CompTIA JK0-017 E2C Project+ Certification Practice Exam Set 12

A project manager receives a request for a minor change to one of the deliverables. Which of the following documents would MOST likely be impacted?


Options are :

  • Project charter
  • Work Breakdown Structure (WBS)
  • Quality plan
  • Communication plan

Answer : Work Breakdown Structure (WBS)

A project sponsor has requested that the training he delivered in parallel to a project's implementation in order to ensure the project is delivered on schedule. If accepted, this request is an example of:


Options are :

  • crashing.
  • fast-tracking.
  • rolling wave planning.
  • the critical path method.

Answer : fast-tracking.

CompTIA SY0-401 Security Certification Practice Exam Set 4

In which of the following organization types is it LEAST likely that a conflict regarding competing demands for resources would take place?


Options are :

  • Projectized
  • Balanced Matrix
  • Functional
  • Weak Matrix

Answer : Projectized

Two of the stakeholders cannot agree on the project timeline or budget. The project is critical to the success of the company. Which of the following actions should the project manager take NEXT?


Options are :

  • Document the points of agreement and create the timeline and budget based upon the expectations of the majority of the stakeholders.
  • Invite all of the stakeholders to a meeting to discuss project requirements
  • Modify the project scope to bring it into alignment with the stakeholders’ expectations
  • Inform the stakeholders that the project will be cancelled if they cannot agree.

Answer : Document the points of agreement and create the timeline and budget based upon the expectations of the majority of the stakeholders.

The greatest amount of conflict occurs in which of the following team development stages?


Options are :

  • Forming
  • Performing
  • Norming
  • Storming

Answer : Storming

Which of the following is a characteristic of a project charter?


Options are :

  • Provides low-level requirements for the project.
  • Issued by the project manager with support from the project sponsor.
  • Formally recognizes the existence or establishment of the project.
  • Links the project to the on-going work of the organization through a business plan.

Answer : Formally recognizes the existence or establishment of the project.

ASPI of 1.1 means that the project Is:


Options are :

  • under-budget.
  • over-budget.
  • ahead of schedule
  • behind schedule

Answer : under-budget.

A project manager sits down to discuss with team members the strengths and weaknesses of a project. This Is BEST described as:


Options are :

  • post-project review.
  • human resource management.
  • work performance review.
  • managing stakeholder expectations.

Answer : post-project review.

SY0-401 CompTIA Security+ Certification Practice Exam Set 8

Which of the following is the BEST reason to review the historical information from a similar project?


Options are :

  • To get a good idea of the writing style of the project manager
  • To get an understanding of the document approval process.
  • To get an understanding of the number of managers within the organization.
  • To get an understanding of the resources needed to complete the projec

Answer : To get an understanding of the resources needed to complete the projec

Which of the following skills would be the MOST useful in assembling an effective project team in a functional organization?


Options are :

  • Estimating
  • Negotiation
  • Compromising
  • Padding

Answer : Negotiation

Which of the following would be considered a valid strategy in response to an adverse risk?


Options are :

  • Exploit
  • Mitigate
  • Monitor
  • Enhance

Answer : Mitigate

Before the execution phase begins, who is in control of the project?


Options are :

  • Project coordinator
  • Project manager
  • Program manager
  • Project sponsor

Answer : Project sponsor

Which of the following BEST describes the chart of accounts?


Options are :

  • The numbering system used to identify each activity on the work breakdown structure
  • The numbering system used to decompose project activities into sub-project activities.
  • The numbering system used to track project costs depending on their activity type.
  • The numbering system used to monitor the quality measurements during the life of the project

Answer : The numbering system used to track project costs depending on their activity type.

Whose approval should be obtained before modifying the scope of a project?


Options are :

  • Executive management team
  • Project team
  • Stakeholders
  • Change control board

Answer : Change control board

JK0-015 CompTIA E2C Security+ 2008 Edition Practice Exam Set 5

Which of the following correctly identifies the application of a projects quality management plan?


Options are :

  • Quality assurance and quality control both occur in the monitoring / controlling phase.
  • Quality assurance occurs in the execution phase, quality control occurs in the monitoring / controlling phase.
  • Quality assurance and quality control both occur in the execution phase.
  • Quality control occurs in the execution phase, quality assurance occurs in the monitoring /controlling phase.

Answer : Quality assurance and quality control both occur in the monitoring / controlling phase.

Which of the following is the correct progression of the project life cycle?


Options are :

  • Planning, Initiating, monitoring / controlling, executing, closing
  • Initiating, planning, executing, monitoring / controlling, closing
  • Planning, Initiating, executing, monitoring / controlling, closing
  • Initiating, planning, monitoring / controlling, executing, closing

Answer : Planning, Initiating, executing, monitoring / controlling, closing

Which of the following sequences represents the correct order for implementing a change request?


Options are :

  • Change is requested, change implemented, change impact analyzed, change request submitted to board, change request approved
  • Change is requested, change request submitted to board, change request approved, change implemented, change impact analyzed.
  • Change is requested, change impact analyzed, change request submitted to board, change request approved, change implemented.
  • Change is requested, change request submitted to board, change impact analyzed, change request approved, change implemented.

Answer : Change is requested, change impact analyzed, change request submitted to board, change request approved, change implemented.

Which of the following documents would a project manager review to determine all the Identified risks on a project?


Options are :

  • Risk response
  • Risk register
  • Risk matrix
  • Risk baseline

Answer : Risk register

When does stakeholder identification initially take place?


Options are :

  • Once the project planning phase is entered
  • Once the project charter document is created
  • When the organizational structure is determined
  • When documenting the project objectives

Answer : Once the project charter document is created

A major change has been approved by the change control hoard and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?


Options are :

  • Distribute details of the change per the communication plan, and implement according to the change control process.
  • Identify the team member responsible for implementing the change and direct the team member to inform the rest of the project team of the date and time of implementation.
  • Ask the change control board to schedule the change, and when scheduled, identify the individual team member responsible for implementing it.
  • Email the project team, identifying the team member responsible for implementing the change, and then schedule it with the appropriate team

Answer : Distribute details of the change per the communication plan, and implement according to the change control process.

CompTIA Security+ Cert. (SY0-501): Practice Tests 2019 Set 4

Monitoring and controlling project work is a control process function that spans from:


Options are :

  • project kickoff to the project plan generation.
  • the creation of the project work plan to the completion of the statement of work (SOW)
  • project kickoff to the project completion, including documentation of lessons learned.
  • the creation of the project work plan to the completion of the work breakdown structure (WBS).

Answer : project kickoff to the project completion, including documentation of lessons learned.

Which of the following are components of an internal / external communication plan? (Select TWO).


Options are :

  • Communication frequency
  • Stakeholders list
  • Technology requirements
  • Communication budget
  • Distribution list

Answer : Communication frequency Technology requirements

Which of the following documents would be generated to solicit bids from outside vendors?


Options are :

  • SOW
  • RFP
  • WBS
  • PERT

Answer : RFP

During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project manager MOST likely use to deliver the project on time?


Options are :

  • Rolling wave planning
  • Bottom-up estimating
  • Resource leveling
  • Fast tracking

Answer : Fast tracking

The work Breakdown structure (WBS) dictionary contains which of the following elements? (Select THREE).


Options are :

  • Identification of stakeholders
  • Risk response strategies
  • Required resources
  • Quality control processes
  • Description of work processes and procedures
  • Estimated calendar time of activities

Answer : Required resources Description of work processes and procedures Estimated calendar time of activities

Information regarding training, extended support, and warranties are detailed in the:


Options are :

  • risk register
  • project scope statement.
  • work Breakdown structure (WBS).
  • transition plan

Answer : project scope statement.

220-801 CompTIA A+ Certification Practice Exam Set 10

Which of the following is a use for a Pareto diagram?


Options are :

  • In procurement management to evaluate vendor proposals.
  • In cost management to determine actual versus expected project costs.
  • In risk management to assess potential project risk occurrences.
  • In quality management to Identify and prioritize problem areas.

Answer : In quality management to Identify and prioritize problem areas.

Which of the following components are included in a communication plan? (Select TWO).


Options are :

  • Frequency
  • Work breakdown Structure (WBS)
  • Distribution list
  • Statement of Work (SOW)
  • Risk matrix

Answer : Frequency Distribution list