Which of the following does not describe a constraint?



Options are :

  • C. Project team actions are restricted.
  • B. It may regard budget, resources, or schedule.
  • A. Project team actions are dictated.
  • D. Project situations are believed to be true.

Answer : D. Project situations are believed to be true.

You are in the process of determining the cost baseline. All of the following are used in the cost baseline except for which one?



Options are :

  • B. Chart of accounts
  • D. Materials and equipment estimates
  • A. Management reserves
  • C. Human resource cost estimates

Answer : A. Management reserves

All of the following are considered stakeholder communication requirements except for which one?



Options are :

  • A. Frequency
  • B. Distribution of printed media
  • D. Tailor communication style to stakeholder needs
  • C. Confidentiality constraints

Answer : B. Distribution of printed media

JK0-019 CompTIA E2C Network + Certification Exam Set 12

You’re working on a project that you and your team have estimated takes 15 business days to complete. Your team does not work on Saturday, Sunday, or holidays. Given the work calendar shown here and a start date of Tuesday, November 1, what is the scheduled completion date for this task?



Options are :

  • A. 21
  • B. 15
  • C. 22
  • D. 23

Answer : C. 22

Which element is not a component or function of the scope management plan?



Options are :

  • A. Describes the deliverables acceptance criteria
  • D. Describes the procedures for preparing the WBS
  • B. Describes how scope changes will be handled
  • C. Describes the procedures for preparing the scope statement

Answer : A. Describes the deliverables acceptance criteria