PMI-001 PMP V5 Initiation Certification Practice Exam Set 1

PMBOI guide is a standard that describes:


Options are :

  • None
  • program management and project management processes.
  • product-oriented and project management processes.
  • product-oriented processes.
  • project management processes.

Answer : project management processes.

PMI-RMP PMI Risk Management Professional Practice Test Set 3

Loading...


Options are :

  • None
  • functional Director
  • Project Management Office
  • Functional Director supports the project manager
  • Project manager

Answer : Project manager

What is Project Portfolio Management?


Options are :

  • The management of a collection of projects, are assembled to facilitate the effective management and to meet strategic business objectives.
  • the management of all projects undertaken by the company.
  • None
  • making use of project portfolio management, general management skills such as planning, organizing, staffing, executing, and monitoring.
  • Management of the project by dividing the project into more manageable sub-projects.

Answer : The management of a collection of projects, are assembled to facilitate the effective management and to meet strategic business objectives.

What are the five project management process groups?


Options are :

  • The initiation, planning, executing, monitoring and controlling, and closing
  • INTRODUCTION, planning, execution, monitoring and controlling, and closing
  • The initiation, planning, executing, monitoring and controlling, and ending
  • Introduction, design, implementation, monitoring and management, and Termination of
  • None

Answer : The initiation, planning, executing, monitoring and controlling, and closing

PMP Exam Questions

Inputs to the identification of stakeholders are:


Options are :

  • The project plan, stakeholder analysis, enterprise environmental factors, and stakeholder management strategy.
  • The project design, procurement documents, expert assessment and organizational process assets.
  • The project plan, stakeholder analysis, enterprise environmental factors and organizational process assets.
  • The project design, procurement documents, company environmental factors, and organizational process assets.
  • None

Answer : The project design, procurement documents, company environmental factors, and organizational process assets.

What is the definition of the implementation of the project plan?


Options are :

  • The performance deliverables
  • Develop and maintain the plan
  • Conduct of the operations included in the plan
  • None
  • Integrate all the planned activities

Answer : Conduct of the operations included in the plan

For any given project, the project manager, in cooperation with the project team, which is responsible for:


Options are :

  • By tailoring processes to fit the capabilities of the organization.
  • Applying the knowledge, skills and processes in a consistent manner.
  • None
  • Informing the project sponsor which processes will be used.
  • What in particular are appropriate.

Answer : What in particular are appropriate.

PMI-SP Scheduling Professional Certification Practice Test Set 9

Which of the following is an input during the qualitative risk analysis?


Options are :

  • Risk assessment of the quality of information
  • risk rating
  • risk of urgency
  • risk register
  • None

Answer : risk register

The main function of a project management office to support project managers in a variety of ways, including which of the following?


Options are :

  • None
  • Aligning organizational / strategic direction that affects project and program objectives
  • Acting as the project sponsor by providing funds for the project
  • Solving and change management common management structure
  • Developing and managing project policies, procedures, templates, and other shared documentation

Answer : Developing and managing project policies, procedures, templates, and other shared documentation

Where the companies environmental factors are taken into account during the evaluation of the cost?


Options are :

  • For commercial databases and corporate structure
  • None
  • Marketplace conditions and corporate structure
  • Existing human resources and market place conditions
  • Market Place and commercial databases

Answer : Market Place and commercial databases

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 8

Description of the product definition is used:


Options are :

  • None
  • Formally authorize the project.
  • Describe the project in great detail.
  • Profit stakeholder support for the project.
  • Document the characteristics of the product.

Answer : Document the characteristics of the product.

Which of the following is a process which identifies the actions that must be performed to produce the project deliverables?


Options are :

  • Define Action
  • activity is determined
  • None
  • The sequence Action
  • Estimate Activity Durations

Answer : Define Action

Which of the following is an example of technology used in quantitative risk analysis?


Options are :

  • sensitivity analysis
  • Risk assessment of the quality of information
  • risk rating
  • The probability and effect of the matrix
  • None

Answer : sensitivity analysis

PMI-001 PMP Closing V5 Certification Practice Exam Set 1

Project management approach should be described:


Options are :

  • change control plan
  • statement of work
  • The project management plan
  • None
  • The scope of the project

Answer : The project management plan

Which of the following tools and techniques used to Develop the project process?


Options are :

  • organizational theories
  • acquisitions
  • Group activities
  • None
  • virtual teams

Answer : Group activities

Which is a document that shows the hierarchical project organization?


Options are :

  • OBS
  • None
  • CPI
  • BOM
  • WBS

Answer : OBS

Which is input to the extent of the revision process?


Options are :

  • The project scope
  • performance report to the
  • requested changes
  • None
  • work breakdown structure

Answer : The project scope

In which process the Group within the scope defined in the first place?


Options are :

  • None
  • control of
  • Design
  • showing
  • commencement of

Answer : commencement of

The cost management processes and their associated tools and techniques are usually chosen in which of the following?


Options are :

  • The project cost estimate
  • Defining the Project Cycle
  • None
  • The project plan development
  • The project housekeeping

Answer : Defining the Project Cycle

Which of the following is an example of the management contract?


Options are :

  • when the agreement
  • The license refurbishment
  • Developing the statement of work
  • None
  • The establishment of evaluation criteria

Answer : The license refurbishment

What characteristic do share of the project and operational work in common?


Options are :

  • Executed systems
  • None
  • Uniqueness
  • Restrict the limited resources
  • repetition

Answer : Restrict the limited resources

What entity is assigned various responsibilities related to its domain centralized and unified management of the projects in question?


Options are :

  • Executive sponsorship office
  • Program Management Office
  • None
  • Project Management Office
  • The project team office

Answer : Project Management Office

PMI-100 Certified Associate Project Management Practice Exam Set 1

What is the process to determine which risks might affect the project?


Options are :

  • identify risks
  • None
  • Quantitative risk analysis
  • Qualitative risk analysis
  • The risk management plan

Answer : identify risks

The initiating process group, at which point it will be officially approved the project?


Options are :

  • None
  • When the project manager has been appointed
  • When the necessary funding or funding is obtained
  • When all stakeholders agree on the scope of the project
  • When the project is signed

Answer : When the project is signed

The project can be defined as:


Options are :

  • The permanent effort that produces repetitive outputs
  • The permanent quest undertaken to create a unique product, service or result
  • Temporary quest undertaken to create a unique product, service or result
  • Temporary project, which produces a repetitive outputs
  • None

Answer : Temporary quest undertaken to create a unique product, service or result

PMI-SP Scheduling Professional Certification Practice Test Set 6

The project plan must input the process?


Options are :

  • To develop a project plan
  • Perform Integrated Change Control
  • To monitor and control project work
  • None
  • Develop Project Management Plan

Answer : Develop Project Management Plan

Stakeholder management strategy is the output:


Options are :

  • None
  • Share knowledge.
  • The report performance.
  • Communications Plan.
  • Identify the stakeholders.

Answer : Identify the stakeholders.

Which of the following forecasting methods use historical data basis for forecasting future results?


Options are :

  • None
  • Time series
  • condemnatory
  • Simulation
  • econometric

Answer : Time series

PMI-SP Scheduling Professional Certification Practical Exam Set 5

Who need to know, when the risk of an event, so that the response can be implemented?


Options are :

  • project Management Team
  • project sponsors
  • None
  • Insurance Claims Department
  • Customers

Answer : project Management Team

PMI-100 Certified Associate Management Practical Exam Set 10

Which of the following is an example of the risk of symptom?


Options are :

  • Remaining in milestones
  • Crashes, front loading or fast tracking
  • Risk limit target
  • None
  • The power of nature, such as floods

Answer : Remaining in milestones

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions

ended-->