scope, management, cost
  • None
  • Scope, time, cost,
  • Scope, time, requirements
  • Resources, time, cost

Answer : Scope, time, cost,

Stakeholder register is the output:


Options are :

  • Control Stakeholder engagement.
  • Manage Stakeholder engagement.
  • Plan stakeholder management.
  • Identify the stakeholders.
  • None

Answer : Identify the stakeholders.

PMI-SP Scheduling Professional Certification Practice Test Set 6

M & A projects purpose or justification, measurable project objectives and related success criteria, a summary of a milestone schedule, summary and budget are factors that document?


Options are :

  • work breakdown structure
  • The project plan
  • requirements document
  • The project management plan
  • None

Answer : The project plan

Scope of the project can not be defined without some basic knowledge on how to create the specified:


Options are :

  • None
  • product
  • objectives
  • approach
  • schedule

Answer : product

Every activity is an input to Conduct Procurement Process?


Options are :

  • Organizational process assets
  • Perform Integrated Change Control
  • None
  • Team performance evaluation
  • availability of resources

Answer : Organizational process assets

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 3

To confirm the extent of the process relates primarily to:


Options are :

  • Formalizing acceptance of the completed project deliverables.
  • None
  • the scope of the official approval.
  • precision work breakdown structure (WBS).
  • the accuracy of the work performances.

Answer : Formalizing acceptance of the completed project deliverables.

Which of the following statements best describes the impact on stakeholders and the cost of changes to the project advances?


Options are :

  • The influence of interest groups is reduced, increases the cost of the changes.
  • The effect of the stakeholders is reduced, decreasing the cost of the changes.
  • None
  • The influence of stakeholders grows, so does the cost of the changes.
  • The influence of stakeholders increases, decreases the cost of changes.

Answer : The influence of interest groups is reduced, increases the cost of the changes.

The component has a risk management plan that documents how risky activity recorded is called:


Options are :

  • cropping
  • defining
  • tracking
  • timing
  • None

Answer : tracking

PMI PGMP Program Management Professional Practice Test Set 1

Every process is included in the Project Integration Management knowledge area?


Options are :

  • Direct and manage project work
  • Collect requirements
  • The sequence Action
  • manage Project Team
  • None

Answer : Direct and manage project work

Each of the basic quality of the tool to explain the dependent variable with respect to a change in the independent variable corresponding to the change is detected;


Options are :

  • control card
  • histogram
  • Cause and effect diagram
  • a scatter diagram
  • None

Answer : a scatter diagram

Organizations are realizing the risks:


Options are :

  • the objectives of the negative effects of unwanted events and the organization for their project.
  • events which could have a negative impact on the objectives of the project and the organization.
  • the effect of uncertainty on their project and organizational goals.
  • None
  • events that will inevitably affect the project and organizational goals.

Answer : the effect of uncertainty on their project and organizational goals.

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 5

Which of the following risk strategies related to the allocation of the ownership of a positive risk to a third party?


Options are :

  • mitigate
  • None
  • Transfer
  • Avoid
  • Ice

Answer : Ice

Which of the following investigates the likelihood that each specific risk will happen?


Options are :

  • audits
  • Risk assessment of urgency
  • None
  • risk register
  • Assessment of risk probability and impact

Answer : Assessment of risk probability and impact

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions