PMI-001 PMP Closing V5 Certification Practice Exam Set 2

Which of the following characteristics can be found in the functional organizational structure?


Options are :

  • None
  • Limited project manager authority limited access to resources, and a part-time project manager role
  • Mild to moderate low to moderate project manager authority on the availability of resources, and a full-time project manager role
  • High-almost the entire project manager authority, almost all of the high availability of resources, and a full-time project management and administrative staff
  • Little or no project manager authority, little or no availability of resources, and functional leader to guide the project budget

Answer : Little or no project manager authority, little or no availability of resources, and functional leader to guide the project budget

Which is the correct formula for calculating the expected cost of operation of the three-point estimation?


Options are :

  • None
  • Ce = (C m + 6C0 + C p) / 4
  • Ce = (C 0 + 6 cm + C p) / 4
  • Ce = (C 0 + 4 cm + C p) / 6
  • Ce = (C 0 + Ca € § + 4Cp) / 6

Answer : Ce = (C 0 + 4 cm + C p) / 6

The project is the current cost index (CPI) of 1.25. To date, US $ 10,000 has been used in carrying out the project. What is the earned value of the work carried out to date?


Options are :

  • None
  • US $ 9500
  • US $ S000
  • US $ 10,000
  • US $ 12,500

Answer : US $ 12,500

The weak matrix, the project manager is responsible for:


Options are :

  • None
  • random
  • part-time
  • unlimited
  • full-time

Answer : part-time

PMP Practice Exams for Certification 2019 PMBOK 6 Edition Set 3

Every degree of authority is the project manager of the project is a strong matrix organizational structure?


Options are :

  • Mild or moderate
  • limited
  • Moderate to high
  • High to almost complete
  • None

Answer : Moderate to high

Which of the following is a tool or technique Define Activities process?


Options are :

  • parametric estimation
  • analysis of options
  • Preference diagram of a method (PDM)
  • None
  • Rolling wave planning

Answer : Rolling wave planning

In which process the Group's documented experience?


Options are :

  • Design
  • None
  • showing
  • Closure
  • commencement of

Answer : Closure

Class, whose contracts by sellers forced to carry out the law, where the potential economic damage if the objectives of the project are not met?


Options are :

  • Cost-reimbursable contracts
  • Fixed-price contract
  • And material contracts (R & M)
  • None
  • Cost plus fixed fee contracts (CPFF)

Answer : Fixed-price contract

When the sequencing of activities, what common abbreviated as FF stand for?


Options are :

  • finishing finishing
  • None
  • fixed charge
  • solid Finish
  • free Float

Answer : finishing finishing

Output Direct and manage project work process is:


Options are :

  • Outputs
  • Scope statement.
  • None
  • Activity lists.
  • Work breakdown structure.

Answer : Outputs

Feed Close Project or Phase is:


Options are :

  • None
  • Final products or services,
  • Work performance information.
  • Approved deliverables,
  • The document updates,

Answer : Approved deliverables,

The process of identifying and documenting relationships with project activities known as:


Options are :

  • The sequence Action
  • Control Schedule.
  • None
  • Define the action.
  • Develop your schedule.

Answer : The sequence Action

What type of addiction is by law or by agreement or the nature of the work, and often physical limitations?


Options are :

  • external
  • None
  • Obligatory
  • internal
  • discretionary

Answer : Obligatory

PMI-SP Scheduling Professional Practice Exam Set 8

Updates organizational process assets, such as procurement files, deliverable acceptances, and the teachings of the documentation of typical outputs of that process?


Options are :

  • behavior procurement
  • acquisition of control
  • None
  • Near the project or phase
  • close procurement

Answer : close procurement

The project manager to build consensus and overcome obstacles by using a communication technology?


Options are :

  • listening to
  • None
  • facilitation
  • management meetings
  • demonstration

Answer : facilitation

What tool or technique enables a large number of ideas are classified into groups for review and analysis?


Options are :

  • The thought / mind mapping
  • Brainstorming
  • The nominal group technique
  • None
  • the affinity diagram

Answer : the affinity diagram

Lessons learned are created and the project resources are released in the process where the Group?


Options are :

  • Closure
  • commencement of
  • Design
  • None
  • showing

Answer : Closure

The bonus may only be effective if it is:


Options are :

  • Formally, given during the project development discussions.
  • Something that is tangible.
  • To satisfy the need for highly valued by the individual.
  • None
  • Is given as soon as the project is completed.

Answer : To satisfy the need for highly valued by the individual.

during which the process is the project manager to review all previous data in order to ensure that all project work is complete and that the project has met its objectives?


Options are :

  • To monitor and control project work
  • Perform quality assurance
  • None
  • Near the project or phase
  • The extent of control

Answer : Near the project or phase

PMI-RMP PMI Risk Management Professional Practice Test Set 7

When the alternative dispute resolution (ADR) is necessary, which tool or technique should be used?


Options are :

  • Conflict management
  • interactive communication
  • claims administration
  • performance reporting
  • None

Answer : claims administration

The conditions, which are not under the control of the project team that directly affect or limit the project is called:


Options are :

  • None
  • Environmental factors
  • context diagrams
  • Work performance reports
  • Organizational process assets

Answer : Environmental factors

When a backward pass is calculated schedule restriction, which is later than the beginning of the coming date, which is calculated during the forward pass calculation, this will cause the type of float?


Options are :

  • positive
  • negative
  • None
  • Zero
  • Free

Answer : positive

External organizations that have a special relationship with the company and offer special skills are called:


Options are :

  • Sellers
  • Functional leaders.
  • Customers
  • None
  • Business Partners.

Answer : Business Partners.

Sensitivity analysis is typically displayed in a / an:


Options are :

  • The decision tree diagram.
  • Tornado charts
  • Ishikawa diagram.
  • Pareto diagram.
  • None

Answer : Tornado charts

Appendix A is an example of a Sequence The following types of activities?


Options are :

  • None
  • precedence diagram
  • The project schedule network charting
  • Activity vs. arrow chart
  • Mathematical analysis chart

Answer : precedence diagram

When will deliverables are accepted or not accepted?


Options are :

  • When the project closing
  • The contract closure
  • The output of the scope of the verification process,
  • When the project starts
  • None

Answer : The output of the scope of the verification process,

The end of the project scope is measured against:


Options are :

  • None
  • work performance measurements.
  • project management plan.
  • The project scope.
  • requirements for documentation.

Answer : project management plan.

What is the technique used in performance reporting process?


Options are :

  • expert assessment
  • Project Management Method
  • stakeholder analysis
  • None
  • Status review meetings

Answer : Status review meetings

PMI-SP Scheduling Professional Practice Exam Set 9

Which of the following is the assessment of the technology, which uses a previous similar projects to evaluate the parameters of the same parameter or measure of a current project?


Options are :

  • analog estimation
  • None
  • booking analysis
  • parametric estimation
  • The three-point estimation

Answer : analog estimation

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?


Options are :

  • The expected monetary value analysis
  • The three-point estimate
  • None
  • Modeling and Simulation
  • sensitivity analysis

Answer : The expected monetary value analysis

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions