CompTIA JK0-017 E2C Project+ Certification Practice Exam Set 10

The EV of a particular project is $6 million. The CV is -$340,000. Which of the following can be determined from this information?


Options are :

  • The AC is less than the EV.
  • The project costs are currently under-budget.
  • The project costs are currently over-budget.
  • The EV Is higher than the AC.

Answer : The project costs are currently over-budget.

Which of the following documents should be used to present the length of identified tasks?


Options are :

  • PERT
  • Key event/activity list
  • Gantt
  • CPM

Answer : CPM

CompTIA 220-801 A+ Advanced Certification Practice Exam Set 5

Which of the following tools is the BEST to measure data organized in time sequence?


Options are :

  • Run chart
  • Pareto chart
  • Histogram
  • Ishikawa diagram

Answer : Pareto chart

Which of the following is the purpose of a Pareto diagram?


Options are :

  • To show the sequence in which work will be performed
  • To direct team efforts to the areas that will have the most impact
  • To create the process that will complete the project
  • To determine the critical path

Answer : To direct team efforts to the areas that will have the most impact

Quality assurance is performed during which phase of a project?


Options are :

  • During the execution phase
  • During both controlling and execution phase
  • During the planning phase
  • During the controlling phase

Answer : During the execution phase

A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?


Options are :

  • Review the plan with the team and develop a way to reduce the time.
  • Continue to work and complete the project as soon as possible.
  • Have the team work overtime and give them time off later to save the budget.
  • Move some of the task to another release.

Answer : Review the plan with the team and develop a way to reduce the time.

Which of the following activities occur during a project kick-off meeting? (Select THREE).


Options are :

  • Review of the risk management pla
  • Review of the stakeholder expectations
  • Review of the change management procedures
  • Review of the project goals and objectives
  • Review of the roles and responsibilities
  • Review of the work breakdown structure (WBS)

Answer : Review of the stakeholder expectations Review of the change management procedures Review of the project goals and objectives

To ensure that project status meetings are effective and productive, the project manager should:


Options are :

  • invite all stakeholders and the sponsor to every meeting.
  • invite only team members who have an immediate task on the project
  • publish an agenda prior to the meeting.
  • hold only one meeting per week.

Answer : invite all stakeholders and the sponsor to every meeting.

CompTIA CySA+ Set 9

The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result?


Options are :

  • The project will be behind schedule and on-budget.
  • The project will be behind schedule and over-budget.
  • The project will be on schedule and on-budget.
  • The project will be on schedule but over-budget.

Answer : The project will be on schedule but over-budget.

The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped. Which of the following should the project manager do?


Options are :

  • Proceed with the release and tell the SME the component will be added in a special release.
  • Delay the release until the component is tested.
  • Schedule a meeting with the stakeholders to review the impact.
  • Proceed with the release and document the adjustment in the change log.

Answer : Schedule a meeting with the stakeholders to review the impact.

In working with the risk management plan all of the following are ways of dealing with opportunities


Options are :

  • enhancing.
  • sharing.
  • mitigating
  • exploiting.

Answer : enhancing.

Project Information is received by the project manager in a number of different formats from team members. Which of the following would be the BEST way for the project manager to standardize the Information?


Options are :

  • Create project templates.
  • Require supervisor approval of documentation.
  • Use document version control
  • Implement organizational format standards.

Answer : Create project templates.

Which of the following is created during the initiation phase?


Options are :

  • Project charter
  • Work Breakdown Structure (WBS)
  • Project scope statement
  • Statement of Work (SOW)

Answer : Project charter

A project manager is presented with a change request for an ongoing project. Which of the following would be the FIRST action?


Options are :

  • Perform an impact analysis.
  • Change the project scope to reflect the change request.
  • Organize a stakeholder meeting to review the changes.
  • Update the project plan to accommodate the changes

Answer : Perform an impact analysis.

CompTIA JK0-022 E2C Security+ Threats & Vulnerabilities Exam Set 3

A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?


Options are :

  • Document the risk in the risk register, accept it and refer to the agreed vendor contracts for methods of raising the issue with the vendor.
  • Call a project team meeting to discuss the risk and communicate the issue directly with the project sponsor.
  • Issue a change request to the change control board to select a different vendor from the qualified sellers list and request early termination of the current vendor contract.
  • Contact the vendor and request a thorough review of the product architecture.

Answer : Document the risk in the risk register, accept it and refer to the agreed vendor contracts for methods of raising the issue with the vendor.

Which of the following is the BEST point for a project manager to join a project?


Options are :

  • Project planning
  • Project executing
  • Project pre-planning
  • Project initiation

Answer : Project pre-planning

In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?


Options are :

  • Quality metrics
  • Benchmarking
  • Process Improvement
  • Cost-benefit analysis

Answer : Quality metrics

Which of the following would be included in a project scope document? (Select THREE).


Options are :

  • Project constraints
  • Work Breakdown Structure (WBS)
  • Project roles and responsibilities
  • Detailed project objectives
  • Key Performance Indicators (KPIs)
  • Gantt chart

Answer : Project roles and responsibilities Detailed project objectives Key Performance Indicators (KPIs)

All of the following are considered part of the risk management plan EXCEPT the risk:


Options are :

  • register
  • baseline
  • matrix,
  • assessment

Answer : register

In which of the following situations would a risk be placed in the upper right quadrant of a risk matrix?


Options are :

  • The team identified a risk to have a medium probability of occurrence and a high impact on project success.
  • The team identified a risk to have a high probability of occurrence and a high impact on project success.
  • The team identified a risk to have a high probability of occurrence and a medium impact on project success.
  • The team identified a risk to have a low probability of occurrence and a high impact on project success.

Answer : The team identified a risk to have a high probability of occurrence and a high impact on project success.

220-701 A+ Essentials Certification Practice Exam Set 5

The lessons-learned activity and formal acceptance documentation form part of which of the following process groups?


Options are :

  • Closing
  • Planning
  • Monitoring/Controlling
  • Executing

Answer : Closing

Which of the following are schedule compression techniques? (Select TWO)


Options are :

  • Crashing
  • Fast tracking
  • PERT analysis
  • Critical Path Method (CPM)
  • Schedule network analysis

Answer : Fast tracking Schedule network analysis

Which of the following are created using information contained in the work breakdown structure (WBS)? (Select TWO).


Options are :

  • Project activity estimates
  • Project resource estimates
  • Project charter
  • Project statement of work
  • Project scope statement

Answer : Project activity estimates Project resource estimates

Which of the following would be the MOST important objective of a kick-off meeting? (Select TWO).


Options are :

  • To educate team members on what will be expected
  • To inform the project sponsor on what will be expected
  • To create a work breakdown structure (WBS)
  • To develop the statement of work (SOW)
  • . To give official notification for the project

Answer : To educate team members on what will be expected To inform the project sponsor on what will be expected

Which of the following is the BEST way for a project manager to conduct a lessons learned session?


Options are :

  • Talk about different conflict resolution techniques that could be used in the future.
  • Talk about specific task failures and who is responsible for the failures.
  • Talk about the project vendor shortcomings and contractual failures.
  • Talk about processes needing improvement versus things that went wrong.

Answer : Talk about different conflict resolution techniques that could be used in the future.

Before a change request is presented to the change control board, which of the following should the project manager do?


Options are :

  • Review the change request with the project sponsor.
  • Evaluate the affect on all other parts of the project.
  • Request team member input on the value of the change.
  • Suggest the hoard study the cost of the change.

Answer : Review the change request with the project sponsor.

FC0-U51 CompTIA IT Fundamentals Certification Exam Set 5

An ongoing project has a BAC of $450,000, an EV of $210,000 and an AC of $200,000. Which of the following is the CPI of the project?


Options are :

  • 1.1
  • $340,000
  • $20,000
  • 0.91

Answer : 1.1

Which of the following is created as part of the closing phase?


Options are :

  • Quality baseline
  • Activity estimation
  • Feasibility analysis
  • Cost review

Answer : Quality baseline

After a change control Board meeting, which of the following actions should the project manager do NEXT?


Options are :

  • Notify the requester of the verdict
  • . Document the specific change request.
  • Update the project scope statement
  • Review the impact of proposed change

Answer : . Document the specific change request.

A stakeholder asks the project manager to finish a project early. The project manager should ask the stakeholder to FIRST:


Options are :

  • Speak to the project sponsor.
  • Consider how this might Impact the quality of the product.
  • Speak to the other stakeholders to get their opinion.
  • Complete a change request form.

Answer : Consider how this might Impact the quality of the product.