CAP Certified Authorization Professional Practice Exam Set 13

You are the project manager NKQ project for your organization. You have completed during the quantitative risk analysis of this part of the project. What is the only output during the quantitative risk analysis?


Options are :

  • Respond to risks
  • Risk Register Updates
  • None
  • Probability of reaching the objectives of the project
  • The risk reserve contingencies

Answer : Risk Register Updates

Wendy is about to perform a qualitative risk analysis identified risks in her project. Which of the following does not help Wendy to carry out this project management activities?


Options are :

  • register of interest groups
  • The project scope
  • risk register
  • None
  • Risk Management plan

Answer : register of interest groups

CAP Certified Authorization Professional Practice Exam Set 3

Which of the following concepts represent the three basic principles of information security? Each correct answer represents a complete solution. Choose three.


Options are :

  • confidence
  • privacy
  • integrity
  • Availability

Answer : confidence integrity Availability

Jeff, a key player in the project, wants to know how risk exposure is calculated as the risk of events during the quantitative risk analysis. He is concerned about the degree of risk, which is too low to have occurred to his project requirements. How can the risks be calculated?


Options are :

  • risk probability and impact in respect of an event is measured based on research and in-depth analysis.
  • The probability of a risk event risk and impact of the event determines the actual risk expo sure.
  • Exposure to risks in the event of risk is determined by historical information.
  • None
  • The probability of a risk event times the impact of a risk event determines the actual risk.

Answer : The probability of a risk event times the impact of a risk event determines the actual risk.

Which of the following are included in the administrative control? Each correct answer represents a complete solution. Check all that apply.


Options are :

  • Making change control procedures
  • development policy
  • Safety checks-education
  • is monitored by intrusion
  • screening of persons

Answer : Making change control procedures development policy Safety checks-education screening of persons

You work for the project manager BLUEWELL Inc. You are working NGQQ Projectyou're company. You have performed a risk analysis processes for risk events. You and your project team created a risk responses for most of the identified project risks. What followingrisk planning at the techniques you use to transfer the impact of the threat of a third party together with the answers?


Options are :

  • None
  • acceptable risk level
  • Risk mitigation measures
  • transfer of risks
  • risk aversion

Answer : transfer of risks

Which of the following objectives defined by the integrity of C.I.A triad of information security systems? Each correct answer represents a part of the solution. Choose three.


Options are :

  • It prevents deliberate or accidental unauthorized disclosure of the contents of the message
  • It prevents unauthorized modification of data users.
  • It preservesthe the consistency of internal and external data
  • It prevents unauthorized or accidental alteration of the information authorized users.

Answer : It prevents unauthorized modification of data users. It preservesthe the consistency of internal and external data It prevents unauthorized or accidental alteration of the information authorized users.

Which of the following are the tasks performed by the owner of the information classification systems? Each correct answer represents a part of the solution. Choose three


Options are :

  • Restoring to perform data backups whenever you need it.
  • In order for the original determination to determine the security classification of information requires, based on the business of safety data.
  • Transfer the responsibility to safeguard the data custodian duties.
  • Check Land classification assignments from time to time and make changes as the business requirements change

Answer : In order for the original determination to determine the security classification of information requires, based on the business of safety data. Transfer the responsibility to safeguard the data custodian duties. Check Land classification assignments from time to time and make changes as the business requirements change

CAP Certified Authorization Professional Practice Exam Set 4

If the official income in the role of approver. What are the responsibilities of authorizing official? Each correct answer represents a complete solution. Check all that apply.


Options are :

  • The review of safety status reports and critical security document
  • Establishing and implementing the organization's continuous monitoring program
  • In determining the reauthorization requirement and, if necessary, information systems reauthorizing
  • In order to determine the security posture of the organization information system

Answer : The review of safety status reports and critical security document In determining the reauthorization requirement and, if necessary, information systems reauthorizing In order to determine the security posture of the organization information system

Which of the following roles is responsible for review and risk analysis of all contracts on a regular basis?


Options are :

  • Configuration Manager
  • IT Service Continuity Manager
  • Vendor Manager
  • None
  • The Service Catalog Manager

Answer : Vendor Manager

Which of the following is the abbreviation of the RTM?


Options are :

  • Resource tracking method
  • None
  • Resource scheduling method
  • Requirements Testing Matrix
  • traceability Matrix

Answer : traceability Matrix

Sammy is a project manager in his organization. He would like to assess each risk based on the likelihood and impact of time, cost and scale. Harry project team member, has never done this before and think Sammy is wrong to try this approach. Harry says that the accumulative risk rating would be created, not three separate risk scores. Who is right in this situation?


Options are :

  • Sammy is right, because he is the project manager.
  • None
  • Sammy is right, because organizations can create a risk score for each objective of the project
  • Harry is right, the risk probability and impact matrix is the only approach to risk assessment.
  • Harry is right, because the risk probability and impact to keep all the objectives of the project.

Answer : Sammy is right, because organizations can create a risk score for each objective of the project

You work as a project manager BLUEWELL Inc. You are preparing to design a risk responses with the project team. How many risk response types are available, with the risk of an event in the project?


Options are :

  • None
  • Three
  • One
  • four
  • seven

Answer : four

There are seven responses to the risks that the project manager can choose from. That threaten the answer is suitable for both positive and negative risk events


Options are :

  • mitigation
  • Adoption
  • distribution
  • transference
  • None

Answer : Adoption

CAP Certified Authorization Professional Practice Exam Set 8

Courtney is a project manager in his organization. He works as a project team to complete a qualitative risk assessment project. During the analysis, Courtney encourage the project team to begin the risks identified grouping of common causes. What is the main advantage of group risks common reasons during a qualitative risk analysis?


Options are :

  • It can lead to the creation of the risk categories unique for each project
  • None
  • It saves time by collecting resources, such as project team members, to assess risk events.
  • It helps the project team to understand the areas of project most fraught with risks
  • It can lead to developing effective risk solutions.

Answer : It can lead to developing effective risk solutions.

Which of the following processes is a structured approach to transitioning the current state of individuals, teams and organizations to the desired future state?


Options are :

  • Managing change
  • procurement management
  • Risk Management
  • None
  • configuration management

Answer : Managing change

Which of the following is the only output during the qualitative risk analysis?


Options are :

  • Environmental factors
  • Organizational process assets
  • The project management plan
  • None
  • Risk Register Updates

Answer : Risk Register Updates

You are the project manager of greenhouse gas emissions from the project. You are preparing a quantitative during the risk analysis. You are using the organization's funds to help you complete the process during the quantitative risk analysis. Which of the following is not a valid reason to use the funds as part of the organization process during the quantitative risk analysis?


Options are :

  • You are using an organizational process assets risk databases that may be available to industry sources.
  • You are using an organizational process assets to determine the cost of all the risks events thecurrent project.
  • None
  • You are using an organization's process of trials, the property of similar projects Risk Expert Team.
  • You are using the organization's process property information on previous similar projects.

Answer : You are using an organizational process assets to determine the cost of all the risks events thecurrent project.

The organization is a project that is expected to last for 20 months, but the customer would really like the project will be completed in 18 months. You worked on similar projects in the past and I believe that you could fast track the project and achieve the 18-month period. What grows when a fast-track project?


Options are :

  • resources
  • communication
  • risks
  • costs
  • None

Answer : risks

You are the project manager GHQ project for your company. You work in a project team to prepare for you during a qualitative risk analysis. Mary, a project team member, does not understand why you have to meet the qualitative risk analysis. Mary do you explain that a qualitative risk analysis to help determine what may cause a need for additional analysis. There are also some other benefits that qualitative risk analysis can be made of the project. Which of the following is not an achievement during a qualitative risk analysis?


Options are :

  • None
  • The cost impacts of risks if the risk event
  • The corresponding impact on project objectives
  • the risk of the events observed in drawing up based on the probability and impact
  • Schedule risk response

Answer : The cost impacts of risks if the risk event

CAP Certified Authorization Professional Practice Exam Set 4

Which of the following are evidence of data that, when viewed together, a conclusion can be inferred from malicious activity / person?


Options are :

  • None
  • detailed
  • Directly
  • confirmatory
  • Undisputed

Answer : detailed

Project risk management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Check all that apply.


Options are :

  • Risk Management Plan
  • Risk monitoring and control
  • Potential Risk Control Function
  • quantitative risk analysis

Answer : Risk Management Plan Potential Risk Control Function quantitative risk analysis

You work as a project manager BLUEWELL Inc. Management has asked you to work with key stakeholders in the project to analyze project risk events you've specified. They would like you to analyze project risks, which aim to improve the performance of the project as a whole. What approach can be used to achieve the aim of improving the performance of the project with a risk analysis of the project stakeholders?


Options are :

  • Linked to experts on the subject of risk analysis activities
  • Use qualitative risk analysis to quickly assess the probability and impact of risk events
  • None
  • Take stakeholders to identify risks only at the stage in which they project directlyaffects
  • Focus on high-priority risks a qualitative risk analysis

Answer : Focus on high-priority risks a qualitative risk analysis

You GGG project manager for the project. You have completed the risk identification process in the early stages of the project. When you start to document your risk events in the risk register what additional information you can attach a recognized risk events?


Options are :

  • risk schedule
  • The risk of potential answers
  • None
  • the risk of the owner
  • the cost of risk

Answer : The risk of potential answers

Which of the following steps DITSCAP C & A process is used to define the C & stress levels to identify the main C & roles and responsibilities, as well as to create a method for implementing the safety requirements of the contract?


Options are :

  • step 2
  • step 3
  • Phase 1
  • step 4
  • None

Answer : Phase 1

What steps can be taken to a party where current negotiations fail and no agreement is reached?


Options are :

  • Zopa
  • BATNA
  • PON
  • None
  • Bias

Answer : BATNA

CAP Certified Authorization Professional Practice Exam Set 6

You are the project manager construction project. The project includes work that requires great financial risks. You decide to insure processes in such a way that all the sick can happen becompensated. What type of strategies have you used to deal with the risks involved in such work?


Options are :

  • Avoid
  • Transfer
  • Accept
  • None
  • mitigate

Answer : Transfer

Which of the following governance bodies provides management, operational and technical controls to meet the safety requirements?


Options are :

  • Business Unit Director
  • None
  • security chief
  • Senior management
  • security Management Team

Answer : Senior management

Sam is a construction project manager in South Florida. This area is prone to hurricanes in the United States during certain times of the year. As part of the project plan and project team Sam recognizes the opportunity to hurricanes and hurricane damage could be project deliverables, schedule of the project, and the entire cost of the project. When Sam and project stakeholders acknowledge the risk of a hurricane they go into the design of the project if the risk is not likely to happen. What kind of risks Sam response to use?


Options are :

  • Avoidance
  • passive acceptance
  • mitigation
  • None
  • active approval

Answer : passive acceptance

a member of the project team has just identified a new risk project. The risk of an event is determined to be a significant impact, but unlikely project. If the risk of an event to happen, it will cause a project is delayed by three weeks, resulting in new risks for the project. What should I do with project risk event?


Options are :

  • None
  • More questions identified in the risk log.
  • More risk identified in a risk register.
  • Add an identified risk of low-level risk monitoring list
  • Add an identified risk of the quality management system control card.

Answer : More risk identified in a risk register.

Comment / Suggestion Section
Point our Mistakes and Post Your Suggestions