JK0-017 CompTIA E2C Project+ Certification Practice Exam Set 10

In which management style would the project manager make themselves available by being visible, interacting with the project team, and hosting an "open door" policy?   


Options are :

  • Dictatorship
  • Active observation
  • Management by walking around
  • Autocratic

Answer : Management by walking around

JK0-015 CompTIA E2C Security+ 2008 Edition Practice Exam Set 2

Project XYZ promises to be worth $587,000 in three years. Assuming that the rate of return is currently six percent, what is the minimum amount of funds that Project XYZ may cost and still be  initiated if the organization wants to earn at least $75,000 on the project? 


Options are :

  • $417,863
  • This answer depends on the cost of the project resources.
  • $492,863
  • $512,000

Answer : $417,863

What type of project manager review requires the project sponsor, functional managers, other project managers, and the project team to review the performance of the project manager? 


Options are :

  • SWOT analysis
  • Peer review
  • 360-degree appraisal
  • Project closure review

Answer : 360-degree appraisal

What term is assigned to the completion of a project that allows the next phase of a project to begin?   


Options are :

  • Milestones
  • Step funding
  • Project phase closure
  • Phase gate

Answer : Phase gate

CompTIA HT0-201 DHTI+ Certification Practice Exam Set 3

What communications theory suggests that the language people speak affects the way they think and process information? 


Options are :

  • Halo Effect
  • Sapir-Whorf Hypothesis
  • Ethnocentrism
  • Parkinson's Law

Answer : Sapir-Whorf Hypothesis

Robert is the project manager of the NHH Project and is working with his project team to create the WBS for his organization. He has a project scope statement that needs to be broken down into smaller, more manageable components. He would like to organize the components by project phase to help organize the deliverables created in each phase of the project. What is the tool and technique called that breaks down the project scope into the WBS?   


Options are :

  • Functional analysis
  • Subdivision
  • Requirements breakdown
  • Decomposition

Answer : Decomposition

Which of the following formulas is used to calculate schedule variance percent (SV %)? 


Options are :

  • SV % = Schedule Variance (SV) / Planned Value (PV)
  • SV % = Schedule Variance (SV) / Earned Value (EV)
  • SV % = Planned Value (EV) / Earned Value (PV)
  • SV % = Earned Value (EV) / Planned Value (PV)

Answer : SV % = Schedule Variance (SV) / Earned Value (EV)

JK0-016 CompTIA Network+ 2009 Edition Practice Exam Set 5

You are the project manager of the NGH Project for your organization. A stakeholder has requested a significant change to the project that will cause an increase in the project budget by fifteen percent and will add six months to the project schedule. You do not have the power as a project manager to make this type of change decision. To whom should you forward the request?   


Options are :

  • Project sponsor
  • Change control board
  • Project portfolio management board
  • Project stakeholder committee

Answer : Change control board

You are the project manager for the GHY Organization. A stakeholder has presented a change to your project that will cause the project scope to increase considerably. You are considering the change for approval and you need to review the impact of the change on all areas of the project.What change control system component is responsible for guiding the review of the impact of all changes on the project management knowledge areas?   


Options are :

  • Change control system
  • Configuration management
  • Integrated change control
  • Scope change control system

Answer : Integrated change control

Which of the following refers to uncontrolled changes in a project's scope? 


Options are :

  • Scope creep
  • Project scope statement
  • Control scope
  • Scope extension

Answer : Scope creep

CT0-101 Convergence+ Certification Practice Exam Set 7

Which of the following provides a method to track project progress during project execution against what was planned? 


Options are :

  • Benefit-cost ratio
  • Team members profile
  • Detailed project budget
  • Schedule baseline

Answer : Schedule baseline

You are the project manager for your organization. Your project has reached the end of a project phase and you believe you're ready to move onto the next phase of the project. Management, however, reviews your project team's work to date and they don't think the deliverables your team has created are accurate. They want you to instruct your project team to fix the problem before the project can move forward. What must happen once the project team completes the corrective action? 


Options are :

  • Quality control
  • Defect repair review validation
  • Scope verification
  • Then the project can move forward

Answer : Defect repair review validation

You are the project manager for your organization; you're currently managing a project to create a Web-based ordering form for your company's clients. The project will allow clients to place their orders through the Website at any time of day regardless of your company's operating hours.Larry, the CIO of the company, demands that you add some extra features to the Website. Larry is not the project sponsor but he is a key stakeholder in this project. What should you do with Larry's request for the additional features? 


Options are :

  • Implement the features as Larry has requested.
  • Determine the cost and schedule impact of the change request
  • Send Larry to the project sponsor for approval on the requested features
  • Complete and submit a change request form

Answer : Complete and submit a change request form

Your project will use labor represented by a union. The union has several requirements about the utilization of employees that they represent and they must approve the project plan that deals with their members. Which part of the project management plan will define when specific union members will be unavailable to work on the project? 


Options are :

  • Communications management plan
  • Resource management plan
  • Resource calendar
  • Staffing management plan

Answer : Resource calendar

You are the project manager for your organization. A vendor has told you that the cost of the resources you'll be implementi