Practice Tests for Scrum Master Certification Assessments Set 10

Formal events reduce the need for any other meetings in Scrum. TRUE or FALSE?


Options are :

  • TRUE
  • FALSE

Answer : TRUE

The increment must be released to the production at the end of every hardening Sprint. TRUE or FALSE


Options are :

  • TRUE
  • FALSE

Answer : FALSE

When will the Sprint Goal be created?


Options are :

  • During the Sprint Planning
  • During the backlog refinement
  • Either during the backlog refinement or during the Sprint Planning
  • During Sprint Review

Answer : During the Sprint Planning

Product Owner tracks the total projected work remaining in the product. When will this happen?


Options are :

  • At least at the end of every Sprint Planning.
  • At least during backlog refinement.
  • At least every Sprint Review.
  • At least when new items are added to the Product Backlog.

Answer : At least every Sprint Review.

Scrum Master Certification Prep - Questions Set 7

If the organisation has a Definition of Done which should be followed by all product teams as it is. TRUE or FALSE?


Options are :

  • FALSE
  • TRUE

Answer : FALSE

A Sprint burn-down chart shows the amount of work that the team should complete every day. TRUE or FALSE


Options are :

  • TRUE
  • FALSE

Answer : FALSE

What are the questions that Scrum Master should ask during Daily Scrum?


Options are :

  • Scrum Master should explain the plan for next 24 hours.
  • Scrum Master is not a participant in Daily Scrum. But should make sure that the Development Team conduct the Daily Scrum.
  • Scrum Master should enquire and collect the remaining work for each member.
  • What did you do yesterday to meet the Sprint Goal? What will you do today? Do you see any impediment?

Answer : Scrum Master is not a participant in Daily Scrum. But should make sure that the Development Team conduct the Daily Scrum.

A distributed team is running one-month Sprints. In the middle of the Sprint a team member raised a concern over the quality of a communication tool that they are using. What should be an appropriate action?


Options are :

  • Coach the team that Agile value individuals and interactions over processes and tools.
  • This has nothing to do with the product increment, ignore.
  • Park the issue for the next retrospective.
  • Coordinate with the vendor to fix the issue.

Answer : Coordinate with the vendor to fix the issue.

The Sprint Backlog is the set of Product Backlog Items selected for the Sprint, plus a plan for delivering the product Increment and realizing the Sprint Goal. Who will be creating this plan?


Options are :

  • Scrum Team
  • Development Team
  • Product Owner
  • Scrum Master

Answer : Development Team

Which of the following is not mandated by the Scrum?


Options are :

  • Velocity chart
  • Sprint backlog
  • Product Backlog
  • None of these are mandated.

Answer : Velocity chart

Scrum Master Certification Prep - Questions Set 8

How can the management help Scrum Team?


Options are :

  • Support the Scrum Team on their way to excel as a self-organising self-managed team.
  • Monitor the Development Team progress and alert them.
  • Review the Sprint backlog and suggest changes.
  • Provide the release plan.

Answer : Support the Scrum Team on their way to excel as a self-organising self-managed team.

The Organisation has decided to change its business priorities. This will stop funding for the project. The CEO has called up the Scrum Master ask him to stop the work on the project. What should the immediate action?


Options are :

  • Inform the Product Owner and follow his/her decision.
  • Disperse the team.
  • Request the CEO for more time.
  • Inform the Development Team to stop the work.

Answer : Inform the Product Owner and follow his/her decision.

Which is the prescribed event used only for package software development?


Options are :

  • Sprint Review
  • All events are mandatory for all kind of project.
  • Sprint Planning
  • Daily Scrum
  • Sprint Retrospective

Answer : All events are mandatory for all kind of project.

What are the benefits of continuous integration? Select two


Options are :

  • A working build is guaranteed all the times
  • Code become more readable
  • Code become more reusable
  • Integration issues detected early

Answer : A working build is guaranteed all the times Integration issues detected early

Customer organisation is conducting a meeting to introduce a new process in their organisation which will be in effect from next calendar year. The Scrum Team is developing a software which will automate a part of this process. Who should represent the Scrum Team in this meeting?


Options are :

  • Scrum Master
  • Product Owner
  • Any one from Scrum Team
  • Development Team

Answer : Product Owner

What is Sprint Review? select the best answer


Options are :

  • Scrum Team and stakeholders inspect the Increment coming out of the Sprint and decides what to do in the upcoming Sprint.
  • Reviews the planning efficiency of the Scrum Team.
  • Reviews how the work was carried out during the Sprint and find areas of improvement.
  • Scrum Team and stakeholders inspect the Increment coming out of the Sprint and create a Sprint Goal for upcoming Sprint.

Answer : Scrum Team and stakeholders inspect the Increment coming out of the Sprint and decides what to do in the upcoming Sprint.

Quick Practice Tests for Scrum Master Certifications Set 8

The Product Owner is responsible to make sure that the Development Team select enough number of items based on their capacity. TRUE or FALSE


Options are :

  • FALSE
  • TRUE

Answer : FALSE

Is it a good idea to conduct Sprint Review for current Sprint during next Sprint?


Options are :

  • No
  • Yes

Answer : No

Why should the Product Owner be a participant in Daily Scrum?


Options are :

  • To collect the status towards achieving the Sprint Goal.
  • He/she is not a participant in Daily Scrum.
  • He represents the stakeholders in Daily Scrum.
  • As Scrum Master is not mandatory participant Product Owner facilitate the event.

Answer : He/she is not a participant in Daily Scrum.

Which is not a topic for Sprint Retrospective?


Options are :

  • Sprint Goal for next Sprint
  • Definition of Done
  • Issues with the tools used
  • The way the team do their work

Answer : Sprint Goal for next Sprint

Development Team follows certain ground rules for performing and updating work within the Sprint. Who is responsible for maintaining these rules?


Options are :

  • Product Owner
  • Scrum Master
  • Development Team
  • Scrum Team

Answer : Development Team

A key stakeholder requests the Scrum Master to add a new feature in the current Sprint. It is of high importance for the business. What should be the best action?


Options are :

  • Address it to the Development Team to take a decision and facilitate the decision.
  • Add to the Product Backlog as the Sprint has already started.
  • Reject the request as it was not part of original scope.
  • Direct the request to the Product Owner. So that he/she can work with the stake holder.

Answer : Direct the request to the Product Owner. So that he/she can work with the stake holder.

Quick Practice Tests for Scrum Master Certifications Set 4

In empiricism decisions are made based on:


Options are :

  • What is known.
  • What is predicted.
  • Risk and Complexity
  • Assumptions

Answer : What is known.

Which statement is NOT TRUE about Scrum?


Options are :

  • High alignment of IT and Business
  • Self-Managed, Cross Functional teams
  • Predictive rather than adaptive planning
  • Iterations or Sprints of max 1 month

Answer : Predictive rather than adaptive planning

When will the sole owner for selected a Backlog Item assigned?


Options are :

  • Never
  • At Sprint Planning.
  • It is a pull system. When a Development Team member start working on it he/she becomes the sole owner of that item.
  • Assignment will be decided during the refinement and ownership start when Sprint begins.

Answer : Never

What should we do if we are not able to finish Sprint scope? Select all that apply in this scenario.


Options are :

  • All items will be moved to next Sprint.
  • Items that are not done or not useable as it is, will be re-estimated and move back to the Product Backlog
  • The done items will be reviewed and if they are usable & potentially shippable the Product Owner accepts it.
  • Done items will be accepted and others will be moved to next Sprint.

Answer : Items that are not done or not useable as it is, will be re-estimated and move back to the Product Backlog The done items will be reviewed and if they are usable & potentially shippable the Product Owner accepts it.

An adjustment must be made as soon as possible to minimize further deviation. What does this refer to?


Options are :

  • Adaptation
  • Transparency
  • Focus
  • Courage

Answer : Adaptation

The Product Backlog is an ordered list of everything that is known to be needed in the product. It is the single source of requirements for any changes to be made to the product. The Product Owner is responsible for the Product Backlog, including its content, availability, and ordering. Who is responsible for estimating Product Backlog Items?


Options are :

  • Development Team
  • Product Owner
  • Scrum Master
  • Scrum Team

Answer : Development Team

Practice Tests for Scrum Master Certification Assessments Set 10

A Development Team member resigns from the organisation and replaced by a new member. What should we expect as an impact on the productivity?


Options are :

  • Increase as we have a fresh perspective.
  • Increase Temporarily
  • Reduce Temporarily
  • No change as capacity remains the same.

Answer : Reduce Temporarily

The Development Team is facing an issue with a new webservice interface which needs their collective effort. Who should coordinate the resolution?


Options are :

  • The Development Team themselves.
  • The Scrum Master as he/she is the facilitator.
  • The Product Owner as the requirement owner.
  • The architect as it is technical issue.

Answer : The Development Team themselves.