PMI-001 PMP Monitoring and Controlling V5 Practice Exam Set 2

Where the companies environmental factors are taken into account in the estimate costs?


Options are :

  • Company structure and market conditions
  • Existing human resources and market conditions
  • Market conditions and the published commercial information
  • Commercial information and corporate structure
  • None

Answer : Market conditions and the published commercial information

Where the companies environmental factors can influence the plan Schedule Management?


Options are :

  • Risk management procedures and the probability and impact matrix
  • Historical information and change management practices
  • Cultural views and schedules of professional and ethical behavior
  • None
  • the availability of resources and the organizational culture and structure

Answer : the availability of resources and the organizational culture and structure

Which type of dependency is used to Action Sequence process is sometimes referred to as preferred logic, preferential logic, or soft logic?


Options are :

  • None
  • Obligatory
  • external
  • internal
  • discretionary

Answer : discretionary

Every method Group's purpose is to monitor, review, and regulate the progress and implementation of the project; identify a point where the changes to the plan is required; and initiate the corresponding changes?


Options are :

  • Design
  • commencement of
  • None
  • showing
  • Monitoring and control of

Answer : Monitoring and control of

PMI-100 Certified Associate Management Practical Exam Set 2

What is the difference between the critical path and the critical chain?


Options are :

  • quality audits
  • resource limitations
  • scope changes
  • None
  • Risk Analysis

Answer : resource limitations

Output Control The schedule is:


Options are :

  • schedule forecasts
  • The project schedule network diagram
  • None
  • schedule data
  • Schedule management plan

Answer : schedule forecasts

What is the schedule network analysis technique to change the project schedule to the account with limited resources?


Options are :

  • Rolling wave planning
  • None
  • Fast tracking
  • The critical chain method
  • Human resource planning

Answer : The critical chain method

A collection of a group of projects managed to achieve its strategic objectives is called:


Options are :

  • plan
  • portfolio
  • program
  • None
  • process

Answer : portfolio

Which of the following is the output monitor and manage the project process?


Options are :

  • earnings Reports
  • Organizational process assets
  • The project management plan
  • change requests
  • None

Answer : change requests

Organizational process assets, a database of lessons learned and historical information are all the income to which the process?


Options are :

  • None
  • Planned Schedule Management
  • The scope of the plan Management
  • Cost management plan
  • Planned stakeholder management

Answer : Planned stakeholder management

PMI-RMP PMI Risk Management Professional Practice Test Set 7

a member of the project team agrees to modify the project is carried out after discussion with external stakeholders. It is later discovered that the change has had an adverse effect on the second deliverable. This could have been avoided if the project was implemented:


Options are :

  • The project team building.
  • Quality Insurance.
  • A stakeholder analysis management plan.
  • Integrated management of change.
  • None

Answer : Integrated management of change.

Success is measured benefits for execution:


Options are :

  • portfolio
  • None
  • strategic plan
  • program
  • project

Answer : program

Perform Quality control takes place:


Options are :

  • Monitoring and recording the results of carrying out quality activities to assess performance and recommend necessary changes.
  • Applying the Monte Carlo sampling, Pareto analysis, and benchmarking techniques in order according to the quality requirements.
  • Identification of quality standards that are relevant to the project and are determined to satisfy them.
  • None
  • Ensure that the entire project team is adequately trained in quality control processes.

Answer : Monitoring and recording the results of carrying out quality activities to assess performance and recommend necessary changes.

When the business objectives of the organization change, the objectives of the project will be:


Options are :

  • improved
  • realigned
  • None
  • completed
  • controlled

Answer : realigned

Input procurement management plan process is:


Options are :

  • Seller's proposals.
  • Activity cost estimates.
  • None
  • The procurement documents.
  • Do-or-buy decisions.

Answer : Activity cost estimates.

Whose approval may be needed for change requests after the change (CCB) approval?


Options are :

  • None
  • Customers or sponsors
  • subject matter experts
  • business Partners
  • functional leaders

Answer : Customers or sponsors

PMI-SP Scheduling Professional Practice Exam Set 8

Which type of the assessment can provide greater accuracy, depending on the sophistication and in-built data model?


Options are :

  • From down to up
  • parametric
  • The three-point
  • None
  • corresponding

Answer : parametric

What is the term given to products or services with the same functionality but different technical characteristics?


Options are :

  • scope
  • Grade
  • definition
  • None
  • Quality

Answer : Grade

Who are developing Schedule tool and technique to produce the theoretical early start date and the late start date?


Options are :

  • None
  • critical path
  • Schedule comparison bar charts
  • schedule compression
  • Analysis of variance

Answer : critical path

An input control schedule is:


Options are :

  • organizational process assets.
  • The activity list.
  • risk management plan.
  • None
  • resource calendar.

Answer : organizational process assets.

The project requires a component specifications very well understood. The performance targets established at the outset, and the final contract price is determined at the end of all the work is based on the seller's performance. with the most suitable supplier:


Options are :

  • Fixed price premium (FPIF).
  • None
  • Fixed price, which corresponds to the economy Price Changes (FP-EPA).
  • Cost Plus Fee (CPIF).
  • Cost Plus Award Fee (CPAF).

Answer : Fixed price premium (FPIF).

Information on job performance and cost forecasts are outputs, of which the cost of the project management process?


Options are :

  • determine your budget
  • None
  • control costs
  • Cost management plan
  • estimate of costs

Answer : control costs

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 7

What is the name of the statistical method that helps identify which factors may affect the variables in development of a product or process or production?


Options are :

  • None
  • quality checklist
  • Failure modes effects analysis
  • Design of Experiments
  • Risk Analysis

Answer : Design of Experiments

Outputs Communications Control process comprising:


Options are :

  • Project management plan updates and performance information
  • None
  • job performance and change requests
  • the issue logs and organizational process assets updates
  • Expert assessment and change requests

Answer : job performance and change requests

At the beginning of a typical project life cycle costs are:


Options are :

  • low, will be steady when the work is being done, and to increase the project nears the end.
  • low, top, when the work is done, and drop the project nears the end.
  • high, drop down when work is being done, and the growth of the project nears the end.
  • high, becomes low as the work is done, and drop the project nears the end.
  • None

Answer : low, top, when the work is done, and drop the project nears the end.

Which is expected to use technology as a basis for the actual cost of previous similar projects assessment of the cost of the current project?


Options are :

  • parametric
  • From top to bottom
  • None
  • corresponding
  • From down to up

Answer : corresponding

Measuring the cost performance which is required to achieve the remaining resources in order to meet a specified management objective and it is expressed as the ratio of the cost needed to finish an excellent job of remaining budget is known:


Options are :

  • Earned Value Management (EVM)
  • the end of the budget (BAC)
  • to-complete performance index
  • None
  • cost index

Answer : to-complete performance index

The cost of baseline and project funding requirements are the outputs of that process Project Cost Management?


Options are :

  • None
  • control costs
  • Cost management plan
  • estimate of costs
  • determine your budget

Answer : determine your budget

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 5

What cost management technique is used to compare the actual performance of the project, the success of the planned or expected?


Options are :

  • trend Analysis
  • combining cost
  • None
  • Analysis of variance
  • divination

Answer : Analysis of variance

Approaches, tools, and data sources that are used to perform the risk management of the project are determined by:


Options are :

  • None
  • Methodology
  • assumption analysis
  • risk category
  • attitude to risk

Answer : Methodology

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions