PMI-001 PMP V5 Executing Certification Practice Exam Set 3

Outputs element methods can be used, such as:


Options are :

  • Inputs to other processes.
  • None
  • Indicators to eliminate redundancies in the project.
  • Identification of the project tasks.
  • Proof of completion of execution

Answer : Inputs to other processes.

Every document describes the procurement item in sufficient detail to enable potential sellers whether they are able to provide the products, services, or results?


Options are :

  • procurement management plan
  • Offer request
  • Procurement statement of work
  • None
  • Offer request

Answer : Procurement statement of work

PMP Exam Questions

Every property is unique in project work and does not apply to the operational work?


Options are :

  • Performed to achieve organizational objectives
  • None
  • By raising
  • Restrictive limits
  • temporary

Answer : temporary

Which of the following is an example of push communications?


Options are :

  • press releases
  • knowledge repositories;
  • intranet sites
  • Videoconferencing
  • None

Answer : press releases

Outlook negative stakeholders can result in / el:


Options are :

  • increase the probability of success of the project.
  • None
  • increase the probability of failure of the project.
  • a decreased likelihood of conflicting interests between stakeholders.
  • a decreased likelihood impede the progress of projects

Answer : increase the probability of failure of the project.

Team performance evaluations, starting at which of the following processes?


Options are :

  • Develop Human Resource Plan
  • Perform Quality Control
  • manage Project Team
  • Develop Project Team
  • None

Answer : Develop Project Team

The project manager has asked all members of the group of experts to carry out an anonymous questionnaire to identify potential risks. This is an example of a technique known as:


Options are :

  • Collection of information technology
  • feedback technology
  • The Delphi technique
  • None
  • interview technique

Answer : The Delphi technique

Which of the following are examples of interactive communication?


Options are :

  • press releases
  • intranet sites
  • None
  • video conferencing
  • audio message

Answer : video conferencing

PMP Exam Questions

The cost of deviation from the project include:


Options are :

  • rework
  • testing
  • inspections
  • None
  • training

Answer : rework

Question change requests and adapt approved changes to the scope of the project, the plans, and the environment is within the function, which of the following project management processes?


Options are :

  • None
  • Monitor and Control Risks
  • Perform Integrated Change Control
  • To monitor and control project work
  • Direct and manage project execution

Answer : Direct and manage project execution

Which of the following is an input to the Plan Risk Responses process?


Options are :

  • None
  • Schedule management plan
  • risk register
  • Organizational process assets
  • Risk assessment of urgency

Answer : risk register

Degradation, rolling wave planning and designs are all the tools and techniques which of the following?


Options are :

  • Define Action
  • Estimate Activity Durations
  • The sequence Action
  • None
  • Develop a schedule

Answer : Define Action

Which of the following is a schematic display of the project schedule activities and the logical relationships among them?


Options are :

  • Project milestone list
  • activity list
  • The project schedule network diagram
  • None
  • Gantt chart

Answer : The project schedule network diagram

Project management processes are:


Options are :

  • None
  • Static; They may not change on various projects.
  • The separate elements, which have well-defined interfaces.
  • Distributed worldwide and with all companies.
  • The project stages shall be given, if necessary, on various projects.

Answer : Distributed worldwide and with all companies.

PMI-001 PMP V5 Planning Certification Practice Exam Set 3

Which of the following is documented in directions engaged in an activity that can reduce the probability of negative consequences associated with project risks?


Options are :

  • Recommended preventive measures
  • None
  • the risk of re-evaluations
  • Recommended corrective actions
  • audits

Answer : Recommended preventive measures

Project management process groups are linked by:


Options are :

  • None
  • outputs them to produce
  • discrete or one-time events
  • The project management plan
  • common tools and techniques

Answer : outputs them to produce

The process of obtaining seller responses, selecting the vendor, and in connection with the grant agreement is called:


Options are :

  • Conduct procurement.
  • Close purchases.
  • procurement plan
  • None
  • Control Supplies.

Answer : Conduct procurement.

Human Resource Management processes include:


Options are :

  • Develop Human Resource Plan acquire project team, develop project team and manage the project team.
  • Acquire Project Team Manage Project Team Manage Stakeholder Expectations and develop the project team.
  • None
  • Acquire Project Team, Develop Human Resource Plan, conflict management and project management group.
  • To develop the project, Manage project team, Estimate Activity Resources, and acquire project team.

Answer : Develop Human Resource Plan acquire project team, develop project team and manage the project team.

What is the schedule performance index (SPI) using the following information? BAC = $ 100,000 PV = $ 50,000 = AC $ 80,000 EV = $ 40,000


Options are :

  • 1
  • 0.5
  • 0.8
  • 0.4
  • None

Answer : 0.8

Organizational Planning effects of projects using project prioritization based on risk, finance and organizations:


Options are :

  • resource plan
  • strategic plan
  • None
  • financial Outlook
  • The scope of the plan

Answer : strategic plan

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 2

Which method is the work performance information input?


Options are :

  • Create WBS
  • None
  • Direct and manage project execution
  • manage procurement
  • Perform Qualitative Risk Analysis

Answer : Direct and manage project execution

In complex projects / initiation of processes should be accompanied by:


Options are :

  • To evaluate the schedule constraints.
  • None
  • To assess the allocation of resources.
  • Within the work package.
  • Each stage of the project.

Answer : Each stage of the project.

Integrative nature of project management requires making the process of interacting with other Group process groups?


Options are :

  • None
  • Monitoring and control of
  • showing
  • Design
  • Project management

Answer : Monitoring and control of

A project management office is managed by a number of factors such as:


Options are :

  • None
  • The task of the project resources to best meet project objectives.
  • Central coordination of communication management on various projects.
  • The project scope, schedule, cost and product quality of the work packages.
  • The overall risk, overall opportunity, and mutual projects at the enterprise level.

Answer : The overall risk, overall opportunity, and mutual projects at the enterprise level.

And to the approved change, a critical defect was introduced. By removing the fault delay the delivery of the product. What is the most appropriate way to manage this situation?


Options are :

  • Crashing the schedule to repair the fault.
  • Leave a fault and work around it.
  • None
  • Use the change management process.
  • A fast-track the remainder of the development.

Answer : Use the change management process.

What type of manager by the performing organization to lead the team, which is responsible for achieving the objectives of the project?


Options are :

  • portfolio
  • None
  • functional
  • project
  • Program

Answer : project

PMP® Certification v6: 2 PMP Exams& Detailed PMP Math_14pdus Set 3

The project manager requesting industry groups and consultants to recommend the project to rely on the intervention of:


Options are :

  • Enterprise environmental factors.
  • Interaction Models.
  • expert assessment
  • The participation of stakeholders.
  • None

Answer : expert assessment

What type of analysis is used to plan the quality of the process?


Options are :

  • Schedule
  • The cost-benefit
  • assumption
  • Checklist
  • None

Answer : The cost-benefit

Which Perform quality assurance tools and techniques can be enhanced by creating a work breakdown structure (WBS) to give structure to the extent of degradation?


Options are :

  • Matrix diagrams
  • Activity network diagrams
  • The interaction between combinations of letters
  • None
  • Affinity diagrams

Answer : Affinity diagrams

Which describes the joint work that needs to be done and the members of the project?


Options are :

  • Work breakdown structure (WBS)
  • Staffing management plan
  • network diagrams
  • Raci (RAM)
  • None

Answer : Raci (RAM)