JK0-017 CompTIA E2C Project+ Certification Practice Exam Set 1

Which of the following actions would require a formal project closure? (Select TWO).A. The project is delayed indefinitely because a required vendor part cannot be delivered.B. The project is producing a product that is no longer compliant with new Federal regulations.C. The project work is completed.D. The project has run out of money.E. The project sponsor has become disinterested in the project.


Options are :

  • C,D
  • D,E
  • B,C (Correct)
  • A,B

Answer : B,C

CompTIA JK0-015 E2C Security+ Certification Practice Test Set 12

Which of the following would MOST likely be reviewed during a project kick-off meeting?


Options are :

  • Work Breakdown Structure (WBS)
  • Change requests (Correct)
  • Risk register
  • Responsibility assignment matrix

Answer : Change requests

Which of the following quality control tools illustrates the various factors that may be linked to potential problems or effects?


Options are :

  • Histogram
  • Ishikawa diagram (Correct)
  • Run chart
  • NONE
  • Scatter diagram

Answer : Ishikawa diagram

The project kick-off meeting is held:


Options are :

  • at the end of the planning process.
  • after the post review meeting.
  • during the initiating process. (Correct)
  • before getting a signed project charter.

Answer : during the initiating process.

JK0-017 CompTIA E2C Project+ Certification Practice Exam Set 2

The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result?


Options are :

  • The project will be behind schedule and over-budget.
  • The project will be on schedule but over-budget. (Correct)
  • The project will be on schedule and on-budget.
  • The project will be behind schedule and on-budget.

Answer : The project will be on schedule but over-budget.

Which of the following elements would be needed to prepare an effective project scope document?


Options are :

  • An approved risk assessment document
  • An approved project milestone schedule
  • An approved project charter (Correct)
  • A responsibility assignment matrix

Answer : An approved project charter

In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?


Options are :

  • Benchmarking
  • Quality metrics (Correct)
  • Process Improvement
  • Cost-benefit analysis

Answer : Quality metrics

SY0-401 CompTIA Security+ Certification Practice Exam Set 4

All of the following are considered part of the risk management plan EXCEPT the risk:


Options are :

  • register (Correct)
  • matrix,
  • assessment
  • baseline

Answer : register

Which of the following is the BEST point for a project manager to join a project?


Options are :

  • Project planning
  • Project pre-planning (Correct)
  • Project executing
  • Project initiation

Answer : Project pre-planning

In which of the following situations would a risk be placed in the upper right quadrant of a risk matrix?


Options are :

  • The team identified a risk to have a high probability of occurrence and a high impact on project success. (Correct)
  • The team identified a risk to have a medium probability of occurrence and a high impact on project success
  • The team identified a risk to have a high probability of occurrence and a medium impact on project success.
  • The team identified a risk to have a low probability of occurrence and a high impact on project success.

Answer : The team identified a risk to have a high probability of occurrence and a high impact on project success.

SK0-004 CompTIA Server+ Certification Practice Exam Set 3

The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped. Which of the following should the project manager do?


Options are :

  • Proceed with the release and document the adjustment in the change log.
  • Delay the release until the component is tested.
  • Schedule a meeting with the stakeholders to review the impact. (Correct)
  • Proceed with the release and tell the SME the component will be added in a special release.

Answer : Schedule a meeting with the stakeholders to review the impact.

An ongoing project requires several parts manufactured at an outside vendor. If the vendor hassufficient quantity and can still ship today, the parts should be received in five days; although in most cases an order of this size requires ten days. Allowing for an upcoming holiday and some potential bad weather the shipment could take up to twenty-one days. Using the PERT method,which of the following is the correct time estimate for a parts delivery?


Options are :

  • 36 days
  • 10 days
  • 21 days
  • 11 days (Correct)

Answer : 11 days

Which of the following is the purpose of a Pareto diagram?


Options are :

  • To create the process that will complete the project
  • To show the sequence in which work will be performed
  • To determine the critical path
  • To direct team efforts to the areas that will have the most impact (Correct)

Answer : To direct team efforts to the areas that will have the most impact

CL0-001 CompTIA Cloud Essentials Practice Test Set 7

To ensure that project status meetings are effective and productive, the project manager should:


Options are :

  • publish an agenda prior to the meeting.
  • invite only team members who have an immediate task on the project.
  • hold only one meeting per week.
  • invite all stakeholders and the sponsor to every meeting. (Correct)

Answer : invite all stakeholders and the sponsor to every meeting.

Which of the following is a representation of the difference between the planned costs of work completed compared to the actual cost at a point in time?


Options are :

  • CV
  • AC
  • CPI (Correct)
  • EV

Answer : CPI

The purpose of the WBS is to:


Options are :

  • determine work packages. (Correct)
  • manage change requests.
  • aid in version control.
  • maintain standards compliance.

Answer : determine work packages.

SY0-401 CompTIA Security+ Certification Practice Exam Set 8

Several stakeholders and the project sponsor have indicated that they are not being supplied with project updates. As the project manager, which of the following should be done to address the situation?


Options are :

  • Send emails to everyone on the project team.
  • Refer to the communications plan (Correct)
  • Create communication roles template.
  • Speak in-depth personally to each stakeholder.

Answer : Refer to the communications plan

After a change control Board meeting, which of the following actions should the project manager do NEXT?


Options are :

  • Update the project scope statement.
  • Review the impact of proposed change
  • Notify the requester of the verdict.
  • Document the specific change request. (Correct)

Answer : Document the specific change request.

A project manager wants to have complete control of the project team members. Which of the following organization structures would allow for this?


Options are :

  • Strong matrix
  • Projectized (Correct)
  • Functional
  • Balanced matrix

Answer : Projectized

JK0-016 CompTIA Network+ 2009 Edition Practice Exam Set 3

Which of the following tools is the BEST to measure data organized in time sequence?


Options are :

  • Histogram
  • Run chart
  • Ishikawa diagram
  • Pareto chart (Correct)

Answer : Pareto chart

Which of the following components is included in a transition plan?A. OwnershipB. Quality metricsC. Project budgetD. Quality baseline


Options are :

  • A,B
  • A,D (Correct)
  • B,C
  • C,D

Answer : A,D

Which of the following describes a work breakdown structure (WBS) dictionary?


Options are :

  • An alphabetical listing of WBS components detailing their associated project schedule dependencies
  • A supporting document that provides more detail for the WBS components. (Correct)
  • An organizational reference defining how WBS levels must be decomposed.
  • A high level requirements document used to create the WBS.

Answer : A supporting document that provides more detail for the WBS components.

SY0-401 CompTIA Security+ Certification Practice Exam Set 5

Before a change request is presented to the change control board, which of the following should the project manager do?


Options are :

  • Suggest the hoard study the cost of the change
  • Review the change request with the project sponsor (Correct)
  • Evaluate the affect on all other parts of the project.
  • Request team member input on the value of the change

Answer : Review the change request with the project sponsor

Which of the following are characteristics of a projects critical path? (Select TWO).A. The critical path is the longest duration.B. The critical path has the least amount of resources.C. The critical path is the shortest durationD. The critical path has less than or equal to zero float time.E. The critical path has a greater than zero float time.


Options are :

  • B,C
  • A,D (Correct)
  • A,B
  • D,E

Answer : A,D

The project scope document should outline which of the following project items? (Select TWO).A. ServicesB. Lessons learnedC. ProductsD. Schedule baselinesE. Resource availability


Options are :

  • A,B
  • B,C
  • D,E (Correct)
  • C,D

Answer : D,E

SY0-401 CompTIA Security+ Certification Practice Exam Set 5

Which of the following is created during the initiation phase?


Options are :

  • Project charter (Correct)
  • Statement of Work (SOW)
  • Work Breakdown Structure (WBS)
  • Project scope statement

Answer : Project charter

Which of the following would be the MOST important objective of a kick-off meeting? (Select TWO).A. To educate team members on what will be expectedB. To give official notification for the projectC. To inform the project sponsor on what will be expectedD. To create a work breakdown structure (WBS)E. To develop the statement of work (SOW)


Options are :

  • C,D
  • A,C (Correct)
  • A,B
  • D,E

Answer : A,C

A project manager was asked to complete a project three weeks early and not crash the project.Which of the following should be done?


Options are :

  • Continue to work and complete the project as soon as possible
  • Have the team work overtime and give them time off later to save the budget
  • Move some of the task to another release
  • Review the plan with the team and develop a way to reduce the time (Correct)

Answer : Review the plan with the team and develop a way to reduce the time

CompTIA Cloud+ Certification

A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?


Options are :

  • Document the risk in the risk register, accept it and refer to the agreed vendor contracts for methods of raising the issue with the vendor. (Correct)
  • Contact the vendor and request a thorough review of the product architecture.
  • Issue a change request to the change control board to select a different vendor from the qualified sellers list and request early termination of the current vendor contract.
  • Call a project team meeting to discuss the risk and communicate the issue directly with the project sponsor.

Answer : Document the risk in the risk register, accept it and refer to the agreed vendor contracts for methods of raising the issue with the vendor.

A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager should update which of the following?


Options are :

  • Risk register
  • Issues log (Correct)
  • Work Breakdown Structure (WBS)
  • Change control form

Answer : Issues log