SAP C_TSCM42_66 Certified Associate - Production Exam Set 4

A user you advise wishes to transfer variable process instructions for automated processing directly to certain work centers and machines in the production department (for example, feed speed, pressing pressure, dry temperature). The user also wishes to receive variable as-is messages (such as actual quantities, actual times) from these work centers and machines and to process these messages for feedback concerning production orders. Which of the following options would you recommend to implement these requirements?


Options are :

  • SAP Application Link Enabling (ALE)
  • Execution Steps (XSteps) and process messages (Correct)
  • Plant data collection (PP-PDC) interface
  • SAP Business Intelligence (BI)

Answer : Execution Steps (XSteps) and process messages

Which of the following master data do you need to provide for process manufacturing? (Choose three.)


Options are :

  • Production versions (Correct)
  • Serial numbers
  • Master recipe (Correct)
  • Resources (Correct)

Answer : Production versions Master recipe Resources

In production order processing, for which of the following objects can you enter a confirmation? (Choose three.)


Options are :

  • Individual Capacity (Correct)
  • Order (Correct)
  • Work Center
  • Operation / Suboperation (Correct)

Answer : Individual Capacity Order Operation / Suboperation

Which options can you offer a user of the SAP ECC system for managing costs (costing and settlement) with regards to production orders? (Choose two.)


Options are :

  • Series-based costing
  • Product cost collecting (Correct)
  • Order-based costing (Correct)
  • Work center-based costing

Answer : Product cost collecting Order-based costing

In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)


Options are :

  • Production Scheduling Profile
  • Material Master (Component) (Correct)
  • Work Center (Correct)
  • Routing (Correct)

Answer : Material Master (Component) Work Center Routing

Which options can you offer someone who uses the SAP ECC system for production orders and requires support for material supply in production? (Choose three.)


Options are :

  • Automatic generation of a transport order (Correct)
  • Material directory
  • Pull list (Correct)
  • Pick list (Correct)

Answer : Automatic generation of a transport order Pull list Pick list

A user has entered planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a product. For the coming months, requirements with requirement type LSF (derived from the main strategy 10) have been planned. The user would like to change the requirement type from LSF to VSF planning with final assembly (in accordance with planning strategy 40) for requirements in the production plan that have already been saved. Which of the following statements are applicable in this case? (Choose two.)


Options are :

  • The user has to change the requirement type for planning strategy 10 to VSF planning with final assembly in Customizing. The requirement type for all existing requirements is then changed automatically.
  • The user can enter the new planning strategy group 40 in the material master of the product, but the requirement type is not changed automatically for existing requirements. (Correct)
  • The planning strategy group can be changed from 10 to 40 in the existing production plan, and the requirement type for all requirements is changed automatically.
  • The present requirement for the product can be changed manually from LSF to VSF in the Requirement Type field in the production plan, so that the new strategy 40 determines the next planning operation. (Correct)

Answer : The user can enter the new planning strategy group 40 in the material master of the product, but the requirement type is not changed automatically for existing requirements. The present requirement for the product can be changed manually from LSF to VSF in the Requirement Type field in the production plan, so that the new strategy 40 determines the next planning operation.

Which of the following requirements for a manufacturing plant can be supported by using process manufacturing? (Choose three.)


Options are :

  • Variable calculation of material quantities (product output, material usage). (Correct)
  • Material requirements planning for production resources.
  • Master recipe-based manufacturing. (Correct)
  • Manufacturing in charge quantities. (Correct)

Answer : Variable calculation of material quantities (product output, material usage). Master recipe-based manufacturing. Manufacturing in charge quantities.

A finished material is to be planned in a controlled manner in the SAP ECC system in the context of requirements planning. The planned orders are scheduled using what is known as basic date scheduling (not lead-time scheduling). Which of the following statements is true for the resulting dependent requirements?


Options are :

  • In multi-level backward scheduling, dependent requirements are triggered at the start date for the higher-level assembly planned order.
  • In multi-level backward scheduling, dependent requirements are triggered at the start date for the higher-level assembly. (Correct)
  • If individual material components are explicitly assigned to operations during BOM and routing maintenance, the requirement dates of the dependent requirements for these components are scheduled at each of the operation start dates.
  • When a customer order is created for the finished product, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.

Answer : In multi-level backward scheduling, dependent requirements are triggered at the start date for the higher-level assembly.

Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)


Options are :

  • Long-term planning generally is operational planning of important components.
  • A planning scenario must be released to use it in long-term planning. (Correct)
  • Reorder point planned materials can be included in long-term planning. (Correct)
  • In case of external procurement, long-term planning creates purchase requisitions.

Answer : A planning scenario must be released to use it in long-term planning. Reorder point planned materials can be included in long-term planning.

The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts or issues are taken into account: planned orders, purchase orders, production orders, reservations, dependent requirements. When the production and/or process order is released, only the stock that is currently freely usable should be taken into consideration. How can you fulfill this request?


Options are :

  • Activate the freely usable stock in the scope of check.
  • Differentiated assignment of two different checking rules in check control. (Correct)
  • Enter an appropriate availability checking group in the material master.
  • Enter an appropriate availability checking rule in the order type.

Answer : Differentiated assignment of two different checking rules in check control.

Which of the following are properties of ECC Multi-Site Planning? (Choose two.)


Options are :

  • The use of scope of planning (cross-plant total planning) is mandatory for Multi-Site Planning.
  • When using two-step stock transport order with delivery, the receiving plant is defined as a customer. (Correct)
  • Both withdrawal from alternative plant and withdrawal from another plant are defined via special procurement keys. (Correct)
  • When using one-step stock transfer posting, transfer stock is created in the receiving plant.

Answer : When using two-step stock transport order with delivery, the receiving plant is defined as a customer. Both withdrawal from alternative plant and withdrawal from another plant are defined via special procurement keys.

Which of the following statements about the planning functions available in SAP ECC are true? (Choose two.)


Options are :

  • Material requirements planning (MRP) does not include automatic capacity leveling. (Correct)
  • In demand management (DM) material shortage situations are identified and given requirement coverage elements.
  • Long-term planning (LTP) is a long-term form of forecast planning.
  • Master production scheduling (MPS) refers to preferred planning of important materials. (Correct)

Answer : Material requirements planning (MRP) does not include automatic capacity leveling. Master production scheduling (MPS) refers to preferred planning of important materials.

A final assembly process takes place at three work centers, one after the other. The routing, which consists of three associated operations (10, 20 and 30), plans for a specific BOM component to be installed during operation 30 and not before. The component should therefore only be requested at the start of operation 30. What sequence do you follow in master data maintenance in SAP ECC to make this component available in line with operations during final assembly?


Options are :

  • 1. Create routing 2. Create work centers 3. Create BOM 4. Carry out component assignment in BOM or routing
  • 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in work center
  • 1. Create work centers 2. Create routing 3. Create BOM 4. Carry out component assignment in work center
  • 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in BOM or routing (Correct)

Answer : 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in BOM or routing

Which of the following elements do you have to prepare for costing of a production order to function without errors? (Choose three.)


Options are :

  • Enter formulas for costing in the work center. (Correct)
  • Use an operation control key with the indicator costing-relevant. (Correct)
  • Assign costing variants to order type. (Correct)
  • Propose a standard text key in work center.

Answer : Enter formulas for costing in the work center. Use an operation control key with the indicator costing-relevant. Assign costing variants to order type.

Which of the following structural elements does a process order have? (Choose three.)


Options are :

  • Phases (Correct)
  • Item data
  • Relationships (Correct)
  • Characteristic-based process instructions (Correct)
  • Parallel sequences

Answer : Phases Relationships Characteristic-based process instructions

In your company planning strategies are used in the SAP-ECC demand management that are based on consumption. Which of the following statements about consumption is true? (Choose two.)


Options are :

  • Consumption always takes place on the material level between the planned independent requirements and the planned orders.
  • A consumption situation is dynamic and is always restructured with the planning run.
  • Consumption can also take place between order reservations and planned independent requirements, depending on the strategy. (Correct)
  • The consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group. (Correct)

Answer : Consumption can also take place between order reservations and planned independent requirements, depending on the strategy. The consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.

Which objects can you use in the production order for a material component to propose the storage location in its reservation? (Choose three.)


Options are :

  • Routing
  • Work center (Correct)
  • Production version (Correct)
  • Material master (component) (Correct)

Answer : Work center Production version Material master (component)

Which of the following situations occur when a production order is set to Technically Complete (TECO)? (Choose three.)


Options are :

  • Capacity requirements are deleted. (Correct)
  • The order and its operations receive the system status Locked (LKD).
  • Reservations are deleted. (Correct)
  • The order is no longer relevant for Material Requirements Planning. (Correct)

Answer : Capacity requirements are deleted. Reservations are deleted. The order is no longer relevant for Material Requirements Planning.

In SAP ECC, you want to map an in-house production process for general warehouse production. The fields in the area of the lot size-dependent in-house production time are to be populated when the material master for the final product is created. These fields can be maintained by updating from the scheduling result for the associated routing. You now think that there could be significant changes to the production times in the routing and decide against updating the material master. What problem could this lead to?


Options are :

  • Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
  • Requirements planning runs up against an exception message in basic dates scheduling because the material master parameters do not match the scheduling result from the routing.
  • In the course of basic dates scheduling with requirements planning, dependent requirements request the components from the bill of materials at the wrong times. (Correct)
  • Lead time scheduling, which occurs by the time that a planned order is converted into a production order (at the latest), cannot take place on the basis of incorrect basic dates.

Answer : In the course of basic dates scheduling with requirements planning, dependent requirements request the components from the bill of materials at the wrong times.

An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default. However, some materials are to be given a different planning horizon. What procedure would you recommend to the project team for setting the planning horizon on the system side?


Options are :

  • The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings.
  • The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.
  • The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question. (Correct)
  • The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.

Answer : The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.

Which of the following statements about ATP (Available To Promise) checks for material components are correct? (Choose two.)


Options are :

  • ATP checks can be carried out automatically when releasing a production order. (Correct)
  • ATP checks can be adjusted to also consider future requirements and receipts. (Correct)
  • ATP checks are automatically performed during MRP (Material Requirements Planning) runs.
  • ATP checks are used to evaluate the free capacity on a certain work center.

Answer : ATP checks can be carried out automatically when releasing a production order. ATP checks can be adjusted to also consider future requirements and receipts.

Which types of objects can be changed with Engineering Change Management? (Choose three.)


Options are :

  • Work Center
  • Bill of Materials (Correct)
  • Task List (Correct)
  • Material Master (Correct)

Answer : Bill of Materials Task List Material Master

In SAP ECC, you calculate the standard available capacity for a work center capacity with the following data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization: 80%, overload. 110%, number of individual capacities: 1. How large is the standard available capacity?


Options are :

  • 6.16 hours
  • 8 hours
  • 7 hours
  • 5.6 hours (Correct)

Answer : 5.6 hours

In the task list, there is the possibility to work with suboperations. What can you do in more detail by using suboperations? (Choose two.)


Options are :

  • Material component allocation
  • Scheduling
  • Capacity planning (Correct)
  • Costing (Correct)

Answer : Capacity planning Costing

When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three.)


Options are :

  • Standard value from operation in task list (Correct)
  • User-defined field from operation in task list (Correct)
  • General values from work scheduling view in the material master
  • General operation values in task list (Correct)

Answer : Standard value from operation in task list User-defined field from operation in task list General operation values in task list

Which functions lead to a reduction in the capacity requirement for an individual operation at a work center? (Choose three.)


Options are :

  • Setting the status technically complete (TECO) (Correct)
  • Rescheduling the operation
  • Confirming the operation (Correct)
  • Posting the goods receipt for the production order
  • Reducing the order quantity (Correct)

Answer : Setting the status technically complete (TECO) Confirming the operation Reducing the order quantity

With which functions of the process order can you fulfill the requirements of the Good Manufacturing Practices (GMP) standard? (Choose three.)


Options are :

  • Material identification and reconciliation (Correct)
  • Digital signature (Correct)
  • Availability check
  • Batch record (Correct)

Answer : Material identification and reconciliation Digital signature Batch record

Which of the following statements about the SAP Solution Manager listed is correct?


Options are :

  • Solution Manager is an add-on industry solution.
  • Solution Manager is part of the SAP ECC System.
  • Solution Manager is a stand-alone system that communicates with other systems in a system landscape. (Correct)
  • Solution Manager is a satellite system in a system landscape.

Answer : Solution Manager is a stand-alone system that communicates with other systems in a system landscape.

In the SAP ECC system, a material is produced with the help of production orders. Though originally used for rate-based planning only, the planning table is to be used to plan this material. On the initial screen of the planning table, you select this material and then receive a message informing you that you cannot use the planning table for this material. Which one of the following reasons for this message applies?


Options are :

  • There is no valid production version for this material. (Correct)
  • There are no requirements present.
  • There are no planned orders or production orders present.
  • The series production indicator has not been set.

Answer : There is no valid production version for this material.