PMI-001 PMP Monitoring and Controlling V5 Practice Exam Set 1

Which of the following is a tool and technique used to track risks?


Options are :

  • Cost-effectiveness Baseline
  • benchmarking
  • None
  • Technical performance measurement
  • at the expense of quality

Answer : Technical performance measurement

Which process includes combining the estimated costs of individual schedule activities or work packages?


Options are :

  • cost variance
  • cost budgeting
  • cost baseline
  • None
  • cost forecasting

Answer : cost budgeting

After allowing the agency will take longer than planned to issue a permit, this risk can be described as:


Options are :

  • perception
  • effect
  • event
  • answer
  • None

Answer : event

Every quality control technology to illustrate the 80/20 principle?


Options are :

  • Ishikawa diagram
  • run chart
  • None
  • control card
  • Pareto diagram

Answer : Pareto diagram

PMI-RMP PMI Risk Management Professional Practice Test Set 7

Manage Procurement is part of that process group?


Options are :

  • Monitoring and control of
  • None
  • Closure
  • Design
  • showing

Answer : Monitoring and control of

Conciliation is a tool for credit lines, and the technology used that method?


Options are :

  • budget control
  • control costs
  • None
  • determine your budget
  • estimate of costs

Answer : determine your budget

Three process Project Cost Management are:


Options are :

  • To estimate the cost, schedule control and management of costs.
  • Assess costs, Decide on your budget, resources and Review Activity.
  • Nothing
  • None
  • Assess costs, Decide on your budget and control costs.

Answer : Assess costs, Decide on your budget and control costs.

Which process is responsible for monitoring the status of the project and the scope of the product and the extent of managing changes to the baseline?


Options are :

  • Analysis of variance
  • The extent of control
  • to review the scope of the
  • None
  • define scope

Answer : The extent of control

Plan-do-check-act is also known as:


Options are :

  • None
  • statistical sampling.
  • management responsibility,
  • continuous improvement.
  • prevention over inspection.

Answer : continuous improvement.

Which of the following is a tool or technique used in Determine Budget procedure?


Options are :

  • historical relations
  • None
  • The three-point estimation
  • Analysis of variance
  • The bottom-up assessment of the

Answer : historical relations

PMI-RMP PMI Risk Management Professional Practice Test Set 9

The agreement, which the seller shall be replaced by the performance of all eligible costs, contract work and then pay a bonus based on the achievement of certain financial targets are called:


Options are :

  • Cost plus fixed fee contract (CPFF).
  • None
  • Contract and material (T & M).
  • Cost Plus Fee Contract (CPIF).
  • Fixed price Contract fee (FPIF).

Answer : Cost Plus Fee Contract (CPIF).

What quality control tool to graphically see how different parts of the system related to one another?


Options are :

  • Pareto diagram
  • control card
  • flow chart
  • run chart
  • None

Answer : flow chart

Under what type of contract the seller does not receive compensation for the performance of all eligible costs of the contract work, as well as a fixed fee payment calculated as a percentage of the initial estimated cost of the project?


Options are :

  • Fixed price, which corresponds to the economy Price Changes Contract (FP-EPA)
  • None
  • Cost plus fixed fee contract (CPFF)
  • The company fixed price (FFP)
  • Cost Plus Fee Contract (CPIF)

Answer : Cost plus fixed fee contract (CPFF)

Every baselines constitute the performance measurement baseline?


Options are :

  • Scope baseline, baseline cost and schedule baseline
  • Cost baseline, project management, basic level and schedule baseline
  • None
  • Scope baseline, project management baseline and the quality of basic
  • Cost baseline, schedule baseline, and the output level of risk

Answer : Scope baseline, baseline cost and schedule baseline

What is the current development of the project established?


Options are :

  • None
  • The revised cost and schedule of the project
  • The estimated project cost and schedule
  • The actual project cost and schedule
  • Approved product requirements

Answer : The estimated project cost and schedule

At what time monitoring and control of the risks occurring?


Options are :

  • During the work, performance analysis
  • Throughout the project,
  • project milestones
  • project initiation
  • None

Answer : Throughout the project,

PMP Certification Questions

What is the minimum project schedule should contain?


Options are :

  • Critical chain analysis
  • Analysis of variance
  • None
  • The planned starting date and a planned finish date of each scheduled activity
  • The critical pathway

Answer : The planned starting date and a planned finish date of each scheduled activity

The detailed steps of the process development plan for the analysis in order to identify which improve their:


Options are :

  • value
  • quality
  • technical performance.
  • Status
  • None

Answer : value

What is the goal of the development project process?


Options are :

  • Functional managers to be more involved.
  • The basic rules of interaction
  • None
  • Feelings of unity of the trust and improved
  • Improved availability of resources

Answer : Feelings of unity of the trust and improved

The process to ensure that appropriate quality standards and operational definitions are used:


Options are :

  • Perform quality assurance
  • None
  • Perform Quality Control.
  • Plan Quality.
  • Full quality control.

Answer : Perform quality assurance

Where the data range employs the processes required to ensure timely and proper fashion, collection, distribution, storage, retrieval, and ultimate investment project information?


Options are :

  • None
  • Project Communications Management
  • project Risk Management
  • Project quality management
  • Project Integration Management

Answer : Project Communications Management

Each index is calculated projection of cost performance that can be achieved in the remaining work to meet a specified management objective?


Options are :

  • Score at the end of the
  • to-complete performance
  • cost-effectiveness
  • None
  • schedule performance

Answer : to-complete performance

PMI Risk Management Professional Certification Practice Exam Set 9

Using the following information, which is a Schedule Performance Index (SPI)? EV = $ 500 = $ 750 PV AC = $ 1000 $ 1200 BAC


Options are :

  • 0.75
  • 1.5
  • 0.5
  • 0.67
  • None

Answer : 0.67

Which technology utilized in the Control Schedule process?


Options are :

  • Analysis of variance
  • performance measurement
  • None
  • Schedule network analysis
  • baseline schedule

Answer : Analysis of variance

Ensuring that the projects and programs is expected to prioritize the allocation of resources is a priority, which of the following?


Options are :

  • relationship care
  • management of programs
  • portfolio management
  • None
  • project management

Answer : portfolio management

How does the quality control performed?


Options are :

  • By following the quality standards to be applied in accordance with the results of a particular project and specify the corrective action where appropriate
  • By applying a Monte Carlo sampling, Pareto analysis and benchmarking techniques to ensure conformity with the quality requirements
  • None
  • By identifying the quality standards that are relevant to the project and are determined to satisfy them
  • By making sure that the entire project team is adequately trained in quality control processes

Answer : By following the quality standards to be applied in accordance with the results of a particular project and specify the corrective action where appropriate

What will happen to the project stakeholders affected by the passage of time?


Options are :

  • None
  • uploads
  • remains the same
  • Reductions
  • Does not matter

Answer : Reductions

The project budget is set to $ 150,000. the duration of the project is designed for one year. the end of Week 16 of the project the following information is collected: Actual Cost = $ 50,000 = Plan costs $ 45,000 earned value = $ 40,000 What is the Cost Performance Index?


Options are :

  • 1.13
  • None
  • 1.25
  • 0.89
  • 0.8

Answer : 0.8

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 6

With the cost variance is negative and schedule variance is positive, the project is:


Options are :

  • on schedule.
  • budget support and behind schedule.
  • None
  • over budget and ahead of schedule.
  • complete; all the planned values have been earned.

Answer : over budget and ahead of schedule.

Total planned (PV) is also known as:


Options are :

  • work breakdown structure (WBS).
  • None
  • schedule target.
  • performance measurement baseline (PMB).
  • earned value baseline.

Answer : performance measurement baseline (PMB).

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions